Professional Documents
Culture Documents
FOR
PIPELINE CONSTRUCTION WORKS
Page 1 of 13
Table of Contents
1.0 PROJECT INTRODUCTION
2.0 LIST OF EQUIPMENT/MACHINERY
3.0 APPLICABLE CODES,STANDARD AND SPECIFICATION
4.0 SURVEY AND ROUTING
5.0 RIGHT-OF-WAY GRADING
6.0 DITCHING/TRENCHING
7.0 HAULING AND STRINGING OF PIPE
8.0 LINE-UP AND WELD
9.0 PRODUCTION WELDING
10.0 NONDESTRUCTIVE TESTING
11.0 JOINT COATING
12.0 “POWER Crete-J” FIELD JOINT COATING
13.0 BARE BEND/PIPE COATING
14.0 PIPE COATING REPAIR
15.0 AS-BUILT QUANTITIES
16.0 LOWERING-IN AND BACKFILLING
17.0 CLEAN-UP AND REINSTATEMENT
18.0 DITCH BREAKERS
19.0 TIE-INS TO EXISTING LINE
20.0 TIE-INS
21.0 CATHODIC PROTECTION
22.0 MARKER POST, AERIAL MARKERS AND WARNING SIGNS
23.0 CROSSING
24.0 PAVED ROADS AND HIGHWAY CROSSING
25.0 WATER COURSE CROSSING
26.0 CLEANING, GAUGING, HYDROSTATIC TESTING AND DRYING
27.0 REMOVAL OF PIPELINE SECTION
28.0 APPLICATION OF PIPELINE SET-ON –WEIGHTS, CONCRETES SADDLE
29.0 FINISH GRADING AND CLEANING UP OF ROW
30.0 ENVIRONMENTAL SAFETY
31.0 AS-BUILT DOCUMENTATION
Page 2 of 13
1.0 PROJECT INTRODUCTION
Roads and Highways Department is committed to construct a multilevel road interchange at
Hatikamrul intersection under South Asian Subregional Economic Cooperation (SASEC) Road
Connectivity Project-II. The construction of the interchange renders relocation of all utility services
from the interchange area. Upon request of Roads and Highways Department Gas Transmission
Company Limited has agreed to relocate the 30” OD x 1000 psig x 1.32 Km Nalka-Hatikamrul Gas
Transmission Pipeline from Dhopakandi (near Aristocrat hotel) to south side of Hatikumrul scraper
trap station from the interchange area. The pipeline relocation works will be implemented by the Gas
Transmission Company Ltd. [the Employer], a company of Bangladesh Oil, Gas and Minerals
Corporation (Petrobangla). The cost of the relocation of pipeline works would be met up from Roads
and Highways Department (SASEC Road Connectivity Project-II).
(i) Requisition of land, Preparation, Clearing, Grading and Development of Right-of-Way (RoW),
Development of Works Site, Transportation of Line Pipe and Pipeline Materials, Carrying &
Hauling and Stringing of Line pipe & Induction Bend , Welding of Pipes, NDT, Joint Coating,
Digging the Trench, Lowering the Pipes, Civil Works (including of all civil materials), Tie-in, Road
Crossing by Thrust Boring, Metalled & Unmetalled road crossing by open-cut method, Crossing
of Khal, Canal, Pond etc., Fabrication and Placement of Set-on-Weight, Aerial and Rout Marker
post, Warning Sign, Backfilling, Cleaning Gauging & Hydrostatic Testing, Dewatering & Drying
and Clean up & Reinstatement of Row, Mitigation Environmental Policy (MEP), Remedy of Defect
etc.
(ii) Highway/Metalled Road crossing by thrust/augur boring method using casing and other crossing
conduits, cables, utilities and other facilities.
(iii) Metalled/unmetalled road crossing by open cut method without casing.
(iv) The khal/canal/pond by open cut method complete in all respect.
(v) Installation & Commissioning of Mg Anode system (vertical ground bed) for casing pipe at each
road crossing as per design and drawing and instruction of site Engineer.
