Professional Documents
Culture Documents
A. Architect/Civil Engineer
Architect/C
ivil Rate/Sheet
Engineer
1 1,500.00
B. Print
Total No. of Rate for
Sheets Tracing Paper
10 70
C. Bidding
Duration
1 month
D. Manpower Requirement
Man Rate/Sign
Plumber 1 1,500.00
Electrical 1 3,000.00
Structural 1 18,000.00
Sub-Total
E. Permit Process
No. of Copies
Sub-Total
B. Manpower Requirement
Man/days Rate / Day
Laborer 4 395.00
Sub-Total
C. Construction Safety
Sub-Total
TOTAL COST OF ITEM
Item
Work Breakdown Structure
No.
VI EMBANKMENT
Volume (cu.m.)
31.27375
A. Materials Qty. Unit of Issue
Mountain Mixed 31.27375 cu.m.
Gravel Fill 11.527 cu.m.
Sub-Total
B. Equipment Requirement No. of Unit Hourly Rental
Plate Compactor 4 123.00
Sub-Total
C. Manpower Requirement
Skilled: Man/days Rate / Day
Foreman 1 800.00
Operator 4 800.00
Unskilled:
Laborer 9 395.00
Sub-Total
TOTAL COST OF ITEM
DIRECT COST:
INDIRECT COST
Contract Profit 10% of Direct Cost
Overhead Contegencies and Miscellaneous 15% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST:
ADJUSTED TOTAL COST OF ITEM VI
Volume (cu.m.)
2 Beam
5.685
A. Materials Qty. Unit of Issue
Portland Cement 53 bags
Washed Sand 2.8425 cu.m.
Washed Gravel 5.685 cu.m.
10mm.dia. X 6.0m. DRB 129 pcs.
16mm.dia. X 6.0m. DRB 100 pcs.
#16 G.I. Tie Wire 37.56 kgs.
6mm.thk. Ordinary Plywood (Form) 30 sht.
Frame Lumber 751.8 bd.ft.
Assorted nails 58 kls.
Sub-Total
B. Direct labor
Labor 30% of the cost of materials
Sub-Total
TOTAL COST OF ITEM VII
Volume (cu.m.)
3 Concrete Flooring : Ground Floor
9.274
A. Materials Qty. Unit of Issue
Portland Cement 84 bags
Washed Sand 4.637 cu.m.
Washed Gravel 9.274 cu.m.
10mm.dia. X 6.0m. DRB 47 pcs.
#16 G.I. Tie Wire 1.14 kgs.
Sub-Total
B. Direct labor
Labor 30% of the cost of materials
Sub-Total
TOTAL COST OF ITEM VII
Volume (cu.m.)
4 Concrete Flooring : Second Floor
7.576
A. Materials Qty. Unit of Issue
Portland Cement 69 bags
Washed Sand 3.788 cu.m.
Washed Gravel 7.576 cu.m.
10mm.dia. X 6.0m. DRB 116 pcs.
Forms 1135.32 bd.ft.
#16 G.I. Tie Wire 13.18 kgs.
1/2" ordinary plyboard 27 sheets
Assorted nails 5 kgs.
Sub-Total
B. Direct labor
Labor 30% of the cost of materials
Sub-Total
TOTAL COST OF ITEM VII
Volume (cu.m.)
5 Roof Beam
2.844
A. Materials Qty. Unit of Issue
Portland Cement 28 bags
Washed Sand 1.422 cu.m.
Washed Gravel 2.844 cu.m.
10mm.dia. X 6.0m. DRB 68 pcs.
16mm.dia. X 6.0m. DRB 60 pcs.
#16 G.I. Tie Wire 21.28 kgs.
6mm.thk. Ordinary Plywood ( form) 16 sht.
Frame Lumber 400.96 bd.ft.
Assorted nails 50 kgs.
Sub-Total
B. Direct labor
Labor 30% of the cost of materials
Sub-Total
TOTAL COST OF ITEM VII
INDIRECT COST
Contract Profit 10% of Direct Cost
Overhead Contegencies and Miscellaneous 15% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST:
ADJUSTED TOTAL COST OF ITEM
Item No.
