IUFMPLot4A Classic Schedule Layout 2022-12-09 22:01

# Activity ID Activity Name Planned Start Finish Total 2023 2024


Duration Float
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 Lot4A-en-MIT221208 IUFMPLot4A
IU 249 2022-10-11 2023-11-28 0 2023-11-28, Lot4A-en-

2 Lot4A-en-MIT221208.11 KEY MILESTONES


Lot4A-en-MIT221208.1 228 2022-11-04 2023-11-28 0 2023-11-28, Lot4A-en-
3 KM1000 Project Starts 0 2022-11-04 0 Project Starts, 2022-11-04

4 KM1010 Site Construction Start Date 0 2022-11-04 176 Site Construction Start Date, 2022-11-04
5 KM1020 Completion of 0+000-3+850 RHSriver training works 0 2023-11-08 0 Completion of 0+000-3+850
6 KM1030 Completion of 0+000-3+850 LHS river training works 0 2023-11-08 0 Completion of 0+000-3+850
7 KM1040 Completion of 150 Bridge 0 2023-04-27 62 Completion of 150 Bridge,
8 KM1050 Project final completion 0 2023-11-28 0 Project final completion
9 Lot4A-en-MIT221208.12 PRELIMINARIES
Lot4A-en-MIT221208.1 249 2022-10-11 2023-11-28 0 2023-11-28, Lot4A-en-

10 Lot4A-en-MIT221208.12.5 PROJECT
P START UP 21 2022-10-11 2022-11-04 0 2022-11-04, Lot4A-en-MIT221208.12.5 PROJECT START UP
11 PSU1000 Contract award 0 2022-10-11 0 Contract award, 2022-10-11
12 PSU1010 Receipt of notice to proceed 0 2022-11-04 0 Receipt of notice to proceed, 2022-11-04
13 PSU1020 Project Starts 0 2022-11-04 0 Project Starts, 2022-11-04
14 Lot4A-en-MIT221208.12.2 PRE-CONSTRUCTION
P WORKS 52 2022-11-04 2023-01-04 176 2023-01-04, Lot4A-en-MIT221208.12.2 PRE-CONSTRUCTION WORKS
15 Lot4A-en-MIT221208.12.2. Shop Drawing
Lot4A-en-MIT221208.12.2.4 52 2022-11-04 2023-01-04 159 2023-01-04, Lot4A-en-MIT221208.12.2.4 Shop Drawing
16 SD1000 Contractor prepare and submits 14 2022-11-04 2022-11-19 159 Contractor prepare and submits
17 SD1010 Consultant comments and corrections 14 2022-11-21 2022-12-06 159 Consultant comments and corrections
18 SD1020 Contractor apply corrections and re-submit 10 2022-12-07 2022-12-17 159 Contractor apply corrections and re-submit
19 SD1030 Consultant final check and approval 14 2022-12-19 2023-01-04 159 Consultant final check and approval
20 Lot4A-en-MIT221208.12.2. SURVEY
Lot4A-en-MIT221208.12.2.0 15 2022-11-04 2022-11-21 196 2022-11-21, Lot4A-en-MIT221208.12.2.0 SURVEY
21 Lot4A-en-MIT221208.12.2.0.1 Channel0+000-3+700 RHS
Lot4A-en-MIT221208.12 15 2022-11-04 2022-11-21 196 2022-11-21, Lot4A-en-MIT221208.12.2.0.1 Channel0+000-3+700 RHS
22 PRE-MOB-OR-1030 Detailed Survey 10 2022-11-04 2022-11-15 196 Detailed Survey
23 PRE-MOB-OR-1140 Initial Setting of ROW 5 2022-11-16 2022-11-21 196 Initial Setting of ROW
24 Lot4A-en-MIT221208.12
Lot4A-en-MIT221208.12.2.0.2 Channel0+000-3+700 LHS 15 2022-11-04 2022-11-21 196 2022-11-21, Lot4A-en-MIT221208.12.2.0.2 Channel0+000-3+700 LHS
25 PRE-MOB-OR-1050 Detailed Survey 10 2022-11-04 2022-11-15 196 Detailed Survey
26 PRE-MOB-OR-1130 Initial Setting of ROW 5 2022-11-16 2022-11-21 196 Initial Setting of ROW
27 Lot4A-en-MIT221208.12
Lot4A-en-MIT221208.12.2.0.3 149Bridge 15 2022-11-04 2022-11-21 196 2022-11-21, Lot4A-en-MIT221208.12.2.0.3 149Bridge
28 PRE-MOB-OR-1070 Detailed Survey 10 2022-11-04 2022-11-15 196 Detailed Survey

