0 Project1 211 days Mon Mon
3/2/20 11/2/20
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 1
ID Task Task Name Duration Start Finish
Mode 16 23
18 Concreting 2 days Tue 5/5/20 Wed 5/6/20
19 2nd flr beams & slabs 36 days Thu 5/7/20 Wed 6/17/20
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 2
ID Task Task Name Duration Start Finish
Mode 16 23
36 Interior walls 35 days Mon 7/6/20 Fri 8/14/20
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 3
ID Task Task Name Duration Start Finish
Mode 16 23
54 Rough-ins 10 days Tue 8/4/20 Tue 9/29/20
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 4
Mar '20 Apr '20
23 1 8 15 22 29 5 12
Layout
3/2 3/2
1 day
Excavation
3/3 3/13
10 days
Backfill/Earthfill
3/11 3/16
5 days
Compaction
3/14 3/17
3 days
Soil Poisoning
3/18 3/18
1 day
Gravel Bedding
3/19 3/20
2 days
Formworks
3/21 3/30
8 days
Rebar Works
3/26 4/6
10 days
Structural Inspection
4/7 4/7
1 day
Concreting
4/8 4/9
2 days
Scaffoldings
4/10
10 days
Rebar W
4/16
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 5
Mar '20 Apr '20
23 1 8 15 22 29 5 12
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 6
Mar '20 Apr '20
23 1 8 15 22 29 5 12
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 7
Mar '20 Apr '20
23 1 8 15 22 29 5 12
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 8
May '20 Jun '20
19 26 3 10 17 24 31 7
Scaffoldings
4/21
Rebar Works
4/27
10 days
Formworks
4/22 5/2
10 days
Structural Inspection
5/4 5/4
1 day
Task External Milestone
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 9
May '20 Jun '20
19 26 3 10 17 24 31 7
Concreting
5/5 5/6
2 days
scaffoldings
5/7 5/29
20 days
rebar Works
5/19 6/4
15 days
formworks
5/28
15 days
structural Inspe
6/15
6/16
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 10
May '20 Jun '20
19 26 3 10 17 24 31 7
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 11
May '20 Jun '20
19 26 3 10 17 24 31 7
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 12
Jul '20 Aug '20
14 21 28 5 12 19 26 2
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 13
Jul '20 Aug '20
14 21 28 5 12 19 26 2
6/13
structural Inspection
6/15 6/15
1 day
concreting
6/16 6/17
2 days
Earthfill
6/18 6/20
3 days
Leveling and Compaction
6/22 6/23
2 days
Soil Poisoning
6/24 6/24
1 day
Gravel Bedding
6/25 6/25
1 day
Rebar Works
6/26 7/2
6 days
Formworks
7/3 7/4
2 days
Concreting
7/6 7/6
1 day
Exterior walls
6/18 7/16
25 days
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 14
Jul '20 Aug '20
14 21 28 5 12 19 26 2
Interior walls
7/6
35 days
Exterior walls
7/4 8/1
25 days
8/3
Fabrication of Truss
6/22 7/2
10 days
Painting
7/3 7/6
3 days
Installation of Truss
7/7 7/17
10 days
Install of Purlins
7/18 7/27
8 days
Install Roofing & Accessories
7/28 8/5
8 days
Touch-up
8/6 8/7
2 days
10 days
waterlines rough-ins
6/18 6/29
10 days
Plumbing Fixtures
6/30 7/8
8 days
Septic Tanks
7/9 7/20
10 days
Testings & Commissioning
7/21 7/22
2 days
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 15
Jul '20 Aug '20
14 21 28 5 12 19 26 2
Fire Hose C
8/8
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 16
Sep '20 Oct '20
9 16 23 30 6 13 20 27
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 17
Sep '20 Oct '20
9 16 23 30 6 13 20 27
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 18
Sep '20 Oct '20
9 16 23 30 6 13 20 27
8/14
Interior walls
9/11
35 days
Touch-up
8/7
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 19
Sep '20 Oct '20
9 16 23 30 6 13 20 27
7 days
Wet and Dry Stand Pipe
8/17 8/27
10 days
Fire Extinguishers
8/28 8/31
3 days
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 20
Nov '20
4 11 18 25 1 8 15 22
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 21
Nov '20
4 11 18 25 1 8 15 22
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 22
Nov '20
4 11 18 25 1 8 15 22
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 23
Nov '20
4 11 18 25 1 8 15 22
11/2
Split Deadline
Milestone Critical
Project: Project1
Summary Critical Split
Date: Sun 3/1/20
Project Summary Progress
External Tasks
Page 24