(Programme of Works)
ID ID Task Name Duration Start Finish Predecessors Qtr 4, 2022 Qtr 1, 2023
Sep Oct Nov Dec Jan Feb
1 1 LKK1 CLS & LKK2 Data Centre Road 120 days Mon 05/09/22 Fri 17/02/23
Construction
2 2 Preliminaries 7 days Mon 19/09/22 Tue 27/09/22
3 3 Mobilization of Resources / Setting of 7 days Mon 19/09/22 Tue 27/09/22
Work Area / Induction Training of
Workers
4 4 Mobilization of Equipment and Personnel 5 days Mon 19/09/22 Fri 23/09/22
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
GANTT CHART FOR WORK ACTIVITIES Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress