TRANSMART @ PADANG (PUBLIC AREA)

INDICATIVE CONSTRUCTION PROGRAMME


ID

Task Name

Duration

Start

Finish

A. DESIGN DEVELOPMENT
( PUBLIC AREAS - To Be Advised)

89 days

Fri 6/26/15 Wed 10/28/15

Receive all final drawings & design guidelines


From TRANS

16 days

Fri 6/26/15

Fri 7/17/15

Planning

10 days

Mon 7/20/15

Fri 7/31/15

Concept Design

7 days

Mon 8/3/15

Tue 8/11/15

Client's Feedback to TID

3 days

Thu 8/6/15

Mon 8/10/15

Design Development

21 days

Tue 8/11/15

Tue 9/8/15

1st Presentation to Client

4 days

Wed 9/9/15

Mon 9/14/15

Revision to Design

14 days

Tue 9/15/15

Fri 10/2/15

2nd submission to Client

4 days

Mon 10/5/15

Thu 10/8/15

10

2nd Revision to Design (Includes final


perspectives. Main Lobby,Lounge @ lobby,ADD
& Ballroom))

21 days

Fri 10/9/15

Fri 11/6/15

11

Final presentation & Approval by Client

7 days

July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
J 14J 21J 28 J 5 J 12J 19J 26 A 2 A 9 A 16A 23A 30 S 6 S 13S 20S 27O 4O 11O 18O 25N 1 N 8N 15N 22N 29D 6D 13D 20D 27 J 3 J 10J 17J 24J 31 F 7 F 14F 21F 28M 6M 13M 20M 27A 3 A 10A 17A 24M 1 M 8M 15M 22M 29 J 5 J 12J 19J 26 J 3 J 10J 17J 24J 31 A 7 A 14A 21A 28 S 4 S 11S 18S 25O 2 O 9O

Mon 11/9/15 Tue 11/17/15

12
13

B. Design Intent Drawings @ Specifications

58 days Wed 11/18/15

Fri 2/5/16

14

Drawings & Documentation

61 days Thu 10/29/15

Thu 1/21/16

15

Coordination with Other Consultants

11 days

Fri 1/22/16

Fri 2/5/16

16

Finalisation / Approval of Drawings

6 days

Mon 2/8/16

Mon 2/15/16

17

Christmas Holiday

1 day

Fri 12/25/15

Fri 12/25/15

18

New Year

1 day

Fri 1/1/16

Fri 1/1/16

19

CNY BREAK

11 days

Mon 2/8/16

Mon 2/22/16

21

C. Tender Process

25 days

Tue 2/23/16 Mon 3/28/16

20

22

Tender Documents to QS

11 days

Tue 2/23/16

23

Tender Process to Contractors

11 days

Wed 3/9/16 Wed 3/23/16

Tue 3/8/16

24

Tender Submission & Evaluation

7 days

Thu 3/24/16

Fri 4/1/16

25

Tender Interview

3 days

Mon 4/4/16

Wed 4/6/16

26

Tender Award

1 day

Thu 4/7/16

Thu 4/7/16

121 days

Fri 4/8/16

Fri 9/23/16

1 day

Tue 3/29/16

Tue 3/29/16

27
28

D. Main Construction Work (By Others)

29

Appoint Main Contractor

30

Mobalization

31

Construction Work & Procurement

32

Completion

33

Inspection & Comments

Date: 24 Jan 2014

11 days Wed 3/30/16 Wed 4/13/16


121 days
1 day
7 days

Thu 4/14/16

Thu 9/29/16

Fri 9/30/16

Fri 9/30/16

Mon 10/3/16 Tue 10/11/16

Task

Summary

External Milestone

Inactive Milestone

Duration-only

Start-only

External Milestone

Split

Project Summary

Inactive Task

Inactive Summary

Manual Summary Rollup

Finish-only

Progress

Milestone

External Tasks

Inactive Milestone

Manual Task

Manual Summary

External Tasks

Deadline

TID tentative planning 24 Jan 2014