29 PRE-MOB-OR-1120 Initial Setting of ROW 5 2022-11-16 2022-11-21 196 Initial Setting of ROW
30 Lot4A-en-MIT221208.12.2. Method Statements
Lot4A-en-MIT221208.12.2.2 23 2022-11-21 2022-12-16 174 2022-12-16, Lot4A-en-MIT221208.12.2.2 Method Statements
31 PRE-TED-MST-1000 Contractor preparation and submission 7 2022-11-21 2022-11-28 174 Contractor preparation and submission
32 PRE-TED-MST-1010 Consultant comments and corrections 3 2022-11-29 2022-12-01 174 Consultant comments and corrections
33 PRE-TED-MST-1020 Contractor apply corrections and re-submit 10 2022-12-02 2022-12-13 174 Contractor apply corrections and re-submit
34 PRE-TED-MST-1030 Consultant final check and approval 3 2022-12-14 2022-12-16 174 Consultant final check and approval
35 Lot4A-en-MIT221208.12.2. ESHS-MSIP
Lot4A-en-MIT221208.12.2.3 23 2022-11-21 2022-12-16 174 2022-12-16, Lot4A-en-MIT221208.12.2.3 ESHS-MSIP
36 PRE-TED-ESHS-1000 Contractor prepartion and submission 7 2022-11-21 2022-11-28 174 Contractor prepartion and submission
37 PRE-TED-ESHS-1010 Consultant comments and corrections 3 2022-11-29 2022-12-01 174 Consultant comments and corrections
38 PRE-TED-ESHS-1020 Contractor apply corrections and re-submit 10 2022-12-02 2022-12-13 174 Contractor apply corrections and re-submit
39 PRE-TED-ESHS-1030 Consultant final check and approval 3 2022-12-14 2022-12-16 174 Consultant final check and approval
40 Lot4A-en-MIT221208.12.2. Mobilization Schedule
Lot4A-en-MIT221208.12.2.6 16 2022-11-22 2022-12-09 180 2022-12-09, Lot4A-en-MIT221208.12.2.6 Mobilization Schedule
41 PRE-TED-MOS-1000 Contractor preparation and submission 5 2022-11-22 2022-11-26 180 Contractor preparation and submission
42 PRE-TED-MOS-1010 Consultant comments and corrections 3 2022-11-28 2022-11-30 180 Consultant comments and corrections
43 PRE-TED-MOS-1020 Contractor apply corrections and re-submit 5 2022-12-01 2022-12-06 180 Contractor apply corrections and re-submit
44 PRE-TED-MOS-1030 Consultant final check and approval 3 2022-12-07 2022-12-09 180 Consultant final check and approval
45 Lot4A-en-MIT221208.12.2. Project Construction Schedule
Lot4A-en-MIT221208.12.2.1 35 2022-11-22 2023-01-02 178 2023-01-02, Lot4A-en-MIT221208.12.2.1 Project Construction Schedule
46 PRE-TED-PCS-1000 Contractor preparation and submission 7 2022-11-22 2022-11-29 178 Contractor preparation and submission
47 PRE-TED-PCS-1010 Consultant comments and corrections 3 2022-11-30 2022-12-02 178 Consultant comments and corrections
48 PRE-TED-PCS-1020 Contractor apply corrections and re-submit 10 2022-12-03 2022-12-14 178 Contractor apply corrections and re-submit

