WORK PLAN
Design and Construction of Network and House Connections in the City of Malanje - Design Stage
ID Task Name Duration Start Finish '19 Mar 17 '19 Jun 2 '19 Aug 18 '19 Nov 3 '20 Jan 19 '20 Apr 5 '20 Jun 21 '20 Sep
S M T W T F S S M T W T F S S M
1 Assessment of the Existing Situation 392 days Wed 19/4/10 Tue 20/5/5
2 Counting total number of home connections in 70 days Wed 19/4/10 Tue 19/6/18
the field(executed by consultant,local water
company and contractor)
Page 1
Design and Construction of Network and House Connections in the City of Malanje - Design Stage
ID Task Name Duration Start Finish '19 Mar 17 '19 Jun 2 '19 Aug 18 '19 Nov 3 '20 Jan 19 '20 Apr 5 '20 Jun 21 '20 Sep
S M T W T F S S M T W T F S S M
31 Preparation and Submittal of ESMP 1 day Wed 20/5/6 Wed 20/5/6
32 Consultant's review and approval of 1 day Thu 20/5/7 Thu 20/5/7
preliminary engineering design report and
ESMP