D/248/22

PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 Proposed Road, Vehicular Bridge, Bus Shelters and Linkways at Hougang Town 522 days Fri 26/8/22 Thu 25/4/24 Mon 29/8/22 Thu 25/4/24 0 days

2 Contract Start Date 1 day Fri 26/8/22 Fri 26/8/22 Mon 29/8/22 Mon 29/8/22 2 days


3 Project Duration 521 days Sat 27/8/22 Thu 25/4/24 Tue 30/8/22 Thu 25/4/24 0 days
4 Preliminaries 70 days Sat 27/8/22 Wed 16/11/22 Tue 30/8/22 Thu 17/11/22 1 day
5  Workman Comp & Insurance 7 days Sat 27/8/22 Sat 3/9/22 Tue 30/8/22 Tue 6/9/22 2 days
6  Public Relation with Stakeholders 60 days Mon 5/9/22 Sat 12/11/22 Fri 9/9/22 Thu 17/11/22 4 days
7  Pre‐construction Condition Survey 60 days Mon 5/9/22 Sat 12/11/22 Fri 9/9/22 Thu 17/11/22 4 days
8 Noise impact assessment  60 days Mon 5/9/22 Sat 12/11/22 Fri 9/9/22 Thu 17/11/22 4 days
9 Topographic Survey 60 days Mon 5/9/22 Sat 12/11/22 Fri 9/9/22 Thu 17/11/22 4 days
10  Set‐up Project Signboard 40 days Mon 5/9/22 Thu 20/10/22 Fri 23/9/22 Tue 8/11/22 16 days
11  Set‐up Contractor Site Office 48 days Mon 5/9/22 Sat 29/10/22 Fri 23/9/22 Thu 17/11/22 16 days
12 Utility Service Coordination 62 days Mon 5/9/22 Tue 15/11/22 Wed 7/9/22 Thu 17/11/22 2 days
13  Cable Detection 18 days Mon 5/9/22 Sat 24/9/22 Wed 7/9/22 Tue 27/9/22 2 days
14  NCE from Utility Agencies 24 days Mon 5/9/22 Sat 1/10/22 Wed 7/9/22 Tue 4/10/22 2 days
15  Trial Trenching 28 days Mon 3/10/22 Thu 3/11/22 Wed 5/10/22 Sat 5/11/22 2 days
16 Utility service identification and coordination with Agencies 10 days Fri 4/11/22 Tue 15/11/22 Mon 7/11/22 Thu 17/11/22 2 days
17 Temporary Hoarding and Washing Bay 44 days Sat 27/8/22 Mon 17/10/22 Fri 2/9/22 Sat 5/11/22 5 days
18 Design of temporary hoarding/noise barrier with gate access 30 days Sat 27/8/22 Fri 30/9/22 Fri 2/9/22 Thu 6/10/22 5 days
19 Design of temporary washing bay 15 days Sat 27/8/22 Tue 13/9/22 Tue 4/10/22 Thu 20/10/22 32 days
20 Submission to HDB/MM 7 days Sat 1/10/22 Sat 8/10/22 Fri 21/10/22 Fri 28/10/22 17 days
21 Approval by HDB/MM 7 days Mon 10/10/22 Mon 17/10/22 Sat 29/10/22 Sat 5/11/22 17 days
22 Biodiveristy Study 51 days Sat 27/8/22 Tue 25/10/22 Tue 20/9/22 Thu 17/11/22 20 days
23 Wildlife biodiversity study and assessment 30 days Sat 27/8/22 Fri 30/9/22 Tue 20/9/22 Mon 24/10/22 20 days
24 Submission to HDB/Nparks 7 days Sat 1/10/22 Sat 8/10/22 Tue 25/10/22 Tue 1/11/22 20 days
25 Approval by HDB/Nparks 14 days Mon 10/10/22 Tue 25/10/22 Wed 2/11/22 Thu 17/11/22 20 days
26 Arborist Report and Tree Survey 51 days Sat 27/8/22 Tue 25/10/22 Tue 20/9/22 Thu 17/11/22 20 days
27 Tree survey and assessment by Arborist 30 days Sat 27/8/22 Fri 30/9/22 Tue 20/9/22 Mon 24/10/22 20 days
28 Submission to HDB/Nparks for tree felling 7 days Sat 1/10/22 Sat 8/10/22 Tue 25/10/22 Tue 1/11/22 20 days
29 Approval by HDB/Nparks 14 days Mon 10/10/22 Tue 25/10/22 Wed 2/11/22 Thu 17/11/22 20 days
30 Temporary Site Access Application 51 days Sat 27/8/22 Tue 25/10/22 Tue 20/9/22 Thu 17/11/22 20 days
31 Design of temporary site access 30 days Sat 27/8/22 Fri 30/9/22 Tue 20/9/22 Mon 24/10/22 20 days
32 Road opening application (ROA) 7 days Sat 1/10/22 Sat 8/10/22 Tue 25/10/22 Tue 1/11/22 20 days
33 ROA approval by LTA 14 days Mon 10/10/22 Tue 25/10/22 Wed 2/11/22 Thu 17/11/22 20 days
34  Completion Prelimaries for commencement of site work 1 day Wed 16/11/22 Wed 16/11/22 Fri 18/11/22 Fri 18/11/22 2 days 16/11
35 Design & Submission 246 days Sat 27/8/22 Fri 9/6/23 Wed 31/8/22 Sat 23/9/23 3 days
36 ECM Design & Submission 46 days Sat 27/8/22 Wed 19/10/22 Fri 2/9/22 Tue 25/10/22 5 days
37 Design and preparation of ECM plan 25 days Sat 27/8/22 Sat 24/9/22 Fri 2/9/22 Fri 30/9/22 5 days
38 Submission of ECM plan to PUB 7 days Mon 26/9/22 Mon 3/10/22 Sat 1/10/22 Sat 8/10/22 5 days
39 Approval by PUB 14 days Tue 4/10/22 Wed 19/10/22 Mon 10/10/22 Tue 25/10/22 5 days
40 [Sewer] Design & Submission 98 days Sat 27/8/22 Mon 19/12/22 Wed 31/8/22 Thu 22/12/22 3 days
41 ERSS Design 70 days Sat 27/8/22 Wed 16/11/22 Wed 31/8/22 Sat 19/11/22 3 days
42 BCA Submission / Approval 28 days Thu 17/11/22 Mon 19/12/22 Mon 21/11/22 Thu 22/12/22 3 days
43 [Z1] Design & Submission 73 days Mon 14/11/22 Mon 6/2/23 Mon 28/11/22 Mon 20/2/23 12 days
44 [Z1] Submission of ERSS Design 72 days Mon 14/11/22 Sat 4/2/23 Mon 28/11/22 Sat 18/2/23 12 days
45 Preparation of ERSS design for drainage work 35 days Mon 14/11/22 Fri 23/12/22 Mon 28/11/22 Fri 6/1/23 12 days
46 Submission of ERSS design for drainage work 7 days Sat 24/12/22 Sat 31/12/22 Sat 7/1/23 Sat 14/1/23 12 days
47 Approval of ERSS design by BCA 30 days Mon 2/1/23 Sat 4/2/23 Mon 16/1/23 Sat 18/2/23 12 days
48 [Z1] Submission of Traffic Diversion Plan 61 days Fri 25/11/22 Fri 3/2/23 Sat 10/12/22 Sat 18/2/23 13 days
49 Preparation of traffic diversion plan for drainage work 40 days Fri 25/11/22 Tue 10/1/23 Sat 10/12/22 Wed 25/1/23 13 days
50 Submission of traffic diversion plan for drainage work 7 days Wed 11/1/23 Wed 18/1/23 Thu 26/1/23 Thu 2/2/23 13 days
51 Approval of traffic diversion by LTA 14 days Thu 19/1/23 Fri 3/2/23 Fri 3/2/23 Sat 18/2/23 13 days
52 Completion of Z1 design and submission 1 day Mon 6/2/23 Mon 6/2/23 Mon 20/2/23 Mon 20/2/23 12 days
53 [Z2] Design & Submission 93 days Sat 15/10/22 Tue 31/1/23 Sat 29/10/22 Tue 21/2/23 12 days
