Battery Test Report for Engineers

A battery discharge test was conducted on a 100Ah battery at the B R Power Gen site on October 19th, 2022. The test recorded the current, battery group voltage, and individual cell voltages every 30 minutes from 18:00 to 18:20 as the battery discharged under a load. The remarks note that the battery being tested only had four cells.

Uploaded by

hhelectronicsbd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
241 views1 page

Battery Test Report for Engineers

A battery discharge test was conducted on a 100Ah battery at the B R Power Gen site on October 19th, 2022. The test recorded the current, battery group voltage, and individual cell voltages every 30 minutes from 18:00 to 18:20 as the battery discharged under a load. The remarks note that the battery being tested only had four cells.

Uploaded by

hhelectronicsbd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Battery Discharge Test

Site name B R Power Gen Site ID 2 Tested by Mirsarsai


Inspect Date 19-Oct-22 Indoor/Outdoor Indoor Bat. Capacity 100Ah
Start Time 18.00 End Time 18.20

Time Power on Power off 0:30 1:00 1:30 2:00 2:30 3:00 3:30 4:00

Clock Time 20.05 20.10 20.40 21.10 21.20

Current(A) 20.1 22.5 21.00 22.8 21.20

Battery group
52.8 49.8 47.1 46.4 45.8
voltage(V)
Cell 1 13.2 12.0 11.7 11.5 11.4

Cell 2 13.2 11.9 11.8 11.6 11.4

Cell 3 13.2 11.9 11.8 11.6 11.5

Cell 4 13.2 11.9 11.8 11.6 11.4

Cell 5

Cell 6

Cell 7

Cell 8

Remarks
Existing only four batteries