We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
F
Substation Configurations
In each of the four figures in this appendix, the bus work or node is
depicted as a solid line. The squares represent circuit breakers that open the
electrical circuit under load or short-circuit conditions. The switches, which
have limited ability to interrupt current, serve to isolate components and bus
sections.
MAIN AND TRANSFER BUS CONFIGURATION
A main and transfer bus configuration consists of two independent buses,
one of which, the main bus, is normally energized, Under normal operating
conditions, all incoming and outgoing circuits are fed from the main bus
through their associated circuit breakers and switches. If it becomes
necessary to remove a circuit breaker from service for maintenance or
repairs, circuit operation can be maintained through use of the isolating
switches and bus transfer equipment. The circuit breaker to be maintained
and its switches are opened, the bus transfer switches are closed, the switch
from the transfer bus to the circuit is closed, and then the bus transfer
breaker is closed to re-energize the circuit. The circuit is then protected by
the bus transfer breaker. Figure F.1 shows the typical configuration of a
main and transfer bus scheme.
The main advantages of this scheme include:
+ Accommodation of circuit breaker maintenance while maintaining
service and line protection;
+ Low cost—essentially one breaker per line or transformer;
+ Fairly small land area; and+ Easily expandable.
‘The primary disadvantages of this scheme include the following:
+ Failure of a circuit breaker or a bus fault causes loss of the entire bus
with outage of all circuits.
+ An additional circuit breaker is required for bus tie.
+ Since the bus tie breaker has to be able to be substituted for any line
breaker, its associated relaying may be complicated.
+ Complicated switching is required to remove a circuit breaker from
service for maintenance.
The main and transfer bus scheme, which has the potential for a major
outage of all circuits, is mainly used in older stations, most often at voltages
of 230 kV and below. For large stations, the bus may be broken into two or
three sections, with bus-sectionalizing circuit breakers. A bus fault or
breaker failure then affects only one section of bus, with the opening of the
sectionalizing breakers preventing outages on other bus sections. It is
important to distribute circuits onto bus sections in a balanced way, so that
sufficient transmission network conductivity remains with a bus section
outage.
TRASNSFER an
oe
FIGURE F.1 One-line diagram of main and transfer bus scheme. In normal
operation, the main bus is energized and the transfer bus is de-energized. In
the bottom bay, the breaker and switches are open. In the top three bays, the
switches on the left are open with the breakers and other switches closed.
BREAKER-AND-A-HALF CONFIGURATIONThe breaker-and-a-half configuration, typically used at extra-high-
voltage (EHV) stations, consists of two buses, each normally energized.
Electrically connected between the buses are three circuit breakers and,
between each two breakers, a circuit, as shown in Figure F.2. In this
arrangement, three circuit breakers are used in a bay for two independent
circuits; hence, each circuit shares the common center circuit breaker, so
there are 1.5 circuit breakers per circuit. The breaker-and-a-half
configuration provides for circuit breaker maintenance, since any breaker
can be removed from service and isolated without interrupting any circuit.
Additionally, faults on either of the main buses cause no circuit
interruptions. Failure of a circuit breaker results in the loss of two circuits if
a common breaker fails and only one circuit if an outside breaker fails. It is
important to balance circuits in the bays, for example, source lines coming
into the right-hand side of bays and load lines leaving the left-hand side of
bays.
The main advantages of this scheme include the following:
+ A bus fault does not interrupt service on any circuit, and circuit breaker
failure causes loss of only one or two circuits;
+ Flexible operation;
+ High reliability; and
+ Double feed to each circuit.
‘The primary disadvantages of this scheme include the following:
+ One-and-a-half breakers are required per circuit;
+ Relaying is complex, since the center breaker has to respond to faults of
either of its associated circuits, and since currents from two sources
must be measured for all circuits; and
+ Each circuit must have its own potential source for relaying.fe ey 1
fe ped |
a
ake aly
- *
FIGURE F.2 One-line diagram of breaker-and-a-half bus configuration.
eg Oe
FIGURE F.3 One-line diagram for ring bus configuration.
RING BUS CONFIGURATION
For stations having three to five circuits, a ring bus is often used. As
more circuits are added, the configuration may evolve to a breaker-and-a-
half arrangement. Figure F.3 shows a three-circuit ring bus that is based on
Figure F.2 but with the bottom bay and three breakers and one bay-two
circuit removed. A maintenance outage of a circuit breaker or circuit causes
an “Open ring.” For open-ring operation, a subsequent circuit outage may
cause outage of additional circuits.
The advantages of this scheme include:
+ Low cost—only one circuit breaker per circuit; and
+ Flexibility to evolve to a breaker-and-a-half arrangements as more
circuits are added.The disadvantages of this scheme include:
+ Reduced reliability in open-ring operation; and
+ Temptation to add circuits without evolution to a breaker-and-a-half
arrangement.
DOUBLE BREAKER-DOUBLE BUS CONFIGURATION
The double breaker-double bus configuration consists of two main buses,
each normally energized. Electrically connected between the buses are two
circuit breakers and, between the breakers, one circuit, as shown in Figure
F.4, Two circuit breakers are required for each circuit.
In the double breaker-double bus configuration, any circuit breaker can
be removed from service without interruption of any circuits. Faults on
either of the main buses cause no circuit interruptions. Circuit breaker
failure results in the loss of only one circuit.
Because of high cost, the double breaker-double bus configuration is
usually limited to large generating stations. The additional reliability
afforded by this arrangement over the breaker-and-a-half scheme usually
cannot be justified for conventional transmission or distribution substations.
Occasionally, at a generating station, one bay of a breaker-and-a-half
arrangement is used as a double breaker-double bus arrangement for a
generator terminal to provide equal access to either main bus.
dt
FIGURE F.4 One-line diagram of double breaker-double bus configuration.
The main advantages of this scheme include:+ Flexible operation,
* Very high reliability,
+ Isolation of either main bus for maintenance without disrupting service,
+ Isolation of any circuit breaker for maintenance without disrupting
service,
+ Double feed to each circuit,
+ No interruption of service to any circuits from bus fault,
+ Loss of only one circuit for breaker failure, and
+ All switching with circuit breakers.
The primary disadvantage of this scheme is high cost because two circuit
breakers are required for each circuit.