54 [Z2] Submission of ERSS Design 92 days Sat 15/10/22 Mon 30/1/23 Sat 29/10/22 Mon 20/2/23 12 days
55 Preparation of ERSS design for retaining wall & drain work 55 days Sat 15/10/22 Sat 17/12/22 Sat 29/10/22 Sat 31/12/22 12 days
56 Submission of ERSS design for retaining wall & drain work 7 days Mon 19/12/22 Mon 26/12/22 Mon 9/1/23 Mon 16/1/23 18 days
57 Approval of ERSS design by BCA 30 days Tue 27/12/22 Mon 30/1/23 Tue 17/1/23 Mon 20/2/23 18 days
58 Completion of Z2 design and submission 1 day Tue 31/1/23 Tue 31/1/23 Tue 21/2/23 Tue 21/2/23 18 days
59 [Z3] Design & Submission 93 days Thu 22/9/22 Sat 7/1/23 Thu 6/10/22 Mon 23/1/23 12 days
60 [Z3] Submission of ERSS Design 92 days Thu 22/9/22 Fri 6/1/23 Thu 6/10/22 Sat 21/1/23 12 days
61 Preparation of ERSS design for retaining wall & drain work 55 days Thu 22/9/22 Thu 24/11/22 Thu 6/10/22 Thu 8/12/22 12 days
62 Submission of ERSS design for retaining wall & drain work 7 days Fri 25/11/22 Fri 2/12/22 Sat 10/12/22 Sat 17/12/22 13 days
63 Approval of ERSS design by BCA 30 days Sat 3/12/22 Fri 6/1/23 Mon 19/12/22 Sat 21/1/23 13 days
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
64 Completion of Z3 design and submission 1 day Sat 7/1/23 Sat 7/1/23 Mon 23/1/23 Mon 23/1/23 13 days
65 [Z4] Design & Submission 199 days Fri 21/10/22 Fri 9/6/23 Thu 12/1/23 Sat 23/9/23 71 days
66 Temporary protection shed for PCN (below bridge) 60 days Wed 7/12/22 Tue 14/2/23 Thu 12/1/23 Wed 22/3/23 31 days
67 Working platform for bridge pier, cantilever slab, floating platform 30 days Wed 7/12/22 Tue 10/1/23 Thu 16/2/23 Wed 22/3/23 61 days
68 Scouring Protection for bridge pier over river including submission and 30 days Fri 21/10/22 Thu 24/11/22 Thu 16/2/23 Wed 22/3/23 101 days
approval from relevant authorities
69 Beam launching bearing capacity check & Approval by HDB 60 days Sat 1/4/23 Fri 9/6/23 Mon 17/7/23 Sat 23/9/23 91 days
70 [Z5] Design & Submission 118 days Mon 5/9/22 Thu 19/1/23 Sat 17/9/22 Wed 1/2/23 11 days
71 [Z5BKD] Submission of ERSS Design 87 days Mon 5/9/22 Wed 14/12/22 Sat 17/9/22 Tue 31/1/23 11 days
72 Preparation of ERSS design for retaining wall & drain work 50 days Mon 5/9/22 Tue 1/11/22 Sat 17/9/22 Mon 14/11/22 11 days
73 Submission of ERSS design for retaining wall & drain work 7 days Wed 2/11/22 Wed 9/11/22 Tue 20/12/22 Tue 27/12/22 41 days
74 Approval of ERSS design by BCA 30 days Thu 10/11/22 Wed 14/12/22 Wed 28/12/22 Tue 31/1/23 41 days
75 [Z5BKD] Submission of Drain Diversion Plan 87 days Mon 10/10/22 Wed 18/1/23 Sat 22/10/22 Tue 31/1/23 11 days
76 Preparation of drain diversion plan 50 days Mon 10/10/22 Tue 6/12/22 Sat 22/10/22 Mon 19/12/22 11 days
77 Submission of drain diversion plan 7 days Wed 7/12/22 Wed 14/12/22 Tue 20/12/22 Tue 27/12/22 11 days
78 Approval of drain diversion plan by PUB 30 days Thu 15/12/22 Wed 18/1/23 Wed 28/12/22 Tue 31/1/23 11 days
79 Completion of Z5 BKD design and submission 1 day Thu 19/1/23 Thu 19/1/23 Wed 1/2/23 Wed 1/2/23 11 days
80 Construction 460 days Mon 5/9/22 Fri 23/2/24 Sat 17/9/22 Thu 25/4/24 11 days
81 Sewer Diversion 198 days Tue 4/10/22 Tue 23/5/23 Tue 1/11/22 Tue 23/5/23 1 day
82 [Sewer] Preliminary 17 days Tue 4/10/22 Sat 22/10/22 Tue 1/11/22 Sat 19/11/22 24 days
83 Soil Investigation 17 days Tue 4/10/22 Sat 22/10/22 Tue 1/11/22 Sat 19/11/22 24 days
84 Sewer Pipe 900mm dia 17 days Tue 4/10/22 Sat 22/10/22 Tue 1/11/22 Sat 19/11/22 24 days
85 NMH3&4 5 days Tue 4/10/22 Sat 8/10/22 Tue 1/11/22 Sat 5/11/22 24 days
86 NMH6 5 days Tue 4/10/22 Sat 8/10/22 Tue 1/11/22 Sat 5/11/22 24 days
87 NMH1&2 5 days Mon 10/10/22 Fri 14/10/22 Mon 7/11/22 Fri 11/11/22 24 days
88 NMH5 5 days Mon 10/10/22 Fri 14/10/22 Mon 7/11/22 Fri 11/11/22 24 days
89 Lab test and reporting 7 days Sat 15/10/22 Sat 22/10/22 Sat 12/11/22 Sat 19/11/22 24 days
90 Sewer Pipe 1500mm dia 17 days Tue 4/10/22 Sat 22/10/22 Tue 1/11/22 Sat 19/11/22 24 days
91 NMH7 5 days Tue 4/10/22 Sat 8/10/22 Tue 1/11/22 Sat 5/11/22 24 days
92 NMH8 5 days Tue 4/10/22 Sat 8/10/22 Tue 1/11/22 Sat 5/11/22 24 days
93 NMH10 5 days Mon 10/10/22 Fri 14/10/22 Mon 7/11/22 Fri 11/11/22 24 days
94 NMH9 5 days Mon 10/10/22 Fri 14/10/22 Mon 7/11/22 Fri 11/11/22 24 days
95 Lab test and reporting 7 days Sat 15/10/22 Sat 22/10/22 Sat 12/11/22 Sat 19/11/22 24 days
96 [Sewer] Construction 198 days Tue 4/10/22 Tue 23/5/23 Fri 25/11/22 Tue 23/5/23 1 day
97 Sewer Pipe 900mm dia 198 days Tue 4/10/22 Tue 23/5/23 Fri 25/11/22 Tue 23/5/23 1 day
98 NMH3 & NMH4 137 days Tue 4/10/22 Sat 11/3/23 Fri 25/11/22 Thu 6/4/23 22 days
99 Site Establishment 14 days Tue 4/10/22 Wed 19/10/22 Fri 25/11/22 Sat 10/12/22 45 days
100 Caisson NMH4 10 days Tue 20/12/22 Fri 30/12/22 Fri 23/12/22 Tue 3/1/23 3 days
101 Caisson NMH3 12 days Sat 31/12/22 Fri 13/1/23 Fri 6/1/23 Thu 19/1/23 5 days
102 RC Pile NMH4 (0.2x0.2x11.7m) 7 days Sat 31/12/22 Sat 7/1/23 Wed 4/1/23 Wed 11/1/23 3 days
103 Mobilization of Jacking machine 7 days Mon 9/1/23 Mon 16/1/23 Thu 12/1/23 Thu 19/1/23 3 days
104 Pipe Jacking NMH4 to NMH3 (29m) 7 days Tue 17/1/23 Tue 24/1/23 Fri 20/1/23 Fri 27/1/23 3 days
105 Pipe Jacking NMH2 to NMH3 (95m) 14 days Wed 25/1/23 Thu 9/2/23 Sat 28/1/23 Mon 13/2/23 3 days
106 Shaft and Manhole (NMH3) 12 days Fri 10/2/23 Thu 23/2/23 Fri 10/3/23 Thu 23/3/23 24 days
107 Shaft and Manhole (NMH4) 12 days Mon 27/2/23 Sat 11/3/23 Fri 24/3/23 Thu 6/4/23 22 days