(vi) Crossing of existing pipeline/facilities as per design and drawings.
(vii) Fabrication and installation of RCC concrete Set-on-Weight (SOW) for buoyancy control.
(viii) Fabrication and installation of required nos. of temporary Test Head for cleaning, gauging and
hydro test purpose.
(ix) Hook-up/Tie-in newly constructed pipeline section with the existing 30” OD Nalka-Hatikumrul
Gas Transmission Pipeline. Contractor has to supply necessary materials required for total
completion of Hook-up works. During Hook-up existing pipelines shall be cut-out by using cold
cutting machine. For Hook-up welding shall be required. All construction works including
destructive & non-destructive testing of welds.
(x) The entire pipeline to be hydrostatically tested with cleaning, gauging, pigging, and drying as
Page 3 of 13
well as required amount nitrogen charging. During pressure testing the contractor shall ensure
presence of representative(s) of explosive department.
(xi) The pipeline shall have a minimum cover of 1.2 meter from the top of pipeline surface.
(xii) The pipeline shall have a minimum cover of 2.5 meter from the top of pipeline surface in
khal/canal/pond area as per technical specification and drawings.
(xiii) Fabrication and installation of route marker and aerial post, warning sign, identification sign etc.
(xiv) Remedying of defects during the defects liability period.
(xv) Supply of Employer’s facilities.
(xvi) Preparation and supply of As-Built Drawings, Radiographic Films including weld book and
interpretation sheets in the form of bounded dossiers, Materials Balance Sheet and return of all
unused and scrap materials to Employer.
(xvii) Supply of all consumable such as welding electrodes, paints, POL, skids, water, electricity,
Nitrogen, vent & drain pipe support, all civil works materials (sand, cement, rod, stone bricks
etc.) etc.
(xviii) Pigging and Commissioning complete in all respects, of around 07 kilometer X 30” OD Pipeline
including supply of required no. of Commissioning Pigs.
(xix) Select store yard near to ROW.
(xx) Carryout ROW survey and submit report before commencement of construction (marshy land,
existing utilities, SOW & CWC probable location, electric pole, high-tension cable, khal/pond/
road etc.).
(xxi) After Hook-up with existing 30" OD Nalka-Hatikumrul pipeline section, the abandoned section
of Pipeline shall be cut at the joint locations and removed the Pipes from trench and transport
to GTCl’s store yard at Bonpara with maintaining all kinds of safety precautions. After removal
of pipes contractor shall backfill with proper compaction.
Page 4 of 13
2.16 Heavy duty air compressor
2.17 Gas Detector
2.18 Pipe and Cable Locator
2.19 Sand Blasting Machine
2.20 Radiography Facility
In case of conflict between this specification, drawing and its associated specifications and the above
codes and standard, contractor shall bring the matter to the Employer’s attention for resolution and
approval in writing. In all cases the most stringent requirement shall be applied.
Page 5 of 13
4.1 During taking over of ROW from the Employer, PEAL will stake the entire alignment of the pipeline(s).
4.2 If in the course of establishing the alignment of the pipeline or any part thereof, PEAL determines a
realignment from the defined route, in a particular area or section, could result in a better installation
at no additional cost or at cost savings to Employer, then PEAL will, by providing sufficient time, seek
Employer’s approval through a change order to proceed. In the event the Employer makes significant
change in the pipeline route, during the course of implementation of the project that will involve
additional costs then PEAL will seek prior approval of the Employer as per provision of the Contract.
4.3 PEAL is responsible for taking reasonable efforts in working around foreign obstructions as described
below:
4.3.2 The proposed pipeline will cross some existing pipelines at different locations, cables,
power lines, conduits, structures (above and underground), or facilities either owned by
the Employer or others. Where pipeline construction work parallels or crosses existing
pipelines, cables, power lines, conduits, structures, or facilities either owned by Employer
or others, extreme care will be exercised by PEAL at all times. PEAL will be responsible for
contacting authorities and owners, and locating such facilities before excavating. . In the
event such obstructions requires PEAL to lay the pipeline with a greater depth of cover,
than what is specified, requiring additional work at additional costs then PEAL may seek
prior approval of the Employer as per contract provision.
