Module Assessment 11
points: 10
time: 30 mins
Started on Saturday, 4 October 2025, 10:22 AM
State Finished
Completed on Saturday, 4 October 2025, 10:26 AM
Time taken 3 mins 56 secs
Grade 5.00 out of 10.00 (50%)
Grade received: 50 %
To Pass: 50% or higher
Mark 0.00 out of 1.00
Question text
[Link] the managing a stage boundary process, what document is primarily reviewed to confirm the project remains
1 marks
viable?
Question 1 Select one:
Quality register
Stage plan
Project plan
Business case
Feedback
The correct answer is: Business case
Mark 0.00 out of 1.00
Question text
[Link] does the managing a stage boundary process support risk management?
1 marks
Question 2 Select one:
By identifying risks that were not previously acknowledged
By assessing the impact of new risks on the upcoming stage
By confirming that all identified risks have been mitigated
By validating the project’s risk tolerance levels with stakeholders
Feedback
The correct answer is: By assessing the impact of new risks on the upcoming stage
Mark 0.00 out of 1.00
Question text
[Link] terms of decision-making, what authority does the project board have at the end of the managing a stage boundary
process? 1 marks
Question 3 Select one:
To reassign project team members as needed
To approve or reject the next stage plan based on performance data
To alter the project scope based on team feedback
To independently initiate the next stage without further input
Feedback
The correct answer is: To alter the project scope based on team feedback
Mark 1.00 out of 1.00
Question text
[Link] the terms of managing a stage boundary, what does the term "continued business justification" refer to?
1 marks
Question 4 Select one:
Ensuring all stakeholders remain engaged
Confirming that the project products meet quality standards
Validating that the project's expected benefits still outweigh the costs
Establishing the team’s capability for future stages
Feedback
The correct answer is: Validating that the project's expected benefits still outweigh the costs
Mark 1.00 out of 1.00
Question text
[Link] information is essential for the project board during the stage boundary review?
1 marks
Question 5 Select one:
Progress towards achieving project deliverables
A comprehensive report of all team member contributions
A summary of all past project decisions
Detailed technical specifications of the product
Feedback
The correct answer is: Progress towards achieving project deliverables
Mark 0.00 out of 1.00
Question text
[Link] is a critical outcome expected at the end of a stage boundary management process?
1 marks
Question 6 Select one:
The creation of a new communication plan for the next stage
The approval of project deliverables by the end users
The initiation of the next stage without further approvals
The submission of an end-stage report to the project board
Feedback
The correct answer is: The submission of an end-stage report to the project board
Mark 1.00 out of 1.00
Question text
[Link] is the primary objective of the managing a stage boundary process?
1 marks
Question 7 Select one:
To ensure the project board can assess the current stage and approve the next
To evaluate team performance during the project stage
To update the risk register with new insights
To identify resource allocation for the next stage
Feedback
The correct answer is: To ensure the project board can assess the current stage and approve the next
Mark 1.00 out of 1.00
Question text
[Link] activity is performed exclusively in the managing a stage boundary process?
1 marks
Question 8 Select one:
Updating the project risk management plan
Assessing stakeholder satisfaction post-delivery
Preparing a detailed work package for team execution
Reporting stage performance to the project board
Feedback
The correct answer is: Reporting stage performance to the project board
Mark 1.00 out of 1.00
Question text
[Link] aspect is NOT typically addressed during the managing a stage boundary process?
1 marks
Question 9 Select one:
Approving the next stage plan
Reviewing changes to the project baseline
Evaluating the performance of project outputs
Confirming stakeholder engagement strategies
Feedback
The correct answer is: Confirming stakeholder engagement strategies
Mark 0.00 out of 1.00
Question text
[Link] of the following best describes the role of the project manager during the managing a stage boundary process?
1 marks
Question 10 Select one:
To facilitate communication between the project team and the project board
To document every stage activity for future reference
To assess the team's performance in detail
To execute tasks defined in the stage plan
Feedback
The correct answer is: To facilitate communication between the project team and the project board
Finish reviewDownload Review