SHELL Riyadh Fit out - Procurement log

Sl No
c d GLASS CHANNELS GLASS OPERABLE WALL b a a b GLASS DOORS CARPET TILES CEILING TILES AND GRID METAL COMPONENTS FOR SOLID CEILINGS LIGHT FITTINGS LIGHTING CONTROLS SPEED GATES/Revolving Door Nominated Supplier (Shell Connect)

TBC: To Be Confirmed N/A: Not Applicable

Project No Date:
Actual Qty Product Details Location
10th FLOOR 10th FLOOR 10th FLOOR 10 FLOOR 10 FLOOR 10th FLOOR 10th FLOOR 10 FLOOR 10 FLOOR 10th FLOOR 10th FLOOR
th th th th

24-Oct-13
Remarks

Material Description

Cost Plan Unit Qty

Supplier KSA Outside KSA


UAE/UK UAE/UK Germany/UAE UAE/UK KSA UK / UAE UK / UAE Sweden/UAE Sweden/UAE TBC TBC

Manufacturer
Otpima Optima Dorma Optima Shaw Carpets SAS SAS Faugerhault Faugerhault BOOM EDAM Steel Case /Herman Miller

Minimum Lead Time


9 WEEKS 4 WEEKS 12 WEEKS 9 WEEKS 14 WEEKS 10 WEEKS 2 WEEKS 12 WEEKS 12 WEEKS 20 WEEKS 14 WEEKS

Date Req on site


TBC TBC TBC TBC TBC TBC TBC TBC TBC TBC TBC

Material Submission Plan Actual

Material Approval Plan Actual

Order date Plan Actual

Delivery in Site Plan Actual

Page 1 of 1