Proposed A & A to Existing 5 Story Main Library Building and 4-Story Library Annex Building (phase

one)
at Singapore polytechnic Master Schedule
ID

Duration

Start

Task Name
1

Proposed A &A to Existing 5 Story Main


219 days
Library Building and 4-Story Library Annex
Building (phase one) at Singapore
polytechnic
11 days

Preliminaries

Wed
7/1/15

Finish June 2015


July 2015
August 2015
September 2015
October 2015
November 2015
December 2015
January 2016
February 2016
March 2016
April 2016
May 2016
8 1114 1720 23 2629 2 5 8 11 1417 2023 2629 1 4 7 10 1316 1922 2528 31 3 6 9 12 1518 2124 2730 3 6 9 12 1518 2124 2730 2 5 8 11 1417 20 2326 29 2 5 8 1114 1720 2326 29 1 4 7 1013 1619 2225 2831 3 6 9 1215 1821 2427 1 4 7 10 1316 1922 2528 31 3 6 9 1215 18 2124 2730 3 6 9

Sat
4/30/16

Wed 7/1/15 Wed 7/15/15

Award of Contract

1 day

Wed 7/1/15

Wed 7/1/15

Purchase of insurance

2 wks

Thu 7/2/15

Wed 7/15/15

Submission of Equipment / Drawing Submission Schedule

2 wks

Thu 7/2/15

Wed 7/15/15

30 days

Design Stage

Thu 7/2/15 Wed 8/12/15

Submission of Mobilization Plan

1 day

Thu 7/2/15

Thu 7/2/15

10

Mobilization of site setting up/safety

2 wks

Thu 7/2/15

Wed 7/15/15

11

Submission of necessary(Demolition/ Structure) plan for approval

1 wk

Thu 7/2/15

Wed 7/8/15

12

Approval of Demolition/ Structure Plan

2 wks

Thu 7/9/15

Wed 7/22/15

13

Selection of Material Sample - Phase

2 wks

Thu 7/16/15

Wed 7/29/15

14

Submission of Equipment/ Shop Drawings for Approval

2 wks

Thu 7/16/15

Wed 7/29/15

Approval of equipment

2 wks

Thu 7/30/15

Wed 8/12/15

15
17
19

185 days

Site Construction
Phase 1(Zones involve in Colours)

Thu 7/9/15 Wed 3/23/16

40 days

Thu 7/9/15

Wed 9/2/15

20

Demolition Works

1 wk

Thu 7/9/15

Wed 7/15/15

21

Architectural/Building work - Phase 1

5 wks

Thu 7/16/15

Wed 8/19/15

22

M&E Works

2 wks

Thu 8/20/15

Wed 9/2/15

23

Fire protection Works

2 wks

Thu 8/20/15

Wed 9/2/15

50 days

Thu 9/3/15

Wed 11/11/15

24

Phase 2 ( Zones involve in 1st Story AHUs 1-1,1-2 &


stairs 1,Event Space, Wonderland, Caf &Reading
Area2, 1st story Counter &staircase 3 Colours )

25

Demolition Works

1 wk

Thu 9/3/15

Wed 9/9/15

26

Architectural/Building work - Phase 2

4 wks

Thu 9/10/15

Wed 10/7/15

27

M&E Works

2 wks

Thu 10/8/15

Wed 10/21/15

28

Fire protection Works

2 wks

Thu 10/8/15

Wed 10/21/15

29

Finishing work and Furniture Works

3 wks

Thu 10/22/15

Wed 11/11/15

50 days

Thu 11/12/15

Wed 1/20/16

30

Phase 3(Zones involve in Colours, Reading Area 5,


Return Mahine, Reading Area 4 Exhiition Area
Collaborative Zone, mobile Counter, Turnstile
Entrance, new Arivals Area, materials Library,
reading Area &Gallery)

31

Demolition Works

1 wk

Thu 11/12/15

Wed 11/18/15

32

Architectural/ Building work - Phase 3

4 wks

Thu 11/19/15

Wed 12/16/15

33

M&E Works

2 wks

Thu 12/17/15

Wed 12/30/15

34

Fire protection Works

2 wks

Thu 12/17/15

Wed 12/30/15

35

Finishing work and Furniture Works

3 wks

Thu 12/31/15

Wed 1/20/16

35 days

Thu 1/21/16

Wed 3/9/16

Demolition Works

1 wk

Thu 1/21/16

Wed 1/27/16

Thu 1/28/16

Wed 2/10/16

36

37
38

Phase 4(Entrance lobby, multimedia Room,kinect


rooms, media viewing & Reading Area)
Architectural/Building work - Phase 4

2 wks

39

M&E Works

2 wks

Thu 2/11/16

Wed 2/24/16

40

Fire protection Works

2 wks

Thu 2/11/16

Wed 2/24/16

41

Finishing work and Furniture Works

2 wks

Thu 2/25/16

Wed 3/9/16

175 days

Thu 7/23/15

Wed 3/23/16

42

Phase X( Unphased works:- Zones involve in


Generator Rooms, Horse reel Tank Rooms, Apron
Walkway, Courtyard 2nd story 7linkway, Annex
Staircase 4, Annex Stair case 5, Slab over of Stair
case 3, lift lobby, Stair Case 1&2, magazine drawers,
directors'Room)

43

Demolition Works

3 wks

Thu 7/23/15

Wed 8/12/15

44

Architectural/building work - Phase X

17 wks

Thu 8/13/15

Wed 12/9/15

45

M&E Works

10 wks

Thu 12/10/15

Wed 2/17/16

46

Fire protection Works

10 wks

Thu 12/10/15

Wed 2/17/16

47

Finishing works

5 wks

Thu 2/18/16

Wed 3/23/16

28 days

Thu 3/24/16

Sat 4/30/16

48

Hand Over

49
50

Testing And Commissioning


BCA/ FSSD submission

1 wk
2 wks

Thu 3/24/16
Thu 3/31/16

Wed 3/30/16
Wed 4/13/16

51

Maintenance serving DLP

2 wks

Thu 3/31/16

Wed 4/13/16

52

OMM and Warranty

2 wks

Tue 4/19/16

Sat 4/30/16

Project: Project Schedule - SP library


Date: Thu 6/11/15

9/2

11/11

1/20

3/9

Must Finished the Full height Glass works


by others before do the ME works! at
Entrance lobby Kinect Rooms
3/23

Task

Summary

External Milestone

Manual Task

Manual Summary

External Tasks

Baseline Milestone

Split

Project Summary

Inactive Milestone

Duration-only

Start-only

External Milestone

Baseline Summary

Milestone

External Tasks

Inactive Summary

Manual Summary Rollup

Finish-only

Baseline

Progress