Actual Level of Effort Remaining Work Page 1 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
IUFMPLot4A Classic Schedule Layout 2022-12-09 22:01
# Activity ID Activity Name Planned Start Finish Total 2023 2024
Duration Float
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
49 PRE-TED-PCS-1030 Consultant final check and approval 3 2022-12-30 2023-01-02 178 Consultant final check and approval
50 Lot4A-en-MIT221208.12.1 MOBILIZATION
M 40 2022-11-04 2022-12-20 171 2022-12-20, Lot4A-en-MIT221208.12.1 MOBILIZATION
51 Lot4A-en-MIT221208.12.1. Channel0+000-3+700 RHS
Lot4A-en-MIT221208.12.1.1 40 2022-11-04 2022-12-20 171 2022-12-20, Lot4A-en-MIT221208.12.1.1 Channel0+000-3+700 RHS
52 PRE-MOB-AG-1000 Mobilization of first set of personel 20 2022-11-04 2022-11-26 0 Mobilization of first set of personel
53 PRE-MOB-AG-1010 Mobilization of first set of equipment 40 2022-11-04 2022-12-20 0 Mobilization of first set of equipment
54 PRE-MOB-AG-1020 Delivery of first set of materials to site 30 2022-11-12 2022-12-16 174 Delivery of first set of materials to site
55 Lot4A-en-MIT221208.12.1. Channel0+000-3+700 LHS
Lot4A-en-MIT221208.12.1.2 37 2022-11-04 2022-12-16 174 2022-12-16, Lot4A-en-MIT221208.12.1.2 Channel0+000-3+700 LHS
56 PRE-MOB-KU-1000 Mobilization of first set of personel 20 2022-11-04 2022-11-26 0 Mobilization of first set of personel
57 PRE-MOB-KU-1010 Mobilization of first set of equipment 20 2022-11-04 2022-11-26 0 Mobilization of first set of equipment
58 PRE-MOB-KU-1020 Delivery of first set of materials to site 30 2022-11-12 2022-12-16 174 Delivery of first set of materials to site
59 Lot4A-en-MIT221208.12.1. 149Bridge
Lot4A-en-MIT221208.12.1.3 40 2022-11-04 2022-12-20 171 2022-12-20, Lot4A-en-MIT221208.12.1.3 149Bridge
60 PRE-MOB-OR-1000 Mobilization of first set of personel 20 2022-11-04 2022-11-26 63 Mobilization of first set of personel
61 PRE-MOB-OR-1010 Mobilization of first set of equipment 20 2022-11-04 2022-11-26 63 Mobilization of first set of equipment
62 PRE-MOB-OR-1020 Delivery of first set of materials to site 20 2022-11-28 2022-12-20 171 Delivery of first set of materials to site
63 Lot4A-en-MIT221208.12.6 TEMPORARY
T FACILITIES 35 2022-11-28 2023-01-07 173 2023-01-07, Lot4A-en-MIT221208.12.6 TEMPORARY FACILITIES
64 PRE-TEM-KU-1000 Site yard area clearance 15 2022-11-28 2022-12-14 156 Site yard area clearance
65 PRE-TEM-KU-1010 Erect site offices, change rooms, stores & toilets 20 2022-12-15 2023-01-07 173 Erect site offices, change rooms, stores & toilets
66 PRE-TEM-KU-1020 Install batching plants 20 2022-12-15 2023-01-07 173 Install batching plants
67 PRE-TEM-KU-1030 Boreholes for water supply 20 2022-12-15 2023-01-07 156 Boreholes for water supply
68 PRE-TEM-KU-1040 Temporary roads 20 2022-12-15 2023-01-07 156 Temporary roads
69 PRE-TEM-KU-1050 Set up workshops for artisans 20 2022-12-15 2023-01-07 173 Set up workshops for artisans
70 Lot4A-en-MIT221208.12.3 GENERAL
G PRELIMINARIES 249 2022-10-11 2023-11-28 0 2023-11-28, Lot4A-en-
71 A1000 Progress photographs (Four copies monthly) by the Client's 228 2022-11-04 2023-11-28 0 Progress photographs
72 A1010 Insurance of the Civil Works 228 2022-11-04 2023-11-28 0 Insurance of the Civil W
73 A1020 Construct and Erect Project Sign Boards 10 2022-11-04 2022-11-15 201 Construct and Erect Project Sign Boards
74 A1030 Maintenance of HSE Provisions 228 2022-11-04 2023-11-28 0 Maintenance of HSE P
75 A1040 Site Meetings and Evaluations 228 2022-11-04 2023-11-28 0 Site Meetings and Eva
76 A1050 Construction Trainings & Workshop 228 2022-11-04 2023-11-28 0 Construction Trainings
77 A1060 Mitigate social impacts 228 2022-11-04 2023-11-28 0 Mitigate social impacts
78 A1070 Compliance to Conditions of Contract 211 2022-11-04 2023-11-08 0 Compliance to Conditions of
79 A1080 Set up site material testing laboratory 20 2022-12-15 2023-01-07 156 Set up site material testing laboratory
80 A1120 Allow for final inspection, commissioning and taking over of 17 2023-11-09 2023-11-28 0 Allow for final inspectio
81 Lot4A-en-MIT221208.12.3. Remove and relocate existing installations within ROW
Lot4A-en-MIT221208.12.3.1 191 2022-10-11 2023-05-22 54 2023-05-22, Lot4A-en-MIT221208.12.3.1 Remove and relocate existing ins
82 A1130 Prepare & submit details of existing utilities 10 2022-11-04 2022-11-15 214 Prepare & submit details of existing utilities
83 A1140 Review and approve relocation 14 2022-10-31 2022-11-15 214 Review and approve relocation
84 A1150 Obtain NOC for existing utilities 30 2022-10-12 2022-11-15 214 Obtain NOC for existing utilities
85 A1170 Remove existing utilities 100 2022-10-11 2023-02-04 145 Remove existing utilities
86 A1180 Reinstall existing utilities 150 2022-10-25 2023-05-22 122 Reinstall existing utilities
87 Lot4A-en-MIT221208.12.3. Provide and maintain diversion roads for traffic control
Lot4A-en-MIT221208.12.3.2 228 2022-11-04 2023-11-28 0 2023-11-28, Lot4A-en-
88 A1100 Provide and maintain diversion roads for traffic control and 228 2022-11-04 2023-11-28 0 Provide and maintain d
89 A1160 Identify and service alternative routes 0 2022-11-04 2022-11-04 228 Identify and service alternative routes
90 Lot4A-en-MIT221208.1 PROCUREMENTS of Building Materials 41 2022-11-04 2022-12-21 61 2022-12-21, Lot4A-en-MIT221208.1 PROCUREMENTS of Building Materials

