Professional Documents
Culture Documents
El Sharara-Mellitah 30 Pipeline
REV. No. : A2
PETROJET Libya
Page 36 of 36
EL SHARARA-MELLITAH 30 PIPELINES
CONTRACT NO. 222
Document No.
0222-160-P-PT-PTJ-0027
A2 A1 REV.
Issued for final approval Issued for approval STATUS M. Elamir PREPARED A. Khater CHECKED Samir Helmi APPROVED E. Trovato COMPANY
El Sharara-Mellitah 30 Pipeline
REV. No. : A2
PETROJET Libya
Page 36 of 36
Description
PRE-CONSTRUCTION SURVEY PIPE HANDLING AND TRANSPORTATION ROW CONSTRUCTION STRINGING LINING-UP, CLAMPING & WELDING WELDING /Pipe Lines- WELDING /Tie ins NON-DESTRUCTIVE TESTING-RT NON-DESTRUCTIVE TESTING-UT NON-DESTRUCTIVE TESTING-PT & MT NON-DESTRUCTIVE TESTING-VT TRENCHING COATING PART1FIELD JOINT REPAIRING OF PIPE COATING BEDDING & PADDING LOWERING-IN FOC LAYING HYDROSTATIC TESTING DRYING & NITROGEN FILLING (HOLD) COLD BENDING CROSSING CIVIL WORK CATHODIC PROTECTION ELECTRICAL INSTALLATION INSTRUMENT INSTALLATION COATING PART II-COATING UNDERGROUND FACILITIES PIGGING & CLEANING REINSTATEMENT OF ROW AND RESTORATION WORK MECHANICAL INSTALLATION FOR GROUND & COATING HSS &
Rev.
A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2 A2
Remarks
28 29 30 31 32 33 34
A2 A2 A2 A2 A2 A2
HYDROTEST LVS and PTS (HOLD) MATERIAL/EQUIPMENT INSPECTION, RECEIVING AND STORAGE
Morphology Situation : Plain Hill Desert Land Sand Dunes Rocky Area Wadi Type of Vegetation : Open View Cultivated Desert Control Doc. No. : FQ-001 Control Doc. Activities
1. Instruments & tools 2. Centerline location 3. Stakes 4.Underground obstacle 5. Interval of each stake 6. Maintenance
Inspection Record
Remind
Inspection Conclusion
PIPE HANDLING AND TRANSPORTATION Location/Area From : Control Doc. No. : FQ-002 Activities
1.Pipe acceptance 2.Inspection 3.Storage and preservation 4.Bevel Protection 5.Supports 6.Security 7.On trail
Pipe Size To :
Report No.
Inspection Record
Remind
Inspection Conclusion
ROW CONSTRUCTION Location/Area Alignment Sheet No.: Pipe Size From : Report No. To :
Morphology Situation: Plain Hill Desert Land Sand Dunes Rocky Area Wadi Excavated Material: To Dump Area Piled Up Screen Plant Control Doc. No. : FQ-003 Activities
1.ROW width 2.Underground obstacle 3.Cleaning 4.High/low points removal 5.Water Crossing 6.Vehicle access
Inspection Record
Remind
Inspection Conclusion
Proceeding work: YES NO Date: Approved by Contractor Rep. QA/QC Contractor Name Signature Date Note: Activities record format is duly filled and signed.
Company
TRENCHING
Location/Area Pipe Size Report No. From : To : Morphology Situation: Plain Hill Desert Land Sand Dunes Rocky Area Wadi Work Area Characteristic: Sandy Area Sandy/Rocky Area Control Doc. No. : FQ-011 Activities
1.Centerline 2.Warning sign
Inspection Record
Remind
3.Minimum cover
Inspection Conclusion
STRINGING
Report No. To :
Inspection Record
Remind
5. Slope area
6. Longitudinal weld
Inspection Conclusion
LINING-UP AND CLAMPING & WELDING Location/Area From : To : Control Doc. No. : FQ-005 Activities
1. Pipe size 2. Pipe cleaning 3. Bevel face 4. Bevel repairing 5. Clamp removing
Pipe Size
Report No.