108 NMH1 & NMH2 129 days Thu 20/10/22 Sat 18/3/23 Mon 12/12/22 Sat 25/3/23 6 days
109 Site Establishment 14 days Thu 20/10/22 Fri 4/11/22 Mon 12/12/22 Tue 27/12/22 45 days
110 RC Pile NMH1 & NMH2 (0.2x0.2x15.8m) 12 days Tue 20/12/22 Mon 2/1/23 Wed 28/12/22 Tue 10/1/23 7 days
111 Rectangular Shaft NMH1 & NMH2  15 days Tue 3/1/23 Thu 19/1/23 Wed 11/1/23 Fri 27/1/23 7 days
112 Pipe laying NMH1 to NMH2 (6m) 10 days Fri 10/2/23 Tue 21/2/23 Fri 17/2/23 Tue 28/2/23 6 days
113 Shaft and Manhole NMH1 & NMH2 22 days Wed 22/2/23 Sat 18/3/23 Wed 1/3/23 Sat 25/3/23 6 days
114 NMH5 121 days Sat 5/11/22 Sat 25/3/23 Fri 6/1/23 Tue 18/4/23 20 days
115 Site Establishment 14 days Sat 5/11/22 Mon 21/11/22 Fri 6/1/23 Sat 21/1/23 53 days
116 Caisson NMH5 12 days Sat 14/1/23 Fri 27/1/23 Mon 23/1/23 Sat 4/2/23 7 days
117 RC Pile NMH5 (0.2x0.2x5.3m) 7 days Sat 28/1/23 Sat 4/2/23 Mon 6/2/23 Mon 13/2/23 7 days
118 Mobilization of Jacking machine 7 days Tue 22/11/22 Tue 29/11/22 Mon 6/2/23 Mon 13/2/23 65 days
119 Pipe Jacking NMH4 to NMH5 (120m) 14 days Fri 10/2/23 Sat 25/2/23 Tue 14/2/23 Wed 1/3/23 3 days
120 Pipe Jacking NMH5 to NMH6 (120m) 14 days Mon 27/2/23 Tue 14/3/23 Thu 2/3/23 Fri 17/3/23 3 days
121 Shaft and Manhole NMH5 10 days Wed 15/3/23 Sat 25/3/23 Fri 7/4/23 Tue 18/4/23 20 days
122 NMH6 & EXT'G MH8 166 days Tue 4/10/22 Fri 14/4/23 Fri 9/12/22 Tue 18/4/23 3 days
123 Site Establishment 14 days Tue 4/10/22 Wed 19/10/22 Fri 9/12/22 Sat 24/12/22 57 days
124 Rectangular shaft NMH6 joint to EXT'G MH8 15 days Tue 20/12/22 Thu 5/1/23 Mon 26/12/22 Wed 11/1/23 5 days
125 Type 4A RW (BKD Eastbound/CH0+224 ‐ CH0+238) 42 days Fri 6/1/23 Thu 23/2/23 Thu 12/1/23 Wed 1/3/23 5 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 2
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
126 Excavation of RW base 10 days Fri 6/1/23 Tue 17/1/23 Thu 12/1/23 Mon 23/1/23 5 days
127 RW Base 10 days Wed 18/1/23 Sat 28/1/23 Tue 24/1/23 Fri 3/2/23 5 days
128 RW until soffit of NMH6 and EXT'G MH8 15 days Mon 30/1/23 Wed 15/2/23 Sat 4/2/23 Tue 21/2/23 5 days
129 Formwork removal and backfill until soffit of NMH6 7 days Thu 16/2/23 Thu 23/2/23 Wed 22/2/23 Wed 1/3/23 5 days
130 Pipe laying NMH6 to EXT'G MH8 (12m) 7 days Wed 15/3/23 Wed 22/3/23 Sat 18/3/23 Sat 25/3/23 3 days
131 Shaft and Manhole with RW 20 days Thu 23/3/23 Fri 14/4/23 Mon 27/3/23 Tue 18/4/23 3 days
132 Comission of new 900mm dia sewer pipe 30 days Sat 15/4/23 Fri 19/5/23 Wed 19/4/23 Tue 23/5/23 3 days
133 Completion of new 900mm dia sewer pipe 0 days Tue 23/5/23 Tue 23/5/23 Tue 23/5/23 Tue 23/5/23 1 day 23/5
134 Sewer Pipe 1500mm dia 198 days Tue 4/10/22 Tue 23/5/23 Fri 9/12/22 Tue 23/5/23 1 day
135 NMH7, NMH8 & EXT'G MH10 146 days Tue 4/10/22 Wed 22/3/23 Fri 9/12/22 Thu 6/4/23 13 days
136 Site establishment 20 days Tue 4/10/22 Wed 26/10/22 Fri 9/12/22 Sat 31/12/22 57 days
137 Caisson NMH7 12 days Tue 20/12/22 Mon 2/1/23 Mon 2/1/23 Sat 14/1/23 11 days
138 Caisson NMH 8 10 days Tue 3/1/23 Fri 13/1/23 Wed 18/1/23 Sat 28/1/23 13 days
139 Caisson EXT'G MH10 8 days Sat 14/1/23 Mon 23/1/23 Mon 30/1/23 Tue 7/2/23 13 days
140 Mobilization of Jacking machine 7 days Tue 24/1/23 Tue 31/1/23 Wed 8/2/23 Wed 15/2/23 13 days
141 Pipe Jacking NMH7 to NMH8 (46m) 8 days Wed 1/2/23 Thu 9/2/23 Thu 16/2/23 Fri 24/2/23 13 days
142 Pipe Jacking NMH7 to EXT'G MH10 (35m) 8 days Fri 10/2/23 Sat 18/2/23 Sat 25/2/23 Mon 6/3/23 13 days
143 Shaft and Manhole NMH8 20 days Fri 10/2/23 Sat 4/3/23 Sat 25/2/23 Mon 20/3/23 13 days
144 Shaft and Manhole NMH7 15 days Mon 6/3/23 Wed 22/3/23 Tue 21/3/23 Thu 6/4/23 13 days
145 NMH9 136 days Thu 27/10/22 Mon 3/4/23 Mon 30/1/23 Tue 18/4/23 13 days
146 Site establishment 14 days Thu 27/10/22 Fri 11/11/22 Mon 30/1/23 Tue 14/2/23 81 days
147 Caisson NMH9 10 days Tue 24/1/23 Fri 3/2/23 Wed 15/2/23 Sat 25/2/23 19 days
148 Mobilization of Jacking machine 7 days Sat 4/2/23 Sat 11/2/23 Mon 27/2/23 Mon 6/3/23 19 days
149 Pipe Jacking NMH10 to NMH9 (42m) 10 days Wed 22/2/23 Sat 4/3/23 Tue 7/3/23 Fri 17/3/23 11 days
150 Shaft and Manhole NMH9 10 days Thu 23/3/23 Mon 3/4/23 Fri 7/4/23 Tue 18/4/23 13 days
151 NMH10 & EXT'G MH9 158 days Tue 4/10/22 Wed 5/4/23 Fri 16/12/22 Tue 18/4/23 11 days
152 Site establishment 14 days Tue 4/10/22 Wed 19/10/22 Fri 16/12/22 Sat 31/12/22 63 days
153 Rectangular shaft NMH10 joint to EXT'G MH9 25 days Tue 20/12/22 Tue 17/1/23 Mon 2/1/23 Mon 30/1/23 11 days
154 Retaining wall type 4A 30 days Wed 18/1/23 Tue 21/2/23 Tue 31/1/23 Mon 6/3/23 11 days
155 Excavation of RW base 10 days Wed 18/1/23 Sat 28/1/23 Tue 31/1/23 Fri 10/2/23 11 days
156 RW Base 7 days Mon 30/1/23 Mon 6/2/23 Sat 11/2/23 Sat 18/2/23 11 days
157 RW until soffit of NMH10 and EXT'G MH9 8 days Tue 7/2/23 Wed 15/2/23 Mon 20/2/23 Tue 28/2/23 11 days
158 Formwork removal and backfill until soffit of NMH10 5 days Thu 16/2/23 Tue 21/2/23 Wed 1/3/23 Mon 6/3/23 11 days
159 Pipe laying NMH10 to EXT'G MH9 (12m) 7 days Mon 6/3/23 Mon 13/3/23 Sat 18/3/23 Sat 25/3/23 11 days
160 Shaft and Manhole NMH10 with RW 20 days Tue 14/3/23 Wed 5/4/23 Mon 27/3/23 Tue 18/4/23 11 days
161 Comission of new 1500mm dia sewer pipe 30 days Thu 6/4/23 Wed 10/5/23 Wed 19/4/23 Tue 23/5/23 11 days
162 Completion of new 1500mm dia sewer pipe 0 days Tue 23/5/23 Tue 23/5/23 Tue 23/5/23 Tue 23/5/23 1 day 23/5
