ID Task Task Name Duration Start November 2020 December 2020

Mode 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1
1 Provision of replacement pipe support at jetty 28.88 days Fri 16/10/20
and wraping pipe 8 inch
2 Planning 8.5 days Fri 16/10/20

3 Develop JMS 8 hrs Fri 16/10/20

4 Develop JHA 36 hrs Sat 17/10/20

5 Develop Rescue plan 8 hrs Sat 24/10/20

6 Develop Scaffolding plan 2 days Mon 26/10/20

7 Plan for Quality 1 day Mon 26/10/20

8 Document Quality Management Plan8 hrs Mon 26/10/20

9 HSE Programme 1 day Wed 28/10/20

10 HSE induction 1 day Wed 28/10/20

11 Execution 28.88 days Fri 16/10/20

12 Perform Scaffolding erection 24 hrs Thu 29/10/20

13 Mobilisation and inspection tools 6 hrs Thu 29/10/20

14 Perform reconfirm measurement pipe support


2 hrs Fri 30/10/20

15 Perform fabrication Support no 1 2.5 days Fri 16/10/20

16 Perform Cutting as per cutting list 1 hr Fri 16/10/20

17 Perform Fit-up and visual inspection 2 hrs Fri 16/10/20

18 Perform welding 6 hrs Fri 16/10/20

19 Perform NDT 1 hr Sat 17/10/20

20 Perform Surface Preparation 2 hrs Sat 17/10/20

21 Perform painting 8 hrs Mon 19/10/20

22 Perform fabrication Support no 2 2.5 days Tue 20/10/20

23 Perform Cutting as per cutting list 1 hr Tue 20/10/20

24 Perform Fit-up and visual inspection 2 hrs Tue 20/10/20

25 Perform welding 6 hrs Tue 20/10/20

26 Perform NDT 1 hr Wed 21/10/20

27 Perform Surface Preparation 2 hrs Thu 22/10/20

28 Perform painting 8 hrs Thu 22/10/20

29 Perform fabrication Support no 3 2.5 days Fri 23/10/20

30 Perform Cutting as per cutting list 1 hr Fri 23/10/20

31 Perform Fit-up and visual inspection 2 hrs Fri 23/10/20

32 Perform welding 6 hrs Sat 24/10/20

33 Perform NDT 1 hr Mon 26/10/20

34 Perform Surface Preparation 2 hrs Mon 26/10/20

35 Perform painting 8 hrs Mon 26/10/20

36 Perform Surface Preparation, repainting 13.88 days Fri 30/10/20


and wraping at site pipe 8"
37 Perform strip off existing wrapping 16 hrs Fri 30/10/20

38 perform Surface preparation (Power 36 hrs Tue 3/11/20


tools/Sand down)
39 Perform repainting first coat 8 hrs Tue 10/11/20

40 Perform painting second coat 8 hrs Wed 11/11/20

41 Perform painting final coat 8 hrs Thu 12/11/20

42 Perfrom Wraping Pipe 8" 35 hrs Sat 14/11/20

43 Installation Pipe support 1 1.25 days Fri 20/11/20

44 Perform drilling and installation wall plug 4 hrs Fri 20/11/20

45 Perform Installation Pipe support 4 hrs Sat 21/11/20

46 Perform cutting existing pipe support 2 hrs Mon 23/11/20


and remove old support
47 Installation Pipe support 2 1.25 days Mon 23/11/20

48 Perform drilling and installation wall plug 4 hrs Mon 23/11/20

49 Perform Installation Pipe support 4 hrs Tue 24/11/20

50 Perform cutting existing pipe support 2 hrs Tue 24/11/20


and remove old support
51 Installation Pipe support 3 1.25 days Wed 25/11/20

52 Perform drilling and installation wall plug 4 hrs Wed 25/11/20

53 Perform Installation Pipe support 4 hrs Wed 25/11/20

54 Perform cutting existing pipe support 2 hrs Thu 26/11/20


and remove old support
55 General Housekeeping 8 hrs Thu 26/11/20

56 Demobilised Equipment and Manpower 8 hrs Sat 28/11/20


from site

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Project1
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 17/10/20
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1