0% found this document useful (0 votes)
54 views1 page

NDLS Costing

The document outlines additional costs for the Konnectus Tower project as per DMRC norms, totaling ₹ 960,000. It includes expenses for bus ducts, MCCBs, bus bars, and earthing provisions. Each item is detailed with its respective cost, highlighting necessary upgrades to electrical components.

Uploaded by

VIMLESH YADAV
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views1 page

NDLS Costing

The document outlines additional costs for the Konnectus Tower project as per DMRC norms, totaling ₹ 960,000. It includes expenses for bus ducts, MCCBs, bus bars, and earthing provisions. Each item is detailed with its respective cost, highlighting necessary upgrades to electrical components.

Uploaded by

VIMLESH YADAV
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Konnectus Tower - NDLS

MAAC Infra NDLS Additional Cost as Per DMRC Norms

Descriptions Amount

1.Bus duct 1200amp copper ip 54 ,4 conductor duly tin plated for entire length in all
directions having termination provision on main electrical panel and new panel.Also
having provision of bends and termination as per site requirements.
₹ 325,000.00

2. 4pole 1000amp 65ka MCCB in place of 1000 3pole 50 ka microprocessor bases to


integrate with existing outgoing feeders ₹ 256,000.00

3.outgoing MCCB also 4pole microprocessor based in place of thermal 3pole. ₹ 38,000.00

4.The bus bar if electrical panel changed from Aluminium to Tinned Copper ₹ 270,000.00

5.additional Copper earthing of main panel and new panel. ₹ 71,000.00

Total ₹ 960,000.00