163 Zone 1 388 days Thu 24/11/22 Tue 20/2/24 Wed 30/11/22 Tue 20/2/24 1 day
164 [Z1] Preliminaries 46 days Thu 22/12/22 Mon 13/2/23 Thu 29/12/22 Mon 20/2/23 6 days
165 [Z1] Utitlity service diversion (by others) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
166 Starhub (SH) cables (YCK Eastbound/CH0 ‐ CH0+070) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
167 6P6/22KV High voltage (HV) cables (YCK Eastbound/CH0+100 ‐  45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
CH0+110)
168 Starhub (SH) cables (YCK Eastbound/CH0+100 ‐ CH0+110) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
169 Starhub (SH) cables (YCK Eastbound/CH0+140 ‐ CH0+190) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
170 Low voltage (LV) cables (YCK Eastbound/CH0+140 ‐ CH0+190) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
171 6P6/22KV High voltage (HV) cables (YCK Centre Median/CH0 ‐  45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
CH0+158)
172 6P6/22KV High voltage (HV) cables (YCK Centre Median/CH0+190 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
‐ CH0+325)
173 Lamp post & public lighting cables relocation (BKD/CH0+048) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
174 Low voltage (LV) cables (BKD Westbound/CH0 ‐ CH0+050) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
175 6P6/22KV High voltage (HV) cables (BKD Westbound/CH0 ‐  45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
CH0+050)
176 6P6/22KV High voltage (HV) cables (GLD left turn into YCK) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
177 Low voltage (LV) cables cables (GLD left turn into YCK) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
178 Starhub (SH) cables  (GLD left turn into YCK) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
179 Singtel (ST) cables  (GLD left turn into YCK) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
180 [Z1] Utitlity service diversion (by KTC) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
181 Water pipe (YCK Eastbound/CH0+100 ‐ CH0+110) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
182 Water pipe (GLD left turn into YCK) 45 days Thu 22/12/22 Sat 11/2/23 Thu 29/12/22 Sat 18/2/23 6 days
183 Completion of utility services diversion 1 day Mon 13/2/23 Mon 13/2/23 Mon 20/2/23 Mon 20/2/23 6 days
184 [Z1] Construction 383 days Thu 24/11/22 Tue 13/2/24 Wed 30/11/22 Tue 20/2/24 5 days
185 [Z1A] (YIO CHU KANG ROAD/CH0 ‐ CH0+100) 233 days Thu 24/11/22 Tue 22/8/23 Wed 30/11/22 Tue 29/8/23 5 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 3
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
186 [Z1A] Site establishment 18 days Thu 24/11/22 Wed 14/12/22 Wed 30/11/22 Tue 20/12/22 5 days
187 [Z1A] Removal of existing trees, road kerb and railing 15 days Thu 15/12/22 Sat 31/12/22 Wed 21/12/22 Fri 6/1/23 5 days
188 [Z1A] Drain  99 days Tue 14/2/23 Thu 8/6/23 Tue 21/2/23 Wed 5/7/23 6 days
189 [Z1A] Covered Drain 600mm (YCK Eastbound/CH0 ‐ CH0+103) 61 days Tue 14/2/23 Tue 25/4/23 Tue 21/2/23 Tue 2/5/23 6 days

190 Jack‐in pile machine mobilization 5 days Tue 14/2/23 Sat 18/2/23 Tue 21/2/23 Sat 25/2/23 6 days


191 Jack‐in Pile (0.15x0.15x12.2m) 18 days Mon 20/2/23 Sat 11/3/23 Mon 27/2/23 Sat 18/3/23 6 days
192 Excavation of drain base 10 days Mon 13/3/23 Thu 23/3/23 Mon 20/3/23 Thu 30/3/23 6 days
193 Drain base, wall and top slab 28 days Fri 24/3/23 Tue 25/4/23 Fri 31/3/23 Tue 2/5/23 6 days
194 [Z1A] Covered Drain 600mm (YCK Centre Median/CH0+190 ‐  76 days Mon 13/3/23 Thu 8/6/23 Sat 8/4/23 Wed 5/7/23 23 days
CH0+325)
195 Jack‐in Pile (0.15x0.15x19.9m) 28 days Mon 13/3/23 Thu 13/4/23 Sat 8/4/23 Wed 10/5/23 23 days
196 Excavation of drain base 10 days Fri 14/4/23 Tue 25/4/23 Thu 11/5/23 Mon 22/5/23 23 days
197 Drain base, wall and top slab 38 days Wed 26/4/23 Thu 8/6/23 Tue 23/5/23 Wed 5/7/23 23 days
198 [Z1A] Bus Shelter & Road  77 days Wed 26/4/23 Mon 24/7/23 Wed 3/5/23 Mon 31/7/23 6 days
199 [Z1A] Bus Shelter No.1 77 days Wed 26/4/23 Mon 24/7/23 Wed 3/5/23 Mon 31/7/23 6 days
200 Structure 76 days Wed 26/4/23 Sat 22/7/23 Wed 3/5/23 Sat 29/7/23 6 days
209 M&E  10 days Wed 12/7/23 Sat 22/7/23 Wed 19/7/23 Sat 29/7/23 6 days
212 Completion of bus shelter No.1 1 day Mon 24/7/23 Mon 24/7/23 Mon 31/7/23 Mon 31/7/23 6 days
213 [Z1A] Road (YCK Eastbound/CH0 ‐ CH0+100) 45 days Mon 8/5/23 Wed 28/6/23 Mon 15/5/23 Thu 13/7/23 6 days
214 Underground utility services 10 days Mon 8/5/23 Thu 18/5/23 Mon 15/5/23 Thu 25/5/23 6 days
215 Subgrade and sub‐base 10 days Fri 19/5/23 Tue 30/5/23 Fri 26/5/23 Tue 6/6/23 6 days
216 Kerb, drop‐inlet chamber and scupper pipe 10 days Wed 31/5/23 Sat 10/6/23 Wed 7/6/23 Sat 17/6/23 6 days
217 Rigid pavement 15 days Mon 12/6/23 Wed 28/6/23 Tue 27/6/23 Thu 13/7/23 13 days
218 [Z1A] Ancillary Work 15 days Thu 29/6/23 Sat 15/7/23 Fri 14/7/23 Mon 31/7/23 13 days
219 Railing 15 days Thu 29/6/23 Sat 15/7/23 Fri 14/7/23 Mon 31/7/23 13 days
220 Turfing and tree planting 15 days Thu 29/6/23 Sat 15/7/23 Fri 14/7/23 Mon 31/7/23 13 days
221 Traffic signage 15 days Thu 29/6/23 Sat 15/7/23 Fri 14/7/23 Mon 31/7/23 13 days
222 [Z1A] Comission of Bus Shelter No. 1 15 days Tue 25/7/23 Thu 10/8/23 Tue 1/8/23 Thu 17/8/23 6 days
223 [Z1A] Demolition of existing bus shelter 10 days Fri 11/8/23 Tue 22/8/23 Fri 18/8/23 Tue 29/8/23 6 days