4.3.3 Although Employer will use its best efforts to provide PEAL with such information as
Employer has available as to locations of existing pipelines, power lines, conduits, cables,
structures or facilities not otherwise apparent, Employer will not be responsible for the
accuracy or completeness of such information. Employer may have its surveyor mark
certain crossed facilities for PEAL's convenience, but in no way does Employer or its
surveyor assume any liability in so doing.
Page 6 of 13
for each work day, total weld defects in the last 50 joints welded, and total weld defects welder
has been responsible for on the job. This report will be required for both pipeline and
fabrication production welders.
5.4 Employer will review the daily weld defect report and undertake the final interpretation.
Subsequently Employer will instruct PEAL of remedial action following the criteria given below:
PEAL will carry out Radiographic testing and inspection. 100% of the welding will be radio graphed by
using of X-ray crawlers. The tie in welds and fabrication welds may be inspected by gamma ray. PEAL or
GTCL’s approved sub PEAL will carry out Radiography testing, developed radiography films, and submit
acceptable films to Employer after carrying out preliminary interpretation in accordance with approved
radiography procedure. The final interpretation will be carried out by Employer. All fitting welds, fillet
welds will be examined by MPT or Ultrasonic testing. “All golden welds” the final closure weld between
hydrostatic test section, will be subjected to 100% radiography and 100% MPT or UT inspection.
The Employer will have the right to call up other NDT method such as UT, MPT etc. to assist the location
and or evaluation of defects.
Before starting of joint coating activities, PEAL will submit joint coating procedure for approval.
Prior to initial field joints coating or making repairs to damaged coating, GTCL will provide
representative for a site demonstration session for all PEAL personnel who will perform joint
coating or coating repair work.
Page 7 of 13
Application of coating, field joints, and repairs, and holiday detection testing will not be done
during inclement weather, unless weather protection and other measures approved by Employer
are provided by PEAL.
PEAL will install wrap-around heat shrinkable sleeves for all field welds on coated pipe not
installed in bored crossings. Sleeve application procedures and personnel will be qualified. All
sleeve materials, supplied by Employer, will be stored in accordance with manufacturer’s
recommendations.
Bare pipe surfaces will be blast cleaned as per SSPC-SP-10 to an anchor pattern of 1 to 3
mils. Areas which cannot be blast cleaned will be prepared using power wire brushes per
SSPC-SP-3 to remove dirt, scale, foreign debris and all but tightly adhering rust.
Sleeves will be installed only after the weld is cooled to ambient. All weld spatter will be
removed and the bare metal prepared by sand blasting. Where necessary, the mill-
applied corrosion coating will be feathered back to avoid a ridge. The bare metal surface
will be preheated using propane torches, ring burners, or induction heaters to a minimum
temperature of 75C as verified by Tempil Sticks or contact pyrometer.
6.3.2 Application
The sleeve will be applied with the lap facing down and centered over the girth weld. Heat
will be applied to one free end (side) or as specified by manufacturer's recommended
practice using propane torches with billowy flame, heating the work from top to bottom
until a complete band is shrunk onto the pipe. Heating will continue toward the opposite
end until the entire sleeve is shrunk on. Immediately after beating, hand rollers will be
used to remove all entrapped air.
7.0 “POWERCRETE-J” FIELD JOINT, IF REQUIRED
Application of powercrete-J coating compound to all field joints installed in drilled or bored
crossings. This compound will be applied in accordance with the manufacturer’s instructions.
Powercrete-J is a two-part compound which is designed for application directly onto pipe whose surface
has been prepared as described in 10.3.1 above to SSPC-10 specifications. The pipe must be dry before
application and should be pre-heated to at least 55C to enhance cure times.
12.2 Application
Page 8 of 13
Once the two parts have been properly mixed, the liquid should be applied using a Powercrete-J
troweling tool or equivalent. The first layer should be applied to a minimum wet film thickness of 15
mils, as verified with a wet mil gauge. The second 15 mil layer should be applied no sooner than 20
minutes after completing the first layer. Thickness should be checked around the weld seam to verify
total wet film thickness of 30 mils.