Lot
2 Kitchen Counter
1
A. Materials Qty. Unit of Issue
Lump Sum
Sub-Total
TOTAL COST OF ITEM VIII
INDIRECT COST
Contract Profit 10% of Direct Cost
Overhead Contegencies and Miscellaneous 15% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST:
ADJUSTED TOTAL COST OF ITEM VIII
INDIRECT COST
Contract Profit 10% of Direct Cost
Overhead Contegencies and Miscellaneous 15% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST:
ADJUSTED TOTAL COST OF ITEM IX
Item
No. Work Breakdown Structure
X
WINDOWS
A. Materials Qty. Unit of Issue
0.80m.x2.80m. Glass Window Block 2 unit
1.85m.x2m. Seamless Reflected Window on Brown 2 unit
Aluminum Frame
1.60m.x2m. 5mm thick Jalousie Windows with Clear Glass
Blades on Standard Jalouplus Casing with Complete 3 unit
Hardware Accessories
0.80m.x1.20m. 5mm thick Jalousie Windows with Clear
Glass Blades on Standard Jalouplus Casing with Complete 1 unit
Hardware Accessories
0.60m.x0.60m. 5mm thick Jalousie Windows with Clear
Glass Blades on Standard Jalouplus Casing with Complete 6 unit
Hardware Accessories
1.60m.x2.40m. 5mm thick Jalousie Windows with Clear
Glass Blades on Standard Jalouplus Casing with Complete 2 unit
Hardware Accessories
1.60m.x0.60m. 5mm thick Jalousie Windows with Clear
Glass Blades on Standard Jalouplus Casing with Complete 2 unit
Hardware Accessories
1.60m.x1.20m. 5mm thick Jalousie Windows with Clear
Glass Blades on Standard Jalouplus Casing with Complete 1 unit
Hardware Accessories
Aluminum Frame (Window Jamb, Mullion, Transom, Header
438.28 bd.ft.
and Sill)
Sub-Total
B. Labor
Direct Labor 30% of the cost of materials
Sub total
TOTAL COST OF ITEM
Item
No. Work Breakdown Structure
XI
ROOFING AND ROOF FRAMING
A. Materials Qty. Unit of Issue
50mm.x100mm.x1.5mm. Cee Purlins 21 pcs.
50mm.x150mm.x1.5mm. Rafter Purlins 304 pcs.
50mm.x50mm.x0.2mm. Angular Bar 2 pcs.
Welding Rods 22 pcs.
10 mm. Ø Sag Rods 22 pcs.
12mm. Ø x200mm. Anchor Bolts with Washers and Nuts 76 pcs.
1 1/2"x1/4" Angular Bar Cleat 162 pcs.
12 mm. thk.x250mm.x300mm. Base Plate 14 pcs.
Fascia Board 68 pcs.
6mm. thk. x50mm.x50mm. Angular Bar 66 pcs.
32"x12' Plain GI Sheet Gutter 8 pcs.
32"x12' GA 26 Plain GI Sheet 180 pcs.
Plain GI Strap on 2"x4" Cee Purlins 8 pcs.
Plain GI Strap on 2"x6" Brace Purlins 8 pcs.
Plain GI Strap on 2"x6" Rafter Purlins 8 pcs.
2 1/2" Steel Tekscrew 124 pcs.
Rivets 25 kgs.
Lead Washers 54 kgs.
G.I. Washers 66 kgs.
Sub total
B. Labor
Direct Labor 30% of the cost of materials
Sub total
TOTAL COST OF ITEM
INDIRECT COST
Contract Profit 8% of Direct Cost
Overhead Contegencies and Miscellaneous 12% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST:
ADJUSTED TOTAL COST OF ITEM XI
Item
Work Breakdown Structure
No.
XII Area (sq.m.)
CEILING WORKS (Including Interior Design)
168.50
A. Materials Qty. Unit of Issue
5mm. Thick Ordinary Plywood 60 shts.
1076 pcs 2"x2"x12' Ceiling Joist 4300 bd.ft.
Assorted nails 8 kgs.
Sub total
B. Labor
Direct Labor 30% of the cost of materials
Sub total
TOTAL COST OF ITEM
INDIRECT COST
Contract Profit 8% of Direct Cost
Overhead Contegencies and Miscellaneous 12% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST:
ADJUSTED TOTAL COST OF ITEM XII
Item Work Breakdown Structure
No.
XIII
ELECTRICAL WORKS
A. Materials Qty. Unit of Issue
Panel Board 1 pc.