224 [Z1B]  (YIO CHU KANG ROAD/CH0+100 ‐ CH0+353) 202 days Thu 24/11/22 Mon 17/7/23 Mon 2/1/23 Sat 29/7/23 11 days
225 [Z1B] Site establishment 20 days Thu 24/11/22 Fri 16/12/22 Mon 2/1/23 Tue 24/1/23 33 days
226 [Z1B] Removal of existing trees, road kerb and railing 28 days Sat 17/12/22 Wed 18/1/23 Wed 25/1/23 Sat 25/2/23 33 days
227 [Z1B] Retaining wall 29 days Tue 14/2/23 Sat 18/3/23 Mon 27/2/23 Fri 31/3/23 11 days
228 [Z1B] RW Type 1 (BKD Westbound/CH0+030 ‐ CH0+040) 29 days Tue 14/2/23 Sat 18/3/23 Mon 27/2/23 Fri 31/3/23 11 days
229 Excavation and diversion of existing drain  7 days Tue 14/2/23 Tue 21/2/23 Mon 27/2/23 Mon 6/3/23 11 days
230 RW base (5.5m wide) 7 days Wed 22/2/23 Wed 1/3/23 Tue 7/3/23 Tue 14/3/23 11 days
231 RW wall (4.5m height) 10 days Thu 2/3/23 Mon 13/3/23 Wed 15/3/23 Sat 25/3/23 11 days
232 Formwork removal and backfilling 5 days Tue 14/3/23 Sat 18/3/23 Mon 27/3/23 Fri 31/3/23 11 days
233 [Z1B] Drain  111 days Tue 14/2/23 Thu 22/6/23 Mon 6/3/23 Wed 5/7/23 11 days
234 [Z1B] Covered Drain 1100mm (BKD Eastbound/CH0 ‐  52 days Tue 14/2/23 Fri 14/4/23 Mon 6/3/23 Fri 26/5/23 17 days
CH0+050)
235 Jack‐in pile machine mobilisation 5 days Tue 14/2/23 Sat 18/2/23 Mon 6/3/23 Fri 10/3/23 17 days
236 Jack‐in Pile (0.15x0.15x13.16m) 12 days Mon 20/2/23 Sat 4/3/23 Sat 11/3/23 Fri 24/3/23 17 days
237 Excavation of drain base 10 days Mon 6/3/23 Thu 16/3/23 Mon 17/4/23 Thu 27/4/23 36 days
238 Drain base, wall and top slab 25 days Fri 17/3/23 Fri 14/4/23 Fri 28/4/23 Fri 26/5/23 36 days
239 [Z1B] Covered Drain 600mm (BKD Centre Median/CH0 ‐  57 days Mon 6/3/23 Wed 10/5/23 Thu 4/5/23 Wed 21/6/23 36 days
CH0+050)
240 Jack‐in Pile (0.15x0.15x10.5m) 10 days Mon 6/3/23 Thu 16/3/23 Thu 4/5/23 Mon 15/5/23 51 days
241 Excavation of drain base 10 days Fri 17/3/23 Tue 28/3/23 Tue 16/5/23 Fri 26/5/23 51 days
242 Drain base, wall and top slab 22 days Sat 15/4/23 Wed 10/5/23 Sat 27/5/23 Wed 21/6/23 36 days
243 [Z1B] Covered Drain 600mm (BKD left turn into YCK/CH0+010 59 days Fri 17/3/23 Wed 24/5/23 Thu 25/5/23 Wed 5/7/23 36 days
‐ CH0+020)
244 Jack‐in Pile (0.15x0.15x19.9m) 14 days Fri 17/3/23 Sat 1/4/23 Thu 25/5/23 Fri 9/6/23 59 days
245 Excavation of drain base 10 days Mon 3/4/23 Thu 13/4/23 Sat 10/6/23 Wed 21/6/23 59 days
246 Drain base, wall and top slab 12 days Thu 11/5/23 Wed 24/5/23 Thu 22/6/23 Wed 5/7/23 36 days
247 [Z1B] Covered Drain 1100mm (BKD Westbound/CH0+030 ‐  12 days Mon 20/3/23 Sat 1/4/23 Sat 1/4/23 Fri 14/4/23 11 days
CH0+040)
248 Drain base, wall and top slab 12 days Mon 20/3/23 Sat 1/4/23 Sat 1/4/23 Fri 14/4/23 11 days
249 [Z1B] Sump 1700x1700mm (Z2) 46 days Mon 20/2/23 Thu 13/4/23 Sat 11/3/23 Wed 26/4/23 11 days
250 Jack‐in pile (4 pts, 200x200mm X16.1m) 10 days Mon 20/2/23 Thu 2/3/23 Sat 11/3/23 Wed 22/3/23 17 days
251 Sump base, wall and top slab 10 days Mon 3/4/23 Thu 13/4/23 Sat 15/4/23 Wed 26/4/23 11 days
252 [Z1B] Sump 1200x1200mm (Z1) 46 days Fri 3/3/23 Tue 25/4/23 Thu 23/3/23 Mon 8/5/23 11 days
253 Jack‐in pile (4 pts, 200x200mm X 16.3m) 10 days Fri 3/3/23 Tue 14/3/23 Thu 23/3/23 Mon 3/4/23 17 days
254 Sump base, wall and top slab 10 days Fri 14/4/23 Tue 25/4/23 Thu 27/4/23 Mon 8/5/23 11 days
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 4
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
255 [Z1B] Box culvert 0.6x0.6x8.873m (Z1‐Z2) 91 days Mon 20/2/23 Mon 5/6/23 Sat 11/3/23 Sat 17/6/23 11 days
256 Road diversion 20 days Mon 20/2/23 Tue 14/3/23 Sat 11/3/23 Mon 3/4/23 17 days
257 Jack‐in pile (0.15x0.15x16.3m) 30 days Wed 15/3/23 Tue 18/4/23 Tue 4/4/23 Mon 8/5/23 17 days
258 Box culvert base, wall and top slab 35 days Wed 26/4/23 Mon 5/6/23 Tue 9/5/23 Sat 17/6/23 11 days
259 [Z1B] Covered Drain 600mm (GLD left turn into YCK) 56 days Wed 19/4/23 Thu 22/6/23 Wed 17/5/23 Wed 5/7/23 11 days
260 Jack‐in Pile (34 pts, 0.15x0.15x19.5m) 18 days Wed 19/4/23 Tue 9/5/23 Wed 17/5/23 Tue 6/6/23 24 days
261 Excavation of drain base 10 days Wed 10/5/23 Sat 20/5/23 Wed 7/6/23 Sat 17/6/23 24 days
262 Drain base, wall and top slab 15 days Tue 6/6/23 Thu 22/6/23 Mon 19/6/23 Wed 5/7/23 11 days
263 [Z1B] Road 21 days Fri 23/6/23 Mon 17/7/23 Thu 6/7/23 Sat 29/7/23 11 days
264 [Z1B] GLD to YCK Slip road widening 21 days Fri 23/6/23 Mon 17/7/23 Thu 6/7/23 Sat 29/7/23 11 days
265 [Z1B] YCK left turn into BKD  21 days Fri 23/6/23 Mon 17/7/23 Thu 6/7/23 Sat 29/7/23 11 days
266 [Z1B] YCK right turn into BKD  21 days Fri 23/6/23 Mon 17/7/23 Thu 6/7/23 Sat 29/7/23 11 days
267 [Z1B] BKD right turn into YCK 21 days Fri 23/6/23 Mon 17/7/23 Thu 6/7/23 Sat 29/7/23 11 days
268 [Z1B] BKD left turn into YCK  21 days Fri 23/6/23 Mon 17/7/23 Thu 6/7/23 Sat 29/7/23 11 days
269 [Z1C] New Junction at Yiu Chu Kang Road/Buangkok Drive/ Gerald  181 days Tue 18/7/23 Tue 13/2/24 Mon 31/7/23 Tue 20/2/24 6 days
Drive
270 [Z1C] Foot path diversion 35 days Tue 18/7/23 Sat 26/8/23 Mon 31/7/23 Fri 8/9/23 11 days
271 [Z1C] New traffic crossing at YCK road junction 10 days Tue 18/7/23 Fri 28/7/23 Mon 31/7/23 Thu 10/8/23 11 days
272 [Z1C] Foot path diversion from HDB to GLD 10 days Sat 29/7/23 Wed 9/8/23 Fri 11/8/23 Tue 22/8/23 11 days
273 [Z1C] Hoarding diversion 15 days Sat 29/7/23 Tue 15/8/23 Fri 11/8/23 Mon 28/8/23 11 days
274 [Z1C] Close lane YCK turn into GLD 10 days Wed 16/8/23 Sat 26/8/23 Tue 29/8/23 Fri 8/9/23 11 days