Subsequent layers to obtain the required minimum 30 mils wet film thickness may only be applied after
the 20-minute interval between layers.
Only after the joint coating has reached a minimum Shore D hardness of 65 may the coating be checked
for holidays and the pipe buried.
Cure time may be accelerated by using a heat gun or shrink sleeve torch, provided flames do not touch
to Powercrete-J surface AND the surface temperature is limited to not more than 70C.
Bare pipe/Bend surfaces shall be prepared using power wire brushes as per SSPC-SP-3 to remove dirt,
scale, foreign debris and all but tightly adhering rust.
13.2 Application
Bare pipe/Bend surfaces shall be coated manual/semi-automatic process with applying primer and poly ethylene
tapes. HD 50 mils poly ethylene tapes and cold primer shall be used for coating. The first layer of coating
shall be 55% overlap and the second layer of the coating shall be 50% overlap.
The pipe surface to be re-coated will be cleaned to remove all dirt and damaged or disbanded
coating. The pipe surface and the surrounding coating will be roughened using a file or wire
brush.
Page 9 of 13
The patch will be made using heat shrinkable sleeves or wraps with a suitable hot melt
adhesive layered on the inner side. If the pipe surface temperature is below 50° F at the time
of patching, the pipe surface and surrounding coating will be warmed using a torch prior to
applying the coating.
PEAL may propose to use a compatible, adhesive lined, polyethylene tape in lieu of heat shrink
sleeves if approved by Employer.
Page 10 of 13
with 150 mm of padding or suitable backfill material so as to prevent possible coating
damage due to ditch sloughing or collapse and will follow as close as practical behind
lowering-in. Complete backfilling will follow initial backfilling by no more than 48 hours
and will consist of depositing fill material in the remainder of the ditch depth, including a
300 mm settlement beam in normal ditch and a 600 mm high rock beam in rock ditch to
restrict vehicular traffic over the pipeline. Forward progress of lowering-in activities may
be halted by Employer Representative if progress of initial and final backfill operations
are not maintained to specified requirements.
11.3.3 Once padding material is installed, final backfilling will be completed with native material
or native top soil in cultivated agricultural areas. No rock larger than 60mm in any
dimension will be allowed within 300mm of the pipe. For the remaining backfill, all rock
larger than 350 cc in volume or 450 cm in any dimension will be excluded.
12.1 All debris, scrap and other waste material will be collected and disposed of. Existing facilities
which were damaged or altered by PEAL’s activities will be restored to their original condition.
12.2 In cultivated lands and pasture, topsoil will be replaced and loosened after any compaction by
construction activities. Fences, dikes, drainage systems, irrigation systems.
12.3 Temporary access roads, stockpile sites, and camp locations will be cleaned up and restored
To the as-found condition.
Page 11 of 13
Slope Percent Spacing, m.
10% 12
15% 8
20% 7
25% 6
30% 5
40% 4
50% 3
60% 2.5
70% 2
13.2 The construction of breakers will be suitable for Withstanding unbalanced loads imposed
during backfilling and the hydrostatic head established during operation. Breakers will be
constructed from either jute sacks filled with soil/cement mixture or polyurethane foam
sprayed in place. The base of the breakers will be set in undisturbed soil and constructed prior to
pipe installation with the remainder of the breaker completed once the pipe is in place. The sides
of breakers will be keyed into the ditch wall.
Page 12 of 13
cable shall consist of No. 10 gauge wire or larger, and of sufficient length to span the
separation in the piping. The ends of the cable shall be securely fastened to the pipe on
each side of the separation.
14.2.5 No "Hot Work" will start until the area has been checked and found to be free of
combustible vapors by the Employer using a combustible gas indicator.
14.2.6 “Bell Holes" will be gas-freed before any hot work is started. All contaminated earth will
be removed or covered with fresh dirt to prevent the escape of combustible vapors.
Page 13 of 13