91 PBM1000 Material Data Sheets and Samples Submitted 5 2022-11-04 2022-11-09 61 Material Data Sheets and Samples Submitted
92 PBM1010 Review of the Submitted Data Sheets and Sample by the C 3 2022-11-10 2022-11-12 61 Review of the Submitted Data Sheets and Sample by the Consultant
93 PBM1020 Contractor review the returned document and re-submit 5 2022-11-14 2022-11-18 61 Contractor review the returned document and re-submit
94 PBM1030 Approval or further Comments on the Material Data Sheets 3 2022-11-19 2022-11-22 61 Approval or further Comments on the Material Data Sheets and Samples by he Consultant
95 PBM1040 Placing Order and Procurement of the First Batch 25 2022-11-23 2022-12-21 61 Placing Order and Procurement of the First Batch
96 Lot4A-en-MIT221208.14 SITE CONSTRUCTION
Lot4A-en-MIT221208.1 181 2022-12-09 2023-11-08 0 2023-11-08, Lot4A-en-MIT2
97 Lot4A-en-MIT221208.14.1 STA.0+000-3+700
S RHS 181 2022-12-09 2023-11-08 0 2023-11-08, Lot4A-en-MIT2

Actual Level of Effort Remaining Work Page 2 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
IUFMPLot4A Classic Schedule Layout 2022-12-09 22:01
# Activity ID Activity Name Planned Start Finish Total 2023 2024
Duration Float
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
98 A1190 site clearing and grubbing 20 2022-12-09 2023-01-02 0 site clearing and grubbing
99 Lot4A-en-MIT221208.14.1. CH 0+000 to 3+700 RHS
Lot4A-en-MIT221208.14.1.2 161 2023-01-03 2023-11-08 0 2023-11-08, Lot4A-en-MIT2
100 CHN1010 cut to shape (partial excavation) 100 2023-01-03 2023-04-28 45 cut to shape (partial excavation)
101 CHN1020 farbricate formwork and rebar 100 2023-01-03 2023-04-28 45 farbricate formwork and rebar
102 CHN1030 water division 100 2023-01-05 2023-05-01 45 water division
103 CHN1040 excavating foundation of shear key 100 2023-01-07 2023-05-03 45 excavating foundation of shear key
104 CHN1050 install rebar for shear key 100 2023-01-11 2023-05-06 45 install rebar for shear key
105 CHN1060 cast shear key 100 2023-01-13 2023-05-09 45 cast shear key
106 CHN1070 install formwork on slope 100 2023-01-16 2023-05-11 45 install formwork on slope
107 CHN1080 install rebar on slope 100 2023-01-18 2023-05-13 45 install rebar on slope
108 CHN1090 cast concrete on slope 100 2023-01-20 2023-05-16 45 cast concrete on slope
109 CHN1100 Excavation of the main body of the river 160 2023-01-03 2023-11-07 0 Excavation of the main body
110 CHN1110 final inspection and report 1 2023-11-08 2023-11-08 0 final inspection and report
111 Lot4A-en-MIT221208.14.4 S
STA0+000-3+700 LHS 181 2022-12-09 2023-11-08 0 2023-11-08, Lot4A-en-MIT2
112 A1200 site clearing and grubbing 20 2022-12-09 2023-01-02 0 site clearing and grubbing
113 Lot4A-en-MIT221208.14.4. CH 0+000 to 3+700 LHS
Lot4A-en-MIT221208.14.4.2 161 2023-01-03 2023-11-08 0 2023-11-08, Lot4A-en-MIT2
114 CHN1230 cut to shape (partial excavation) 100 2023-01-03 2023-04-28 45 cut to shape (partial excavation)
115 CHN1240 farbricate formwork and rebar 100 2023-01-03 2023-04-28 45 farbricate formwork and rebar