275 [Z1C] Drain 105 days Wed 23/8/23 Fri 22/12/23 Wed 30/8/23 Fri 29/12/23 6 days
276 [Z1C] Sump 1700x1700mm (B3) 20 days Wed 23/8/23 Thu 14/9/23 Wed 30/8/23 Tue 3/10/23 6 days
277 Jack‐in pile (4 pts, 200x200mm X 11.4m) 10 days Wed 23/8/23 Sat 2/9/23 Wed 30/8/23 Sat 9/9/23 6 days
278 Sump base, wall and top slab 10 days Mon 4/9/23 Thu 14/9/23 Fri 22/9/23 Tue 3/10/23 16 days
279 [Z1C] Sump 1700x1700mm (A1) 20 days Mon 4/9/23 Tue 26/9/23 Mon 11/9/23 Sat 14/10/23 6 days
280 Jack‐in pile (0.2x0.2x11.4m) 10 days Mon 4/9/23 Thu 14/9/23 Mon 11/9/23 Thu 21/9/23 6 days
281 Sump base, wall and top slab 10 days Fri 15/9/23 Tue 26/9/23 Wed 4/10/23 Sat 14/10/23 16 days
282 [Z1C] Box culvert 1.1x1.6x18m (B3‐A1) 80 days Wed 23/8/23 Thu 23/11/23 Wed 30/8/23 Thu 30/11/23 6 days
283 Road diversion 20 days Wed 23/8/23 Thu 14/9/23 Wed 30/8/23 Thu 21/9/23 6 days
284 Jack‐in pile (0.15x0.15x21.1m) 20 days Fri 15/9/23 Sat 7/10/23 Fri 22/9/23 Sat 14/10/23 6 days
285 Box culvert base and wall 20 days Mon 9/10/23 Tue 31/10/23 Mon 16/10/23 Tue 7/11/23 6 days
286 Approach slab  20 days Wed 1/11/23 Thu 23/11/23 Wed 8/11/23 Thu 30/11/23 6 days
287 [Z1C] Covered Drain 1100mm (YCK Centre Median/CH0 ‐  65 days Mon 9/10/23 Fri 22/12/23 Sat 21/10/23 Fri 29/12/23 6 days
CH0+158)
288 Jack‐in Pile (0.15x0.15x14.5m) 25 days Mon 9/10/23 Mon 6/11/23 Sat 21/10/23 Sat 18/11/23 11 days
289 Excavation of drain base 10 days Tue 7/11/23 Fri 17/11/23 Mon 20/11/23 Thu 30/11/23 11 days
290 Drain base, wall and top slab 25 days Fri 24/11/23 Fri 22/12/23 Fri 1/12/23 Fri 29/12/23 6 days
291 [Z1C] Sump 1200x1200mm (U1) 25 days Mon 28/8/23 Mon 25/9/23 Sat 9/9/23 Sat 7/10/23 11 days
292 Jack‐in pile (0.2x0.2x19.6m) 10 days Mon 28/8/23 Thu 7/9/23 Sat 9/9/23 Wed 20/9/23 11 days
293 Sump base, wall and top slab 15 days Fri 8/9/23 Mon 25/9/23 Thu 21/9/23 Sat 7/10/23 11 days
294 [Z1C] Sump 1700x1700mm (U2) 30 days Fri 8/9/23 Thu 12/10/23 Wed 27/9/23 Wed 25/10/23 11 days
295 Jack‐in pile (0.2x0.2x19.1m) 10 days Fri 8/9/23 Tue 19/9/23 Wed 27/9/23 Sat 7/10/23 16 days
296 Sump base, wall and top slab 15 days Tue 26/9/23 Thu 12/10/23 Mon 9/10/23 Wed 25/10/23 11 days
297 [Z1C] Box culvert 0.6x0.6x13m (U1‐U2) 35 days Wed 20/9/23 Mon 30/10/23 Mon 9/10/23 Sat 11/11/23 11 days
298 Jack‐in pile (14pts, 150x150mm x 19.9m) 12 days Wed 20/9/23 Tue 3/10/23 Mon 9/10/23 Sat 21/10/23 16 days
299 Box culvert base, wall and top slab 15 days Fri 13/10/23 Mon 30/10/23 Thu 26/10/23 Sat 11/11/23 11 days
300 [Z1C] Coverd Drain 600mm (BKD left turn into YCK/CH0+020 ‐ 35 days Wed 4/10/23 Mon 13/11/23 Mon 23/10/23 Sat 25/11/23 11 days
CH0+026)
301 Jack‐in Pile (150x150mm x19.9m) 10 days Wed 4/10/23 Sat 14/10/23 Mon 23/10/23 Thu 2/11/23 16 days
302 Excavation of drain base 8 days Mon 16/10/23 Tue 24/10/23 Fri 3/11/23 Sat 11/11/23 16 days
303 Drain base, wall and top slab 12 days Tue 31/10/23 Mon 13/11/23 Mon 13/11/23 Sat 25/11/23 11 days
304 [Z1C] Covered Drain 1100mm (BKD Westbound/CH0‐010 ‐  37 days Mon 16/10/23 Mon 27/11/23 Mon 6/11/23 Sat 9/12/23 11 days
CH0+030)
305 Jack‐in Pile (0.15x0.15x19.9m) 10 days Mon 16/10/23 Thu 26/10/23 Mon 6/11/23 Thu 16/11/23 18 days
306 Excavation of drain base 8 days Fri 27/10/23 Sat 4/11/23 Fri 17/11/23 Sat 25/11/23 18 days
307 Drain base, wall and top slab 12 days Tue 14/11/23 Mon 27/11/23 Mon 27/11/23 Sat 9/12/23 11 days
308 [Z1C] Covered Drain 1100mm (BKD Eastbound/CH0‐010 ‐  39 days Fri 27/10/23 Mon 11/12/23 Mon 20/11/23 Sat 23/12/23 11 days
CH0‐016)
309 Jack‐in Pile (0.15x0.15x12.2m) 10 days Fri 27/10/23 Tue 7/11/23 Mon 20/11/23 Thu 30/11/23 20 days
310 Excavation of drain base 8 days Wed 8/11/23 Thu 16/11/23 Fri 1/12/23 Sat 9/12/23 20 days
311 Drain base, wall and top slab 12 days Tue 28/11/23 Mon 11/12/23 Mon 11/12/23 Sat 23/12/23 11 days
312 [Z1C] Road 30 days Tue 12/12/23 Mon 15/1/24 Sat 30/12/23 Mon 22/1/24 6 days
313 YCK right turn into BKD road construction 20 days Tue 12/12/23 Wed 3/1/24 Sat 30/12/23 Mon 22/1/24 16 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 5
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
314 BKD right turn into YCK road construction 20 days Tue 12/12/23 Wed 3/1/24 Sat 30/12/23 Mon 22/1/24 16 days
315 YCK left turn into BKD road construction 20 days Sat 23/12/23 Mon 15/1/24 Sat 30/12/23 Mon 22/1/24 6 days
316 [Z1C] Linkway 50 days Tue 12/12/23 Wed 7/2/24 Mon 25/12/23 Tue 20/2/24 11 days
317 Linkway Footing 25 days Tue 12/12/23 Tue 9/1/24 Mon 25/12/23 Mon 22/1/24 11 days
318 Linkway column and roof 25 days Wed 10/1/24 Wed 7/2/24 Tue 23/1/24 Tue 20/2/24 11 days
319 [Z1C] Ancillary works 25 days Tue 16/1/24 Tue 13/2/24 Tue 23/1/24 Tue 20/2/24 6 days
320 Railing 25 days Tue 16/1/24 Tue 13/2/24 Tue 23/1/24 Tue 20/2/24 6 days
321 Turfing and tree planting 25 days Tue 16/1/24 Tue 13/2/24 Tue 23/1/24 Tue 20/2/24 6 days
322 Traffic signage 25 days Tue 16/1/24 Tue 13/2/24 Tue 23/1/24 Tue 20/2/24 6 days
323 Traffic light 25 days Tue 16/1/24 Tue 13/2/24 Tue 23/1/24 Tue 20/2/24 6 days
324 Lamp post 25 days Tue 16/1/24 Tue 13/2/24 Tue 23/1/24 Tue 20/2/24 6 days
325 [Z1] Completion of Zone 1 0 days Tue 20/2/24 Tue 20/2/24 Tue 20/2/24 Tue 20/2/24 1 day 20/2
326 Zone 2 390 days Thu 24/11/22 Thu 22/2/24 Wed 30/11/22 Thu 22/2/24 1 day
327 [Z2] Preliminaries 46 days Thu 22/12/22 Mon 13/2/23 Fri 30/12/22 Tue 21/2/23 7 days
