ID Task Task Name Duration Start Finish

Mode 16 23
0 Project1 211 days Mon Mon
3/2/20 11/2/20

1 Foundation Works 34 days Mon 3/2/20 Thu 4/9/20

2 Layout 1 day Mon 3/2/20 Mon 3/2/20

3 Excavation 10 days Tue 3/3/20 Fri 3/13/20

4 Backfill/Earthfill 5 days Wed Mon 3/16/20


3/11/20

5 Compaction 3 days Sat 3/14/20 Tue 3/17/20

6 Soil Poisoning 1 day Wed Wed 3/18/20


3/18/20

7 Gravel Bedding 2 days Thu 3/19/20 Fri 3/20/20

8 Formworks 8 days Sat 3/21/20 Mon 3/30/20

9 Rebar Works 10 days Thu 3/26/20 Mon 4/6/20

10 Structural Inspection 1 day Tue 4/7/20 Tue 4/7/20

11 Concreting 2 days Wed 4/8/20 Thu 4/9/20

12 Superstructure 75 days Fri 4/10/20 Mon 7/6/20

13 Ground floor columns 23 days Fri 4/10/20 Wed 5/6/20

14 Scaffoldings 10 days Fri 4/10/20 Tue 4/21/20

15 Rebar Works 10 days Thu 4/16/20 Mon 4/27/20

16 Formworks 10 days Wed Sat 5/2/20


4/22/20

17 Structural Inspection 1 day Mon 5/4/20 Mon 5/4/20

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 1
ID Task Task Name Duration Start Finish
Mode 16 23
18 Concreting 2 days Tue 5/5/20 Wed 5/6/20

19 2nd flr beams & slabs 36 days Thu 5/7/20 Wed 6/17/20

20 scaffoldings 20 days Thu 5/7/20 Fri 5/29/20

21 rebar Works 15 days Tue 5/19/20 Thu 6/4/20

22 formworks 15 days Thu 5/28/20 Sat 6/13/20

23 structural Inspection 1 day Mon Mon 6/15/20


6/15/20

24 concreting 2 days Tue 6/16/20 Wed 6/17/20

25 Slab on grade 16 days Thu 6/18/20 Mon 7/6/20

26 Earthfill 3 days Thu 6/18/20 Sat 6/20/20

27 Leveling and Compaction 2 days Mon Tue 6/23/20


6/22/20

28 Soil Poisoning 1 day Wed Wed 6/24/20


6/24/20

29 Gravel Bedding 1 day Thu 6/25/20 Thu 6/25/20

30 Rebar Works 6 days Fri 6/26/20 Thu 7/2/20

31 Formworks 2 days Fri 7/3/20 Sat 7/4/20

32 Concreting 1 day Mon 7/6/20 Mon 7/6/20

33 Masonry 74 days Thu 6/18/20 Fri 9/11/20

34 Ground floor 50 days Thu 6/18/20 Fri 8/14/20

35 Exterior walls 25 days Thu 6/18/20 Thu 7/16/20

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 2
ID Task Task Name Duration Start Finish
Mode 16 23
36 Interior walls 35 days Mon 7/6/20 Fri 8/14/20

37 Second floor 60 days Sat 7/4/20 Fri 9/11/20

38 Exterior walls 25 days Sat 7/4/20 Sat 8/1/20

39 Interior walls 35 days Mon 8/3/20 Fri 9/11/20

40 Trusses and Roofing 41 days Mon Fri 8/7/20


6/22/20

41 Fabrication of Truss 10 days Mon Thu 7/2/20


6/22/20

42 Painting 3 days Fri 7/3/20 Mon 7/6/20

43 Installation of Truss 10 days Tue 7/7/20 Fri 7/17/20

44 Install of Purlins 8 days Sat 7/18/20 Mon 7/27/20

45 Install Roofing & Accessories 8 days Tue 7/28/20 Wed 8/5/20

46 Touch-up 2 days Thu 8/6/20 Fri 8/7/20

47 Plumbing Lines 30 days Thu 6/18/20 Wed 7/22/20

48 Sewer Lines rough-ins 10 days Thu 6/18/20 Mon 6/29/20

49 waterlines rough-ins 10 days Thu 6/18/20 Mon 6/29/20

50 Plumbing Fixtures 8 days Tue 6/30/20 Wed 7/8/20

51 Septic Tanks 10 days Thu 7/9/20 Mon 7/20/20

52 Testings & Commissioning 2 days Tue 7/21/20 Wed 7/22/20

53 Electrical Works 76 days Tue 8/4/20 Fri 10/30/20

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 3
ID Task Task Name Duration Start Finish
Mode 16 23
54 Rough-ins 10 days Tue 8/4/20 Tue 9/29/20