Inspection Record
Remind
Inspection Conclusion
WELDING P/L Location/Area Alignment Sheet No.: Control Doc. No. : FQ-006 Activities
1.Welder qualification
Remind
2. Welding material
5. Pipe preparation
6.Pre-heating
7.Welding
8.Welds inspection
9.Parent material repair 10.NDT 11.Repair & re-inspection 12.Weld mark 13.Seal
NO
Contractor Rep.
QA/QC Contractor
NON-DESTRUCTIVE TESTING-RT
Pipe Size To :
Report No.
Inspection Record
Remind
Inspection Conclusion
Pipe Size To :
Report No.
Inspection Record
Remind
Inspection Conclusion
Pipe Size PT
Report No. MT
Inspection Record
Remind
Inspection Conclusion
NON-DESTRUCTIVE TESTING-VT
Pipe Size
Report No.
Inspection Record
Remind
1.Welding inspection
Inspection Conclusion
COATING PART I-FIELD JOINT COATING HSS & REPAIRING OF PIPE COATING
Pipe Size To :
Report No.
Inspection Record
Remind
3.Material
4.Pipe ends cleaning 5.Surface treatment of pipe joint 6.Appliciation of epoxy primer 7. Pre-heating 8.Installation and location of tape
Inspection Conclusion
Company
BEDDING & PADDING Location/Area Alignment Sheet No. : Control Doc. No. : FQ-013 Activities
1.Bottom situation of trench 1) 2)
Report No.
Inspection Record
Remind
2.Material
3.Thickness of bedding 4.Padding and FOC protection 5.Room left for tie-in 6.Pipeline anchor 7.Open-cut crossing
Inspection Conclusion
LOWERING-IN Location/Area Alignment Sheet No. : Pipe Size From : Report No. To :
Morphology Situation: Plain Hill Desert Land Sand Dunes Rocky Area Wadi Type of Vegetation: Open View Cultivated Desert Control Doc. No. : FQ-014 Activities
1.Ditch dimensions 2.Dithc cleaning 3.Holiday detection 4.Pre-check 5.Pipe ends protection 6.Lifting equipments & tools
Inspection Record
Remind
7.Lower-in
Inspection Conclusion
FOC LAYING Location/Area Report No. From : To : Morphology Situation: Plain Hill Desert Land Sand Dunes Rocky Area Wadi Type of Vegetation: Open View Cultivated Desert Control Doc. No. : FQ-015 Activities
1.Visual check 2.Depth & location 3.Caution tape 4.Tie-in of FOC 5.Spare cable
Inspection Record
Remind
Inspection Conclusion
Pipe Size: To :
Report No.
Inspection Record
Remind
Inspection Conclusion
DRYING & NITROGEN FILLING (OPTION) Location/Area From : To : Pipe Size: Report No.
Inspection Record
Remind
2.Vacuum drying 3.Records and reports for drying 4.Preparation for nitrogen filling 5. Nitrogen inspect 6.Pressure inspection
Inspection Conclusion
Pipe Size: To :
Report No.
Inspection Record
Remind
Inspection Conclusion
CROSSING Location/Area From : Control Doc. No. : FQ-019 Activities Pipe Size: To : Report No.
Inspection Record
Remind
1.Preparation
4.Inspection *
Inspection Conclusion
3.Ground leveling and location measurement 4.Equipment foundation construction 5. Road construction
6.Undergroun building 2) Floating floor installation meets the requirement of the design. 1) Aboveground building construction be carried out as per the regulation of procedure. 7.Aboveground building 2) Laying of external wall tiles meet the requirement of the design. 8.Fence construction 9.Tests and records Fence construction be carried out as per the regulation of procedure. 1) All of the inspections and tests are completed as per the procedure. 2) All of the relative records are made out and pass muster.
Inspection Conclusion
Report No.