328 [Z2] Utitlity service diversion (by others) 45 days Thu 22/12/22 Sat 11/2/23 Fri 30/12/22 Mon 20/2/23 7 days
329 6P6/22KV High voltage (HV) cables (FR Northbound/CH0+030 ‐  45 days Thu 22/12/22 Sat 11/2/23 Fri 30/12/22 Mon 20/2/23 7 days
CH0+100)
330 Gas pipe (FR Northbound/CH0+080 ‐ CH0+110) 45 days Thu 22/12/22 Sat 11/2/23 Fri 30/12/22 Mon 20/2/23 7 days
331 Singtel (ST) cables (FR Northbound/CH0+030 ‐ CH0+100) 45 days Thu 22/12/22 Sat 11/2/23 Fri 30/12/22 Mon 20/2/23 7 days
332 Low voltage (LV) cables (FR Northbound/CH0+030 ‐ CH0+100) 45 days Thu 22/12/22 Sat 11/2/23 Fri 30/12/22 Mon 20/2/23 7 days
333 6P6/22KV High voltage (HV) cables (BKD Westbound/CH0+050 ‐  45 days Thu 22/12/22 Sat 11/2/23 Fri 30/12/22 Mon 20/2/23 7 days
CH0+360)
334 Low voltage (LV) cables (BKD Westbound/CH0+050 ‐ CH0+200) 45 days Thu 22/12/22 Sat 11/2/23 Fri 30/12/22 Mon 20/2/23 7 days
335 [Z2] Utitlity service diversion (by KTC) 45 days Thu 22/12/22 Sat 11/2/23 Fri 30/12/22 Mon 20/2/23 7 days
336 Water pipe (FR Northbound/CH0+090 ‐ CH0+100) 45 days Thu 22/12/22 Sat 11/2/23 Fri 30/12/22 Mon 20/2/23 7 days
337 Completion of utility services diversion 1 day Mon 13/2/23 Mon 13/2/23 Tue 21/2/23 Tue 21/2/23 7 days
338 [Z2] Construction 384 days Thu 24/11/22 Wed 14/2/24 Wed 30/11/22 Thu 22/2/24 5 days
339 [Z2BKD] Buangkok Drive CH0+050 ‐ CH0+360 384 days Thu 24/11/22 Wed 14/2/24 Wed 30/11/22 Thu 22/2/24 5 days
340 [Z2BKD] Site establishment 25 days Thu 24/11/22 Thu 22/12/22 Wed 30/11/22 Wed 28/12/22 5 days
341 [Z2BKD] Removal of existing trees & site clearance 15 days Fri 23/12/22 Mon 9/1/23 Thu 29/12/22 Sat 14/1/23 5 days
342 [Z2BKD] Retaining Wall and Parapet Wall 204 days Tue 14/2/23 Mon 9/10/23 Wed 22/2/23 Tue 17/10/23 7 days
343 [Z2BKD] RW Type 1 (BKD Westbound/CH0+335 ‐ CH0+360) 55 days Tue 14/2/23 Tue 18/4/23 Wed 22/2/23 Tue 13/6/23 7 days
344 Sheet pile machine mobilisation 5 days Tue 14/2/23 Sat 18/2/23 Wed 22/2/23 Mon 27/2/23 7 days
345 ERSS (Sheet Pile) 15 days Mon 20/2/23 Wed 8/3/23 Tue 28/2/23 Thu 16/3/23 7 days
346 Excavation of RW base 8 days Thu 9/3/23 Fri 17/3/23 Fri 17/3/23 Sat 25/3/23 7 days
347 RW base (6.0m wide) 10 days Sat 18/3/23 Wed 29/3/23 Mon 27/3/23 Thu 6/4/23 7 days
348 RW wall (4.5m height) 10 days Thu 30/3/23 Mon 10/4/23 Fri 7/4/23 Tue 18/4/23 7 days
349 ERSS removal and backfill 7 days Tue 11/4/23 Tue 18/4/23 Tue 6/6/23 Tue 13/6/23 48 days
350 [Z2BKD] RW Type 3 (BKD Westbound/CH0+265 ‐ CH0+335) 59 days Thu 9/3/23 Tue 16/5/23 Fri 17/3/23 Mon 5/6/23 7 days
351 ERSS (Sheet Pile) 18 days Thu 9/3/23 Wed 29/3/23 Fri 17/3/23 Thu 6/4/23 7 days
352 Excavation of RW base 8 days Thu 30/3/23 Fri 7/4/23 Mon 10/4/23 Tue 18/4/23 9 days
353 RW base (6.8m wide) 10 days Tue 11/4/23 Fri 21/4/23 Wed 19/4/23 Sat 29/4/23 7 days
354 RW wall (4.5m height) 14 days Sat 22/4/23 Mon 8/5/23 Mon 1/5/23 Tue 16/5/23 7 days
355 ERSS removal and backfill 7 days Tue 9/5/23 Tue 16/5/23 Mon 29/5/23 Mon 5/6/23 17 days
356 [Z2BKD] RW Type 3 (BKD Westbound/CH0+220 ‐ CH0+265) 67 days Thu 30/3/23 Thu 15/6/23 Fri 7/4/23 Wed 19/7/23 7 days
357 ERSS (Sheet Pile) 15 days Thu 30/3/23 Sat 15/4/23 Fri 7/4/23 Mon 24/4/23 7 days
358 Excavation of RW base 10 days Mon 17/4/23 Thu 27/4/23 Fri 5/5/23 Tue 16/5/23 16 days
359 RW base (6.8m wide)  12 days Tue 9/5/23 Mon 22/5/23 Wed 17/5/23 Tue 30/5/23 7 days
360 RW wall (4.5m height) 14 days Tue 23/5/23 Wed 7/6/23 Wed 31/5/23 Thu 15/6/23 7 days
361 ERSS removal and backfill 7 days Thu 8/6/23 Thu 15/6/23 Wed 12/7/23 Wed 19/7/23 29 days
362 [Z2BKD] RW Type 3 BKD Westbound/CH0+130 ‐ CH0+205) 55 days Mon 27/3/23 Mon 29/5/23 Tue 4/4/23 Wed 19/7/23 7 days
363 ERSS (Sheet Pile) 10 days Mon 27/3/23 Thu 6/4/23 Tue 4/4/23 Fri 14/4/23 7 days
364 Excavation of RW base 8 days Fri 7/4/23 Sat 15/4/23 Sat 15/4/23 Mon 24/4/23 7 days
365 RW base (6.8m wide)  14 days Mon 17/4/23 Tue 2/5/23 Tue 25/4/23 Wed 10/5/23 7 days
366 RW wall (5m height) 16 days Wed 3/5/23 Sat 20/5/23 Thu 11/5/23 Mon 29/5/23 7 days
367 ERSS removal and backfill 7 days Mon 22/5/23 Mon 29/5/23 Wed 12/7/23 Wed 19/7/23 44 days
368 [Z2BKD] RW Type 1 (BKD Westbound/CH0+050 ‐ CH0+123) 69 days Mon 17/4/23 Wed 5/7/23 Tue 25/4/23 Thu 13/7/23 7 days
369 ERSS (Sheet Pile) 20 days Mon 17/4/23 Tue 9/5/23 Tue 25/4/23 Wed 17/5/23 7 days
370 Excavation of RW base 10 days Wed 10/5/23 Sat 20/5/23 Thu 18/5/23 Mon 29/5/23 7 days
371 RW base (6.0m wide) 14 days Mon 22/5/23 Tue 6/6/23 Tue 30/5/23 Wed 14/6/23 7 days
372 RW wall (4.5m height) 18 days Wed 7/6/23 Tue 27/6/23 Thu 15/6/23 Wed 5/7/23 7 days
373 ERSS removal and backfill 7 days Wed 28/6/23 Wed 5/7/23 Thu 6/7/23 Thu 13/7/23 7 days
374 [Z2BKD] PW (BKD Westbound/CH0+205 ‐ CH0+220) 27 days Fri 16/6/23 Mon 17/7/23 Thu 20/7/23 Sat 19/8/23 29 days
375 PW base (1.5m wide)  10 days Fri 16/6/23 Tue 27/6/23 Thu 20/7/23 Mon 31/7/23 29 days
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 6
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
376 PW wall (3.0m height) 10 days Wed 28/6/23 Sat 8/7/23 Tue 1/8/23 Fri 11/8/23 29 days
377 Formwork removal and backfill 7 days Mon 10/7/23 Mon 17/7/23 Sat 12/8/23 Sat 19/8/23 29 days
378 [Z2BKD] PW (BKD Westbound/CH0+123 ‐ CH0+130) 27 days Mon 10/7/23 Wed 9/8/23 Thu 7/9/23 Sat 7/10/23 51 days
379 PW base (1.5m wide)  10 days Mon 10/7/23 Thu 20/7/23 Thu 7/9/23 Mon 18/9/23 51 days