55 Wires and Cables 10 days Wed Sat 10/10/20


9/30/20

56 Electrical Fixtures 8 days Mon Tue 10/20/20


10/12/20

57 Main Feeder lines 5 days Wed Mon


10/21/20 10/26/20

58 Emergency Lights 2 days Tue Wed


10/27/20 10/28/20

59 Testings & Commissioning 2 days Thu Fri 10/30/20


10/29/20

60 Fire Protection Works 20 days Sat 8/8/20 Mon 8/31/20

61 Fire Hose Cabinet 7 days Sat 8/8/20 Sat 8/15/20

62 Wet and Dry Stand Pipe 10 days Mon Thu 8/27/20


8/17/20

63 Fire Extinguishers 3 days Fri 8/28/20 Mon 8/31/20

64 Project Inspections 2 days Sat 10/31/20 Mon 11/2/20

65 Project Close-out and 0 days Mon Mon 11/2/20


Turn-over 11/2/20

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 4
Mar '20 Apr '20
23 1 8 15 22 29 5 12

Layout
3/2 3/2

1 day
Excavation
3/3 3/13

10 days
Backfill/Earthfill
3/11 3/16

5 days
Compaction
3/14 3/17

3 days
Soil Poisoning
3/18 3/18

1 day
Gravel Bedding
3/19 3/20

2 days
Formworks
3/21 3/30

8 days
Rebar Works
3/26 4/6

10 days
Structural Inspection
4/7 4/7

1 day
Concreting
4/8 4/9

2 days

Scaffoldings
4/10
10 days
Rebar W
4/16

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 5
Mar '20 Apr '20
23 1 8 15 22 29 5 12

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 6
Mar '20 Apr '20
23 1 8 15 22 29 5 12

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 7
Mar '20 Apr '20
23 1 8 15 22 29 5 12

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 8
May '20 Jun '20
19 26 3 10 17 24 31 7

Scaffoldings
4/21

Rebar Works
4/27

10 days
Formworks
4/22 5/2

10 days
Structural Inspection
5/4 5/4

1 day
Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 9
May '20 Jun '20
19 26 3 10 17 24 31 7
Concreting
5/5 5/6

2 days

scaffoldings
5/7 5/29

20 days
rebar Works
5/19 6/4

15 days
formworks
5/28
15 days
structural Inspe
6/15

6/16

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 10
May '20 Jun '20
19 26 3 10 17 24 31 7

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 11
May '20 Jun '20
19 26 3 10 17 24 31 7

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 12
Jul '20 Aug '20
14 21 28 5 12 19 26 2

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 13
Jul '20 Aug '20
14 21 28 5 12 19 26 2

6/13

structural Inspection
6/15 6/15

1 day
concreting
6/16 6/17

2 days

Earthfill
6/18 6/20

3 days
Leveling and Compaction
6/22 6/23

2 days
Soil Poisoning
6/24 6/24

1 day
Gravel Bedding
6/25 6/25

1 day
Rebar Works
6/26 7/2

6 days
Formworks
7/3 7/4

2 days
Concreting
7/6 7/6

1 day

Exterior walls
6/18 7/16

25 days

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 14
Jul '20 Aug '20
14 21 28 5 12 19 26 2
Interior walls
7/6
35 days

Exterior walls
7/4 8/1

25 days

8/3

Fabrication of Truss
6/22 7/2

10 days
Painting
7/3 7/6

3 days
Installation of Truss
7/7 7/17

10 days
Install of Purlins
7/18 7/27

8 days
Install Roofing & Accessories
7/28 8/5

8 days
Touch-up
8/6 8/7

2 days

Sewer Lines rough-ins


6/18 6/29

10 days
waterlines rough-ins
6/18 6/29

10 days
Plumbing Fixtures
6/30 7/8

8 days
Septic Tanks
7/9 7/20

10 days
Testings & Commissioning
7/21 7/22

2 days

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 15
Jul '20 Aug '20
14 21 28 5 12 19 26 2

Fire Hose C
8/8

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 16
Sep '20 Oct '20
9 16 23 30 6 13 20 27

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 17
Sep '20 Oct '20
9 16 23 30 6 13 20 27

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 18
Sep '20 Oct '20
9 16 23 30 6 13 20 27

8/14

Interior walls
9/11

35 days

Touch-up
8/7

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 19
Sep '20 Oct '20
9 16 23 30 6 13 20 27

Fire Hose Cabinet


8/15

7 days
Wet and Dry Stand Pipe
8/17 8/27

10 days
Fire Extinguishers
8/28 8/31

3 days

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 20
Nov '20
4 11 18 25 1 8 15 22

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 21
Nov '20
4 11 18 25 1 8 15 22

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 22
Nov '20
4 11 18 25 1 8 15 22

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks

Page 23
Nov '20
4 11 18 25 1 8 15 22

11/2

Task External Milestone

Split Deadline

Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress

Manual Task Manual Progress

External Tasks