Neighborhood Libraries Capital Project Report – Revision 3-3-08

Group 1 – Fully Funded

New Construction
Anacostia (Ward 7) - $14,741,000
Benning (Ward 7) - $15,707,000
Tenley Friendship (Ward 3) - $16,135,000
Watha T. Daniel/Shaw (Ward 2) - $15,005,000

March - June 2007 A/E Selection (90-days)


July 2007 Programming Phase (30-days)
August 2007 – June 2008 Design (215-days)
May 2008 – June 2008 Bidding and Permitting (60-days)
July 2008 – December 2009 Construction (515-days)
January 2010 – February 2010 Move-in and testing (60-days)
March 2010 Open to Public

Substantial Renovation – (Schedule Change from 1-14-08)


Mount Pleasant (Ward 1) - $7,750,000

September 2007 A/E Selection (60-days)


September 2007 Programming Phase (30-days)
March 2008 – December 2008 Design (245-days) – Design Start pushed back
November 2008 – December 2008 Bidding and Permitting (60-days)
January 2009 – June 2010 Construction (515-days)
July 2010 – August 2010 Move-in and testing (60-days)
September 2010 Open to Public

Restoration and Renovation


Georgetown (Ward 2) - $ 6,065.500*

August – September 2007 A/E Selection (60-days)


September 2007 Programming Phase (30-days)
February 2008 – November 2008 Design (245-days)
November 2008 – December 2008 Bidding and Permitting (60-days)
January 2009 – June 2010 Construction (515-days)
July 2010 – August 2010 Move-in and testing (60-days)
September 2010 Open to Public

* Budget amount is per the FY 07, does not include dollars set aside by
Mayor’s office for the fire restoration efforts.

Document #9C.2
Board of Library Trustees Meeting
March 19, 2008
Group 2 – Partially Funded

New Construction
Design & Construction Shortfall
Francis Gregory (Ward 7) – $4,693,000 + $2,850,000 (Federal Funds)
Washington Highlands (Ward 8) - $4,700,000 + $3,300,000 (Federal Funds)
Petworth (Ward 4) - $4,200,000 + $2,850,000 (Federal Funds)

February - March 2008 A/E Selection (60-days)


February 2008 Programming Phase (30-days)
April 2008 – January 2009 Design (245-days)
February 2009 – March 2009 Bidding and Permitting (60-days)
April 2009 – October 2010 Construction (515-days)
November – December 2010 Move-in and testing (60-days)
January 2011 Open to Public

Group 3 – Based on Proposed FY 2009-2014 Capital Budget Schedule


Budget Amounts are PROPOSED, NOT APPROVED

New Construction
Lamond Riggs (Ward 5) - $14,498,000
Capital View (Ward 7) - $15,098,000

October – November 2008 A/E Selection (60-days)


October 2008 Programming Phase (30-days)
December 2008 – February 2009 Community Meetings (90-days)
December 2008 – July 2009 Design (245-days)
August 2009 – September 2009 Bidding and Permitting (60-days)
November 2009 – March 2011 Construction (515-days)
April – May 2011 Move-in and testing (60-days)
June 2011 Open to Public

Substantial Renovation
Northeast (Ward 6) - $10,260,000

October – November 2008 A/E Selection (60-days)


October 2008 Programming Phase (30-days)
December 2008 – February 2009 Community Meetings (90-days)
December 2008 – July 2009 Design (245-days)
August 2009 – September 2009 Bidding and Permitting (60-days)
November 2009 – March 2011 Construction (515-days)
April – May 2011 Move-in and testing (60-days)
June 2011 Open to Public

Document #9C.2
Board of Library Trustees Meeting
March 19, 2008
Group 4 – Based on Proposed FY 2009-2014 Capital Budget Schedule
Budget Amounts are PROPOSED, NOT APPROVED

New Construction
Chevy Chase (Ward 3) - $15,896,275
Southwest (Ward 6) - $15,660,000

October – November 2009 A/E Selection (60-days)


October 2009 Programming Phase (30-days)
December 2009 – February 2010 Community Meetings (90-days)
August 2010 – September 2010 Bidding and Permitting (60-days)
November 2010 – March 2012 Construction (515-days)
April – May 2012 Move-in and testing (60-days)
June 2012 Open to Public

Group 5 – Based on Proposed FY 2009-2014 Capital Budget Schedule


Budget Amounts are PROPOSED, NOT APPROVED

New Construction
Cleveland Park (Ward 3) - $16,341,760
Woodridge (Ward 5) -$16,423,170

October – November 2010 A/E Selection (60-days)


October 2010 Programming Phase (30-days)
December 2010 – February 2011 Community Meetings (90-days)
August 2011 – September 2011 Bidding and Permitting (60-days)
November 2011 – March 2013 Construction (515-days)
April – May 2013 Move-in and testing (60-days)
June 2013 Open to Public

Document #9C.2
Board of Library Trustees Meeting
March 19, 2008
Group 6 – Based on Proposed FY 2009-2014 Capital Budget Schedule
Budget Amounts are PROPOSED, NOT APPROVED

New Construction
Palisades (Ward 3) - $15,657,440

Substantial Renovation

Takoma Park (Ward 4) - $7,684,250

October – November 2011 A/E Selection (60-days)


October 2011 Programming Phase (30-days)
December 2011 – February 2012 Community Meetings (90-days)
December 2012 – July 2014 Design (245-days)
August 2014 – September 2014 Bidding and Permitting (60-days)
November 2011 – March 2013 Construction (515-days)
April – May 2013 Move-in and testing (60-days)
June 2013 Open to Public

Group 7 – Based on Proposed FY 2009-2014 Capital Budget Schedule


Budget Amounts are PROPOSED, NOT APPROVED

New Construction

West End (Ward 2) - $17,885,000


Juanita E. Thornton/Shepard Park (Ward 4) - $17,556,000

October – November 2012 A/E Selection (60-days)


October 2012 Programming Phase (30-days)
December 2012 – February 2013 Community Meetings (90-days)
December 2012 – July 2013 Design (245-days)
August 2013 – September 2013 Bidding and Permitting (60-days)
November 2013 – March 2015 Construction (515-days)
April – May 2015 Move-in and testing (60-days)
June 2015 Open to Public

Document #9C.2
Board of Library Trustees Meeting
March 19, 2008