4.Testing
Inspection Conclusion
ELETRICAL INSTALLATION Location/Area From : Installing facility: Control Doc. No. : FQ-022 Activities
1.Cable Laying 2.Grounding System 3.Power Distribution Panel 4.Lighting
Inspection Record
Remind
Inspection Conclusion
INSTRUMENT INSTALLATION Location/Area From : Installing facility: Control Doc. No. : FQ-023 Activities
1.Preparation for construction
Inspection Record
Remind
2.Instrument installation
3.The connection of the instrument to process 4.Installation of support 5.Cables and junction 6.Earthing
Inspection Conclusion
COATING PART II-COATING FOR GROUND & UNDERGROUND FACILITIES Location/Area From : Pipe Size: To : Report No.
Inspection Record
Remind
Inspection Conclusion
Company
PIGGING & CLEANING Location/Area From : To : Control Doc. No. : FQ-025 Activities
1) 1.Pig and pig traps 2.Cleaning system installation 3.Inspection 4.Record and report
Pipe Size:
Report No.
Inspection Record
Remind
Inspection Conclusion
REINSTATEMENT OF ROW AND RESTORATION WORK Location/Area Pipe Size: Report No. From : To : Morphology Situation: Plain Hill Desert Land Sand Dunes Rocky Area Wadi Type of Vegetation: Open View Cultivated Desert Control Doc. No. : FQ-026 Activities Control Requirements or Accept Criteria
1) Public\ private lawns or courtyards or entrances etc. in the ROW have the same or better condition than before. 2) The cropland and water supply and drainage system and walls/fences which be destroyed are all be reinstated and acceptable. 3) All the residual materials and waste materials are moved to the proper place. 4) The original physiognomy in other place are all be reinstated. 5) The bund on the trench is acceptable. The banks and embankments which be destroyed are all reinstated and acceptable. The reinstatement of physiognomy be proved by essential photographs. The marker posts (KP posts, CP posts etc.) and warning signs are all setup and installed according to the relative requirement and acceptable.
Inspection Record
Remind
1.Reinstatement of ROW
2.Reinstatement of banks and embankments 3. Photograph 4.Pipeline marker posts and warning signs
Inspection Conclusion
STATION MECHANICAL INSTALLATION Location/Area From : Control Doc. No. : FQ-027 Activities
1.Acceptance to Equipment, fitting & material 2.Cleaning 3.Inspection to the base of the equipment 4.Installation to the equipment, fitting and auxiliary 5. Inspection*
Inspection Conclusion
BACKFILLING Location/Area Alignment Sheet No. : Morphology Situation: Plain Hill Desert Land Control Doc. No. : FQ-028 Activities
1.Backfilling material 2.Shape 3.Residual material 4.Backfilling high 5.Room left for tie-in and FOC joints* 6.Pipeline anchor 7.Crossing area
Report No.
Rocky Area
Inspection Conclusion
PAINTING ABOVE GROUND Location/Area From : Control Doc. No. : FQ-029 Activities
1.Preparation of painting 2.Painting operation 3.Inspection in painting 4.Repair 1) 2)
Inspection Conclusion
PRE-COMMISSIONING (FOR INSTRUMENT SYSTEM) Location From : System : Control Doc. No. : FQ-030 Activities
1. Preparation prior to pre-commissioning 2. Pre-commissioning 3. Record
Report No. To :
Inspection Record
Remind
Inspection Conclusion
PRE-COMMISSIONING ( FOR ELECTRIC SYSTEM) Location From : System: Control Doc. No. : FQ-031 Activities
1.Preparation prior to pre-commissioning
Report No. To :
Inspection Record
Remind
2.Pre-commissioning
3.Record
Inspection Conclusion
Inspection Record
Remind
2.Pre-commissioning
3.Record
Inspection Conclusion
Report No. To :
Activities
1.Water for Pressure Test
Inspection Record
Remind
2.Testing System
3.Testing Pressure
4. Dewatering
5. Record
Inspection Conclusion
Company
Purchase Order No. : Goods Name : Control Doc. No. : FQ-034 Activities
1.Acceptance of material and equipment 2.Piece count and visual check 3.Storage and preservation 4.Control of Non-conformed Products
Inspection Conclusion
El Sharara-Mellitah 30 Pipeline
REV. No. : A2
PETROJET Libya
Page 36 of 36