Duplex Convenience Outlet 32 pcs.
6m long 25mm Ø conduit 42 pcs.
2-3.5mm THW wire 200 mtrs.
32W Circular Fluorescent Lamp 4 pcs.
32W Energy Lamp 5 pcs.
8W LED Bulbs 36 pcs.
Single Switch 8 pcs.
Two-Gang Switch 11 pcs.
Three-Gang Switch 5 pcs.
Sub total
B. Labor
Direct Labor 30% of the cost of materials
Sub total
TOTAL COST OF ITEM
INDIRECT COST
Contract Profit 8% of Direct Cost
Overhead Contegencies and Miscellaneous 12% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST
ADJUSTED TOTAL COST OF ITEM XIII
B. Labor
Direct Labor 30% of the cost of materials
Sub total
TOTAL COST OF ITEM
INDIRECT COST
Contract Profit 8% of Direct Cost
Overhead Contegencies and Miscellaneous 12% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST
ADJUSTED TOTAL COST OF ITEM XIV
Item
No. Work Breakdown Structure
XV
STAIRS / RAILINGS
A. Materials Qty. Unit of Issue
Portland cement 35 bags
Washed Sand 1.23925 cu.m.
Washed Gravel 2.4785 cu.m.
10mm Ø x 6m DRB 70 pcs.
12mm Ø x 6m DRB 9 pcs.
16mm Ø x 6m DRB 34 pcs.
#16 G.I. Tie wire 8 kgs.
Stair Railings(stainless steel) 1 set
1.2mx2.4mx14mm plywood 4 shts
Sub total
B. Labor
Direct Labor 30% of the cost of materials
TOTAL COST OF ITEM
INDIRECT COST
Contract Profit 10% of Direct Cost
Overhead Contegencies and Miscellaneous 15% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST:
ADJUSTED TOTAL COST OF ITEM XV
Item
No. Work Breakdown Structure
XVI Area (sq.m.)
1. TILEWORKS
561.00
A. Materials Qty. Unit of Issue
24"x24" Polished Tiles 1557 pcs.
Portland Cement 85 bags
Washed Sand 18 cu.m.
ABC Grout 60 bags
Sub total
B. Labor
Direct Labor 30% of the cost of materials
Sub total
Work Breakdown Structure
2. TILEWORKS ( C.R. )
A. Materials Qty. Unit of Issue
200mmx20mm Ceramic Tiles 500 pcs.
Portland cement 35 bags
washed sand 10 cu.m.
ABC grout 25 bags
Sub total
3.LABOR
Direct Labor 30% of the cost of materials
Sub total
INDIRECT COST
Contract Profit 10% of Direct Cost
Overhead Contegencies and Miscellaneous 15% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST:
ADJUSTED TOTAL COST OF ITEM XVI
INDIRECT COST
Contract Profit 10% of Direct Cost
Overhead Contegencies and Miscellaneous 15% of Direct Cost
Value Added Tax 5% of DC+CP+OCM
INDIRECT COST:
ADJUSTED TOTAL COST OF ITEM XVII
Item
Work Breakdown Structure
No.
XVIII Lot
DEMOLITION / LOT PREPARATION / BLDG. PERMIT
DEMOLITION / LOT PREPARATION / BLDG. PERMIT
1.00
A. Materials Qty. Unit of Issue
LUMPSUM
Prepared by:
Approved by:
MANUEL CALUYA NA
Project Owne
SIDENTIAL BUILDING
CK 37 LOT 20, PONTE VERDE SUBDIVISION,
AO CITY
C. NARIO
ESTIMATES
Unit Cost
30 24,000.00
Rate for
Cost
Blueprint
20 900.00
Duration Cost
1 month
o. of Copies Cost
5
3 26,000.00
3
26,000.00
I 73,400.00
Unit Cost
Cost
5,000.00
5,000.00
II 5,000.00
Unit Cost
Cost
30,000.00
30,000.00
30,000.00
30,000.00
III 67,900.00
Unit Cost
Unit Cost
ume (cu.m.)
31.27375
Unit Price Cost
300.00 9,382.13
1,237.00 14,258.90
23,641.02
Duration (hr) Cost
32 15,744.00
15,744.00
Cost
No. of Days
5 4,000.00
5 16,000.00
5 17,775.00
37,775.00
VI 77,160.02
DIRECT COST: 77,160.02
Unit Cost
ume (cu.m.)
