Cost Estimating
WSDOT Unit Bid Analysis
Outline
Construction organizations (review) Construction contracts (review) Contract documents
Unit prices
Standard specifications Standard specifications for DOTs Unit bid items WSDOT Unit bid items Short in-class exercise
Construction Organizations
Construction Using Owner Forces
Owner
Owner-Managed Construction
Owner
Construction Staff
Construction Staff
Project Director
Project Director
Construction Forces 3
Hired Forces
Contractors
Construction Organizations
General Contractor
Owner
Design/Build
Owner
Design Firm
Prime Contractor
Design/Build Firm
Subcontractors
Construction Organizations
Construction Management
Owner
Construction Manager
Design Firm
Construction Firms
Construction Contracts
Method of award
Formally advertised contracts Negotiated contracts
Method of pricing
Fixed-price
Lump sum contract Unit price contract
Cost-plus
6
percentage of cost fixed fee fixed fee with a guaranteed maximum cost incentive fee
Contract Documents
General conditions
Defines responsibilities and rights
Supplementary conditions
Types:
Modification of general conditions Additional information beyond general conditions
Contract Documents : What You Might See Standard Specifications Contract Provisions
Plans
Bid proposal forms and regulations Required contract provisions (bond, DBE, etc.) Amendments to the standard specifications Special provisions Wage rate documentation
Standard Specifications
Construction Specifications Institute
MasterFormat 2004 Edition
50 Divisions of construction information Specifications-writing standard for most construction
MasterFormat 2004
Example
32 12 16.13 Plant-Mix Asphalt Paving
32
12 16 13
= Level 1 =
= Level 2 = = Level 3 = = Level 4 =
10
General Requirements Earthwork Production from Quarry and Pit Sites and Stockpiling Bases Surface Treatments and Pavements Structures Drainage Structures, Storm Sewers, Water Mains, and Conduits Miscellaneous Construction Materials
http://www.wsdot.wa.gov/Design/ProjectDev
11
Unit Prices
Standard Units
Defined in Standard Specifications
12
13
Contents Year of expenditure dollars Do not rely on historic records alone Risk and uncertainty Validation
14
Year of expenditure dollars Do not rely on historic records alone Risk and uncertainty Validation
15
16
17
Validation
18
19
Guidance
Includes field investigation, testing, admin, environmental work, preparing plans/specs, ad/bid/award process, etc. Can be estimated as a percentage of construction costs
WSDOT average for all types of projects = 15%
Help
Cost Estimating Manual for WSDOT Projects (July 2009)
http://www.wsdot.wa.gov/Publications/Manuals/M3034.htm Table 3 and related text
21
Guidance
Covers ROW for road, stormwater, wetland mitigation, etc. Costs vary widely depending upon location Partial vs. complete takes Urban Seattle: $20-50/ft2
Help
Real estate experts Zillow (http://www.zillow.com)
22
Guidance
High potential for risk and change Utility adjustments
Located in WSDOT ROW by franchise or permit = utility pays costs Located in WSDOT ROW by easement or outside ROW = WSDOT pays
Railroads
Take a LONG time to negotiate Railroads were generally there first, roads cross by easement
Help
WSDOT Utilities Manual
http://www.wsdot.wa.gov/Publications/Manuals/M22-87.htm Who pays for utility relocation? Section 200.02(2) Railroads: Section 300.02
23
Guidance
Can include items like signal retiming, ITS deployment, staffing at command centers, etc.
Help
ITS Big I optional reading FHWAs Developing and Implementing Transportation Management Plans for Work Zones (chapter 4)
http://ops.fhwa.dot.gov/wz/resources/publications/trans_mgmt_pla ns/trans_mgmt_plans.pdf Laundry list of TDM/TSM items
24
Guidance
Includes profit, costs of labor/materials/equipment, mobilization Estimates are usually:
Bid-based (we will use this one) Cost-based
Help
Historical bid prices: WSDOT Unit Bid Analysis
http://www.wsdot.wa.gov/Design/ProjectDev/EngineeringApplications/UnitBi dHistory.htm
Guidance
Typically calculated as a percentage Typical values are 5-10% but can be higher Type and nature of contract can influence contingency estimate May be higher for time-sensitive projects
Help
WSDOT Plans Preparation Manual (Dec 2009)
http://www.wsdot.wa.gov/Publications/Manuals/M22-31.htm Section 800.03(2) 4% max allowed
26
Guidance
Can be estimated as a percentage Depends on type of job, duration, size, etc.
Help
WSDOT Plans Preparation Manual (Dec 2009)
http://www.wsdot.wa.gov/Publications/Manuals/M22-31.htm Section 800.03(2) 8-20% based on construction cost
27
Guidance
Includes motorist information, advertising, publications, press releases, PR firm, etc.
Help
FHWAs Public Information and Outreach Strategies
http://ops.fhwa.dot.gov/wz/publicinfostrategies.htm Go to the Project-level page (second bullet point link)
28
Guidance
WSDOT Risk Reserve
Base cost (assumes no risk usually at the 40% confidence level) Risk percentage (70% confidence level) for use with approval by Regional Program management risk reserve As risks are retired the risk reserve amount is adjusted
Help
Project Risk Management Guidance for WSDOT Projects (Jul 2010)
http://www.wsdot.wa.gov/publications/fulltext/cevp/ProjectRiskManagement.pdf
29
Risk-Based Estimate
Base cost estimate
Cost that can be reasonably expected if project goes as planned Unbiased and neutral Includes construction contingency Does not include risks
Risk-based estimate
Risk elements applied to base cost and modeled to provide a probable range for cost and schedule
30
31
32
33
Density
Gravel borrow, aggregate, soils: 1.85 tons/yd3 HMA, PCC: 2.05 tons/yd3
Mobilization
5 to 15% of construction cost
Traffic control
5 to 25% of construction cost Urban freeway work costs more (up to 30%)
Right-of-way
Cost is per square foot ($20 to $50/ft2 in urban areas) Administration cost for each take Relocation costs $6/ft2 of roadway surface $10/ft2 of roadway surface in pond area is purchased $150,000/acre or $31/yd2 2% of construction cost
35
Primary References
Nunnally, S.W. (2001). Construction Methods and Management. 5th edition. Prentice Hall, Upper Saddle River, NJ. Construction Specifications Institute (CSI). (2010). CSI website. http://www.csinet.org
Washington State Department of Transportation (WSDOT). (2010). Unit Bid History website. http://www.wsdot.wa.gov/biz/contaa/uba/bid.cfm
WSDOT. (2010). Project Risk Management Guidance for WSDOT Projects. WSDOT, Olympia, WA.
http://www.wsdot.wa.gov/publications/fulltext/cevp/ProjectRiskManagement.pdf
50