Implementation Plan
Implementation Plan
JUNE
% OF
SEPT
JULY
NOV
AUG
PERSONS INVOLVED OUTPUT REMARKS
OCT
DEC
SEF MOOE TOTAL
PAGBASA COMPLETION
1. Administration of the Phil 5000 5000 Principal, Phil IRI Result 100 Completed
IRI Class Advisers,
Master Teachers
2. Consolidation and English Coordinator Consolidated 100 Completed
Submission of the Results by Grade Level, Results
Master Teacher
3. Evaluate and Analyze the School English List of Non 100 Completed
Results Coordinator Readers
4. Conduct Survey CI Team Survey Forms 100 Completed
5. Prepare the Project Project Coordinator Project 100 Completed
Proposal, Project Charter, Proposal
Implementation Plan
6. Presentation of Proposal, Principal, Project 100 Completed
Teachers, Pupils English Team Launching
7. Prepare Logistics Principal, Class 100 Completed
CI Team Organization,
Class Schedule,
Classroom
8. Validation and Finalization Principal, Memorandum, 100 Completed
of the List of Non Readers English Coordinator Program of
Activities
9. Prepare Reading Materials 5000 5000 Principal, Big Books, 100 Completed
CI Team Developing
Reading Power
10. Preparation of 5000 5000 Principal, Manila Paper, 100 Completed
Instructional Materials CI Team Pentel Pen,
Ink, Fuller’s
Manual
11. Pilot/ CI Team and Monitoring 50 On Going
Implementation/ Conduct Implementers and Evaluation
Activities Based on the Result and
Plan Merit System
12. Monitor the Progress Principal, Monitoring 50 On Going
CI Team Tools
13. Roll Out CI Team Minutes/ 50 On Going
Pictorial/
Narrative
14. Prepare CI Team and Stakeholders, 50 On going
Documentation Implementers Analysis,
Communicatio
n Strategies,
and Risk
Assessment
15. Conduct Post Test CI Team and Result of Phil - -
Implementers IRI
TOTAL 0 15 000 15 000