20.9225
Unit Price Cost
260.00 50,960.00
1,035.00 10,827.39
1,010.00 21,131.73
156.00 26,988.00
394.00 85,104.00
330.00 18,150.00
65.00 106,070.25
16.00 963.04
70.00 2,800.00
322,994.41
Cost
e cost of materials 96,898.32
96,898.32
1 419,892.73
ume (cu.m.)
5.685
Unit Price Cost
260.00 13,780.00
1,035.00 2,941.99
1,010.00 5,741.85
156.00 20,124.00
394.00 39,400.00
16.00 600.96
330.00 9,900.00
65.00 48,867.00
70.00 4,060.00
145,415.80
Cost
e cost of materials 43,624.74
43,624.74
2 189,040.54
ume (cu.m.)
9.274
Unit Price Cost
260.00 21,840.00
1,035.00 4,799.30
1,010.00 9,366.74
156.00 7,332.00
16.00 18.24
43,356.28
Cost
e cost of materials 13,006.88
13,006.88
3 56,363.16
ume (cu.m.)
7.576
Unit Price Cost
260.00 17,940.00
1,035.00 3,920.58
1,010.00 7,651.76
156.00 18,096.00
65.00 73,795.80
16.00 210.88
660.00 17,820.00
70.00 350.00
139,785.02
Cost
e cost of materials 41,935.51
41,935.51
4 181,720.53
ume (cu.m.)
2.844
Unit Price Cost
260.00 7,280.00
1,035.00 1,471.77
1,010.00 2,872.44
156.00 10,608.00
394.00 23,640.00
16.00 340.48
330.00 5,280.00
65.00 26,062.40
70.00 3,500.00
81,055.09
Cost
e cost of materials 24,316.53
24,316.53
5 105,371.62
DIRECT COST: 952,388.57
Unit Cost
rea (sq.m.)
392
Unit Price Cost
10.00 46,820.00
240.00 138,240.00
1,232.05 38,699.87
156.20 41,080.60
16.00 182.26
265,022.73
Cost
e cost of materials 79,506.82
79,506.82
1 344,529.55
Lot
1
Unit Price Cost
50,000.00
50,000.00
2 50,000.00
Unit Cost
Unit Cost
-
Cost
e cost of materials -
-
X -
Unit Cost
Cost
e cost of materials -
-
XI -
DIRECT COST: -
8% of Direct Cost -
12% of Direct Cost -
5% of DC+CP+OCM -
INDIRECT COST: -
OTAL COST OF ITEM XI -
Unit Cost
rea (sq.m.) 1,147.70
sq.m. Per area
Unit Price Cost
320.00 19,200.00
30.00 129,000.00
70.00 560.00
148,760.00
Cost
e cost of materials 44,628.00
44,628.00
XII 193,388.00
DIRECT COST: 193,388.00
Unit Cost
66.00 1,452.00
95.00 1,710.00
95.00 285.00
250.00 1,000.00
27.50 550.00
4,997.00
480.00 480.00
95.00 95.00
95.00 380.00
95.00 95.00
485.00 1,940.00
85.00 2,125.00
95.00 950.00
95.00 1,900.00
95.00 760.00
95.00 190.00
490.00 980.00
95.00 95.00
95.00 95.00
440.00 8,800.00
18,885.00
485.00 2,910.00
85.00 1,530.00
95.00 570.00
5,010.00
Cost
e cost of materials 14,870.01
14,870.01
XIV 64,436.72
DIRECT COST: 64,436.72
Unit Cost
rea (sq.m.)
sq.m.
Unit Price Cost
250.00 389,250.00
240.00 20,400.00
400.00 7,200.00
80.00 4,800.00
421,650.00
Cost
e cost of materials 168,660.00
168,660.00
Unit Cost
Unit Price Cost
200.00 100,000.00
240.00 8,400.00
400.00 4,000.00
80.00 2,000.00
114,400.00
Cost
e cost of materials 211,413.00
211,413.00
XVI 916,123.00
DIRECT COST: 916,123.00
Unit Cost
Unit Cost
Lot 20,000.00
lot Per lot
Unit Price Cost
20,000.00
-
XVIII 20,000.00