1 AUDIT ANALYSIS
6.1 ORGANIZATION LEVEL ANALYSIS
Audit Analysis is performed as an annual exercise to identify the top strengths and areas of
weaknesses. The same is analyzed and reviewed with the Leadership team to arrive at
recommendations and future improvement action items to avoid the recurrence of similar findings
going forward.
The types of audits considered for analysis are as below:
PQI: This is quarterly audit performed by QA team for engineering projects to check
compliance to QMS by arriving at Process Quality Index score.
CMMI Internal Review: This audit is performed on need basis to review the compliance of
engineering projects to CMMI requirements. In many occasions, this audit will be clubbed
with PQI audit for projects undergoing both audits the same time. This is performed by
SEPG/QA team.
QMS Audits: This audit is a quarterly audit to ensure compliance of engineering project
teams as well as support functions (HR, IT, SCM, Facility Admin, Management, QA, MR) to
AS9100 Standard requirements and TIDC QMS.
In process audit and technical reviews are being conducted by Quality personnel regularly
based on project specific plans and as per customer requirements, which helps to improve
the weak areas to great extent in the Engineering Practice Area such as VV, TS, RDM, PR, PI.
ORG Audit Status
47.5
42.5
37.5
32.5
27.5
22.5
4
Findings
17.5
12.5
7.5
2.5
PQI Audits - 3 QMS+CMMI Audits - 12
OI 10 34
O+ 9 65
NC 4 21
6.2 PROJECT/FUNCTION LEVEL ANALYSIS
Product Engineering
16
Findings
4
2
OI O+ NC
Software Engineering
15
11
Findings
OI O+ NC
CMC
6
4
Findings
OI O+ NC
EME
11
Findings
1
0
OI O+ NC
DDC
4
Findings
0
OI O+ NC
Technical Publications
26
Findings
13
OI O+ NC
Support Department
28
16
Findings
Series1; 6
OI O+ NC
Process Area vs Observations
14 100.00%
90.00%
12 2
80.00%
10 70.00% NC
8 2 60.00% OI
5 50.00% Cumm %
6 11 3 40.00%
4 3 4 1 30.00%
7 5
1 20.00%
2 4 4 3 4 3 1 1 1
2 2 10.00%
0 1 1 1 1 1 0.00%
OT MPM CM PLN RSK PCMM&CSAM EST PR II RDMPAD DAR TS PI VV CAR
Based on the above Pareto Chart, below are the top weak practice areas:
Organization Training (OT)
Managing Performance & Measurement (MPM)
Configuration Management (CM)
Positive Observations
14 100.00%
12 90.00%
80.00%
10 70.00%
8 60.00% O+
13 50.00% Cumm %
6 11 40.00%
4 9 9 8 30.00%
5 20.00%
2 3 3 3 3 10.00%
2 2 2 1
0 0 0 0 0 0.00%
II T OT TS PI
N
PL SAM MPM &C RSK DM ES PQA PCM PR P AD CA
R VV DA
R
M R
Based on the above Pareto Chart, below are the top strengths and practice areas:
Planning (PLAN)
Supplier Agreement Management (MPM)
Managing Performance & Measurement (MPM)
.