Professional Documents
Culture Documents
PQR
Well-02
Well-01
STRUCTURAL CORRELATION
Well-01 Well-02
Well-02
Por H*SW
Ave_POR
Water Saturation
Well -01
H Layer-1 Layer-2 Layer-3 Layer-4 0.00 35.50 0.00 2.65 SW 0.00 0.37 0.00 0.59 H*SW 0.00 13.26 0.00 1.56 H 2.89 53.61 9.53 4.50
Well-02
SW 0.62 0.48 0.57 0.62 H*SW 1.78 25.71 5.44 2.79
Ave_SW
Well-02
NTG 0.18 0.77 0.39 0.06 H*SW 2.89 53.61 9.53 4.50
Ave_NTG
Well-02
Well-01
Well-02
Well-01
C apillary P ressure,ps
100.0 90.0 80.0 70.0 60.0 50.0 40.0 30.0 20.0 10.0 0.0 0 0.1 0.2 0.3 0.4
0.5
0.6
0.7
0.8
0.9
Gas-Oil Rel-Permeability
1.00 0.90 0.80 Rel-Perm, Krog, Krg 0.70 0.60 0.50 0.40 0.30 0.20 0.10 0.00 0.00
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
Oil-Water Rel-Permeability
1.00 0.90 0.80 0.70 0.60 0.50 0.40 0.30 0.20 0.10 0.00 0.00
Krw @ Core 107 Krow@ Core 107 Krw @Core 127 Krow @ Core 127 Krw @ Core 130 Krow @ Core 128 Krow @ Core 130 Krw @ Core128
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
Wa t e r S a t ur a t i on, Fr a c t i on
Hydrogen Sulfide Carbon Dioxide Nitrogen Methane Ethane Propane Iso-Butane N-Butane Iso-Pentane N-Pentane Hexanes Heptanes Octanes Nonanes Decanes Undecanes plus Total ......
0.00 0.17 0.02 5.83 3.08 6.95 3.00 5.15 4.09 4.00 7.77 11.66 11.58 6.11 4.47 26.12 100.00
0.00 0.06 0.00 0.73 0.72 2.39 1.36 2.33 2.30 2.25 5.08 8.23 9.26 5.53 4.60 55.16 100.00
Component
Mol %
GPM
Hydrogen Sulfide Carbon Dioxide Nitrogen Methane Ethane Propane iso-Butane n-Butane iso-Pentane n-Pentane Hexanes Heptanes Octanes Nonanes Decanes Undecanes plus Total ......
0.00 1.07 0.75 77.48 8.64 7.34 1.49 1.81 0.56 0.39 0.26 0.15 0.05 0.01 0.00 0.00 100.00
2.310 2.022 0.488 0.570 0.204 0.142 0.108 0.054 0.020 0.004 0.000 0.000 5.922
Gas Gravity
(air = 1.000)
0.759
1292.7
VOLUMETRIC DATA (at 176 F) Saturation Pressure (Psat) ......................... 1870 psig Density at Psat .............................................. 0.6503 gm/cc Thermal Exp @ 5000 psig .......................... 1.07295 V at 176 F / V at 60 F
Pressure Range
psig
Single-Phase Compressibility
v/v/psi
to to to to
DIFFERENTIAL VAPORIZATION
ADJUSTED TO SEPARATOR CONDITIONS*
Solution Gas/Oil Ratio
Rs (A)
Kodeco Energy Company Ltd.
KE-30-1
JFL 2001094
Pressure
psig
Differential Vaporization
Oil Density
gm/cc
1 .7
Differential Vaporization Separator Test, 350 psig at 90 F Separator Test, 250 psig at 90 F Separator Test, 150 psig at 90 F Separator Test, 50 psig at 90 F
5000 4500 4000 3500 3000 2500 2200 2100 2000 1900 1870 1600 1400 1200 1000 800 600 400 200 109 0
836 836 836 836 836 836 836 836 836 836 836 723 643 567 494 423 354 283 201 148
1.435 1.443 1.452 1.462 1.472 1.484 1.492 1.495 1.498 1.500 1.501 1.446 1.408 1.371 1.336 1.303 1.269 1.234 1.187 1.153
0.6805 0.6767 0.6725 0.6680 0.6631 0.6578 0.6543 0.6532 0.6519 0.6507 0.6503 0.6627 0.6715 0.6800 0.6883 0.6965 0.7050 0.7141 0.7254 0.7326 0.7598
1 .6
1 .5
1 .4
1 .3
1 .2
1 .1
Figure D-2
Pre ssure
VS
(psig)
RIES
Oil Viscosity
cp
Gas Viscosity
cp
1 .20
5000 4500 4000 3500 3000 2500 2200 2100 2000 1900 Pb1870 1600 1400 1200 1000 800 600 400 200 109 0
0.346 0.335 0.323 0.312 0.300 0.289 0.282 0.279 0.277 0.275 0.274 0.304 0.327 0.351 0.375 0.402 0.431 0.467 0.520 0.564 1.00
1 .00
0.80
0.60
0.40
Pressure , psig
0.035
0.025
0.01 5
Figure C-1
Pressure
VS
(psig)
RIES
DST-SUMMARY
Well-01 Well-02
HYDROCARBON DISTRIBUTION
Well-01 Well-02
GIIP 18.9 BCF (FREE-GAS) 19.5 BCF (SOL. GAS) EUR : 13.0 BCF
DEVELOPMENT SCENARIOS
TOTAL
2,950
13,045
COMPLETION
Artificial Lift Completion will be installed immediately. Select In-situ/Auto Gas lift Completion.