116 CHN1250 water division 100 2023-01-05 2023-05-01 45 water division
117 CHN1260 excavating foundation of shear key 100 2023-01-07 2023-05-03 45 excavating foundation of shear key
118 CHN1270 install rebar for shear key 100 2023-01-11 2023-05-06 45 install rebar for shear key
119 CHN1280 cast shear key 100 2023-01-13 2023-05-09 45 cast shear key
120 CHN1290 install formwork on slope 100 2023-01-16 2023-05-11 45 install formwork on slope
121 CHN1300 install rebar on slope 100 2023-01-18 2023-05-13 45 install rebar on slope
122 CHN1310 cast concrete on slope 100 2023-01-20 2023-05-16 45 cast concrete on slope
123 CHN1320 Excavation of the main body of the river 160 2023-01-03 2023-11-07 0 Excavation of the main body
124 CHN1330 final inspection and report 1 2023-11-08 2023-11-08 0 final inspection and report
125 Lot4A-en-MIT221208.14.3 1
149Bridge 113 2022-12-16 2023-04-27 62 2023-04-27, Lot4A-en-MIT221208.14.3 149Bridge
126 Lot4A-en-MIT221208.14.3. Mainbody
Lot4A-en-MIT221208.14.3.1 103 2022-12-16 2023-04-15 61 2023-04-15, Lot4A-en-MIT221208.14.3.1 Mainbody
127 BRD1000 Denolition of Old Bridge 8 2022-12-16 2022-12-24 63 Denolition of Old Bridge
128 BRD1010 Structural excavation 14 2022-12-27 2023-01-11 63 Structural excavation
129 BRD1020 R.C.C Works for Foundation, Pier, Colums, Abuntment stem 30 2023-01-02 2023-02-04 63 R.C.C Works for Foundation, Pier, Colums, Abuntment stems and Wing wall s
130 BRD1030 precast of prestressed beams 45 2023-02-01 2023-03-24 61 precast of prestressed beams
131 BRD1040 Waterproffing 2 2023-02-06 2023-02-07 63 Waterproffing
132 BRD1050 Backfilling 5 2023-02-08 2023-02-13 63 Backfilling
133 BRD1060 In-situ Pier Crossheads 10 2023-02-14 2023-02-24 85 In-situ Pier Crossheads
134 BRD1070 Precast Beams Installation 5 2023-03-28 2023-04-01 61 Precast Beams Installation
135 BRD1080 Deck Slabs and Apron Slabs 10 2023-04-03 2023-04-13 61 Deck Slabs and Apron Slabs
136 BRD1090 Parapets and Sidewalk 8 2023-04-07 2023-04-15 61 Parapets and Sidewalk
137 Lot4A-en-MIT221208.14.3. Roadwork
Lot4A-en-MIT221208.14.3.2 23 2023-04-01 2023-04-27 62 2023-04-27, Lot4A-en-MIT221208.14.3.2 Roadwork
138 RD1000 earth works 2 2023-04-01 2023-04-03 63 earth works
139 RD1010 Subbase and Base course 5 2023-04-04 2023-04-10 140 Subbase and Base course
140 RD1020 Curbs and Guardrail Bases 3 2023-04-11 2023-04-13 140 Curbs and Guardrail Bases
141 RD1030 Guardrail installation 2 2023-04-17 2023-04-18 139 Guardrail installation
142 RD1040 Asphalt Work 5 2023-04-19 2023-04-25 139 Asphalt Work
143 RD1050 Pavement Markings 2 2023-04-26 2023-04-27 139 Pavement Markings
144 Lot4A-en-MIT221208.15 PROJECT CLOSE OUT
Lot4A-en-MIT221208.1 17 2023-11-09 2023-11-28 0 2023-11-28, Lot4A-en-

145 PCL1000 Final Inspection, Commissioning & Demobilization 17 2023-11-09 2023-11-28 0 Final Inspection, Comm
146 PCL1010 Project Close out 0 2023-11-28 0 Project Close out,

Actual Level of Effort Remaining Work Page 3 of 3 TASK filter: All Activities