PQR POD Completion Proposal In-Situ/Auto Gas Lift Selection Completion cost considerations (compare with conventional Gas Lift and ESP) Utilize Kujung I gas for gas lift supply to optimize production. Minimize the use of the gas as minimum as possible. Minimize workover for future completion. Minimize wireline works for high angle well.
Permeabilty : 3.3 mD
Kujung I ( Oil Zone) DST Result : Perforation Intervals : 4326' - 4348' / 22 ft (MD/TVD) Chk Size 32/64" FTP, psi 500 BOPD 1740 MMSCF/D 0.62 BWPD 2 Test Duration, hrs 12 hrs Res. Press : 1870 psi Remark No acid
Total Skin : 42
Permeabilty : 191 mD
40 ft
Gas
80 ft
Oil
64 degree
50 ft
Water
Gas
40 ft
80 ft
Oil
50 ft
Water
Oil intervals
COMPLETION COST
ITEM ESP US $ 50,000 64,000 60,000 16,000 46,000 SM ART COM PLETION US $ 50,000 64,000
Tubing $ 8.0/ ft Eqpt Surface-Wellhead Electric Submersible Pump Electric Cable Pack er/ SSD/Downhole Safety Eqp. Bottom pack er Hydrow II Dual Pack er Remotely Operated SSD Dual Hydraulic line Downhole safety valve Misc.
Total
236,000
234,000
420,000.00
390,000.00
406,000.00
445,000.00
390,000.00
Oil production reduce Require wireline work to 3 wells in the future works
More expensive but Oil production only from easy to operate 3 wells only
PROJECT
PQR DEVELOPMENT
INTRODUCTION : INSTALL 4 PILE PLATFORM TO ACCOMMODATE MAX. 7 WELLS AND TIE IN TO AW PLATFORM VIA 10 x 25 KM SUBSEA PIPELINE
EQUIPMENT TO BE INSTALLED :
PRODUCTION AND TEST MANIFOLD CRANE WHCP (WELLHEAD CONTROL PANEL) SCADA SYSTEM CHEMICAL INJECTION PRODUCTION SEPARATOR WITH LIQUID AND GAS METERING FOR ALLOCATION MULTI PHASE FLOW METER
PROJECT ACTIVITIES: REVISION OF AMDAL STUDY (RKL / RPL) FEED STUDY PROCUREMENT OF LONG LEAD ITEM PREPARE EPC BID PACKAGE ISSUE TENDER PROCUREMENT AND FABRICATION ISSUE TENDER INSTALLATION FABRICATION OF PLATFORM AND PRODUCTION FACILITIES INSTALLATION OF PLATFORM, PRODUCTION FACILITY AND PIPELINE TIE IN / HOOK UP AT AW PLATFORM COMMISSIONING AND START UP
PROJECT COST :
PQR FOUR PILE PLATFORM Deck & Substructure Engineering, Procurement & Fabrication Installation of Platform Facilities Hook Up PIPELINES 10 inch x 25 Km : PQR to Poleng MISCELLANEOUS Engineering, Certification & QA / QC Project Management US$8,650
US$3,600 US$1,250
TOTAL
US$13,500
ECONOMICS
1. Economical Aspects
1. The estimated total cost, including three (3) producing wells in 2004 and two (2) wells in 2005, is 27.352 MMUS$.
2. PQR Field is capable of production 2.950 MMSTB of oil production and 10.366 BCF of gas production in Kujung I formation by the end of year 2011 with five (5) producing wells.
3. Oil price was assumed U$$ 22.00 per barrel and gas price of US$ 3.0 per MMBTU.
4. The PQR operating cost is 13.954 MMUS$, which is calculated as the fractional portion of PQR production against the total operating cost of both West Madura and Poleng.
Deck & Substructure eng., Procurement, & Fabrication Installation of Platform Facilities Hook-up 3,600
1,250
13,852
TOTAL
27,352
3. Economic Summary
Gross Production Oil Price Gross Revenue Operation Costs Capital Expenditure Total Cost Recovery Contractor NPV (10% D.C.) Payout Time Contractor IRR Pertamina NPV (10% D.C.) Indonesia NPV (10% D.C.) Mbbls US$/bbl MUS$ MUS$ MUS$ MUS$ MUS$ Years % MUS$ MUS$ 2,950 22 96,121 13,954 27,352 48,252 3,669 4.5 26.6 6,933 19,289
4. Sensitivity Analysis
KE-30 Field Development PQR FIELD DEVELOPMENT Sensitivity to Contractor NPV SENSITIVITY TO CONTRACTOR NPV
7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4
45.0 40.0 35.0 30.0 25.0 20.0 15.0 10.0 5.0 0.0 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4
KE-30 Field Development PQR FIELD DEVELOPMENT Sensitivity TOContractor IRR IRR SENSITIVITY to CONTRACTOR
SENSITIVITY FACTOR
CAPEX Production
IRR ( % )
KE-30 Field Development PQR FIELD DEVELOPMENT Sensitivity toTO PARTNER NPV SENSITIVITY Pertamina NPV
13.0 12.0 11.0 10.0 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4
KE-30 Field DEVELOPMENT PQR FIELD Development Sensitivity to Government NPV NPV SENSITIVITY TO GOVERNMENT
40.0 35.0
SENSITIVITY FACTOR
CAPEX Production
SENSITIVITY FACTOR
CAPEX Production