380 PW wall (3.0m height) 10 days Fri 21/7/23 Tue 1/8/23 Tue 19/9/23 Fri 29/9/23 51 days
381 Formwork removal and backfill 7 days Wed 2/8/23 Wed 9/8/23 Sat 30/9/23 Sat 7/10/23 51 days
382 [Z2BKD] RW Type 4 (BKD Eastbound/CH0+325 ‐ CH0+360) 58 days Wed 10/5/23 Sat 15/7/23 Wed 24/5/23 Fri 25/8/23 12 days
383 ERSS (Sheet Pile) 10 days Wed 10/5/23 Sat 20/5/23 Wed 24/5/23 Sat 3/6/23 12 days
384 Excavation of RW base 10 days Mon 22/5/23 Thu 1/6/23 Mon 5/6/23 Thu 15/6/23 12 days
385 RW base (8.45m wide) 12 days Thu 8/6/23 Wed 21/6/23 Fri 16/6/23 Thu 29/6/23 7 days
386 RW wall (4.5m height) 14 days Thu 22/6/23 Fri 7/7/23 Fri 30/6/23 Sat 15/7/23 7 days
387 ERSS removal and backfill 7 days Sat 8/7/23 Sat 15/7/23 Fri 18/8/23 Fri 25/8/23 35 days
388 [Z2BKD] RW Type 1(BKD Eastbound/CH0+080 ‐ CH0+176) 88 days Mon 22/5/23 Thu 31/8/23 Tue 6/6/23 Tue 12/9/23 10 days
389 ERSS (Sheet Pile) 25 days Mon 22/5/23 Mon 19/6/23 Tue 6/6/23 Tue 4/7/23 13 days
390 Excavation of RW base 10 days Tue 20/6/23 Fri 30/6/23 Wed 5/7/23 Sat 15/7/23 13 days
391 RW base (6.0m wide) 18 days Sat 8/7/23 Fri 28/7/23 Mon 17/7/23 Sat 5/8/23 7 days
392 RW wall (4.5m height) 22 days Sat 29/7/23 Wed 23/8/23 Mon 7/8/23 Thu 31/8/23 7 days
393 ERSS removal and backfill 7 days Thu 24/8/23 Thu 31/8/23 Tue 5/9/23 Tue 12/9/23 10 days
394 [Z2BKD] RW Type 4 (BKD Eastbound/CH0+176 ‐ CH0+224) 96 days Tue 20/6/23 Mon 9/10/23 Fri 28/7/23 Tue 17/10/23 7 days
395 ERSS (Sheet Pile) 20 days Tue 20/6/23 Wed 12/7/23 Fri 28/7/23 Sat 19/8/23 33 days
396 Excavation of RW base 10 days Thu 13/7/23 Mon 24/7/23 Mon 21/8/23 Thu 31/8/23 33 days
397 RW base (8.45m wide) 15 days Thu 24/8/23 Sat 9/9/23 Fri 1/9/23 Mon 18/9/23 7 days
398 RW wall (4.5m height) 20 days Mon 11/9/23 Tue 3/10/23 Tue 19/9/23 Wed 11/10/23 7 days
399 ERSS removal and backfill 5 days Wed 4/10/23 Mon 9/10/23 Thu 12/10/23 Tue 17/10/23 7 days
400 [Z2BKD] Drain  147 days Wed 17/5/23 Fri 3/11/23 Tue 6/6/23 Sat 11/11/23 7 days
401 [Z2BKD] Sump 1700x1700mm (L) 10 days Fri 16/6/23 Tue 27/6/23 Mon 21/8/23 Thu 31/8/23 56 days
402 Sump base, wall and top slab 10 days Fri 16/6/23 Tue 27/6/23 Mon 21/8/23 Thu 31/8/23 56 days
403 [Z2BKD] Sump 1700x1700mm (K2) 20 days Fri 28/7/23 Sat 19/8/23 Mon 21/8/23 Tue 12/9/23 20 days
404 Jack‐in pile (4pts, 200x200mm x 13.2m) 10 days Fri 28/7/23 Tue 8/8/23 Mon 21/8/23 Thu 31/8/23 20 days
405 Sump base, wall and top slab 10 days Wed 9/8/23 Sat 19/8/23 Fri 1/9/23 Tue 12/9/23 20 days
406 [Z2BKD] Sump 1700x1700mm (K1) 20 days Wed 9/8/23 Thu 31/8/23 Fri 1/9/23 Sat 23/9/23 20 days
407 Jack‐in pile (4pts, 200x200mm x 13.5m) 10 days Wed 9/8/23 Sat 19/8/23 Fri 1/9/23 Tue 12/9/23 20 days
408 Sump base, wall and top slab 10 days Mon 21/8/23 Thu 31/8/23 Wed 13/9/23 Sat 23/9/23 20 days
409 [Z2BKD] Box culvert 1.1x0.60x16.77m (K1‐K2) 25 days Mon 21/8/23 Mon 18/9/23 Wed 13/9/23 Wed 11/10/23 20 days
410 Jack‐in pile (14pts, 200x200mm x 12.1m) 10 days Mon 21/8/23 Thu 31/8/23 Wed 13/9/23 Sat 23/9/23 20 days
411 Box culvert base, wall and top slab 15 days Fri 1/9/23 Mon 18/9/23 Mon 25/9/23 Wed 11/10/23 20 days
412 [Z2BKD] Box culvert  1.1x18.33m (K1‐K2) 27 days Tue 19/9/23 Thu 19/10/23 Thu 12/10/23 Sat 11/11/23 20 days
413 Demolish of existing box culvert 12 days Tue 19/9/23 Mon 2/10/23 Thu 12/10/23 Wed 25/10/23 20 days
414 Box culvert base, wall and top slab 15 days Tue 3/10/23 Thu 19/10/23 Thu 26/10/23 Sat 11/11/23 20 days
415 [Z2BKD] Sump 1700x1700mm ( C) 10 days Fri 1/9/23 Tue 12/9/23 Mon 2/10/23 Thu 12/10/23 26 days
416 Sump base, wall and top slab 10 days Fri 1/9/23 Tue 12/9/23 Mon 2/10/23 Thu 12/10/23 26 days
417 [Z2BKD] Sump 1200x1200mm (C1) 20 days Fri 1/9/23 Sat 23/9/23 Thu 28/9/23 Wed 25/10/23 23 days
418 Jack‐in pile (200x200mm x 6.2m) 10 days Fri 1/9/23 Tue 12/9/23 Thu 28/9/23 Mon 9/10/23 23 days
419 Sump base, wall and top slab 10 days Wed 13/9/23 Sat 23/9/23 Sat 14/10/23 Wed 25/10/23 27 days
420 [Z2BKD] Box culvert 0.6x0.9x17m (C1‐C) 39 days Fri 1/9/23 Mon 16/10/23 Mon 2/10/23 Sat 11/11/23 23 days
421 Underground utility service 7 days Fri 1/9/23 Fri 8/9/23 Mon 2/10/23 Mon 9/10/23 26 days
422 Jack‐in pile (14pts, 150x150mm x 12.7m) 14 days Wed 13/9/23 Thu 28/9/23 Tue 10/10/23 Wed 25/10/23 23 days
423 Box culvert base, wall and top slab 15 days Fri 29/9/23 Mon 16/10/23 Thu 26/10/23 Sat 11/11/23 23 days
424 [Z2BKD] Covered Drain 1100mm (BKD Westbound/CH0+335 ‐ 25 days Tue 30/5/23 Tue 27/6/23 Wed 14/6/23 Wed 12/7/23 13 days
CH0+360)
425 Drain base, wall and top slab 25 days Tue 30/5/23 Tue 27/6/23 Wed 14/6/23 Wed 12/7/23 13 days
426 [Z2BKD] Covered Drain 1100mm (BKD Westbound/CH0+265 ‐ 25 days Wed 28/6/23 Wed 26/7/23 Thu 13/7/23 Thu 10/8/23 13 days
CH0+335)
427 Drain base, wall and top slab 25 days Wed 28/6/23 Wed 26/7/23 Thu 13/7/23 Thu 10/8/23 13 days
428 [Z2BKD] Covered Drain 1100mm (BKD Westbound/CH0+220 ‐ 25 days Thu 27/7/23 Thu 24/8/23 Fri 11/8/23 Fri 8/9/23 13 days
CH0+265)
429 Drain base, wall and top slab 25 days Thu 27/7/23 Thu 24/8/23 Fri 11/8/23 Fri 8/9/23 13 days
430 [Z2BKD] Covered Drain 1100mm (BKD Westbound/CH0+130 ‐ 25 days Fri 25/8/23 Fri 22/9/23 Sat 9/9/23 Sat 7/10/23 13 days
CH0+220)
431 Drain base, wall and top slab 25 days Fri 25/8/23 Fri 22/9/23 Sat 9/9/23 Sat 7/10/23 13 days
432 [Z2BKD] Covered Drain 1100mm (BKD Westbound/CH0+050 ‐ 30 days Sat 23/9/23 Fri 27/10/23 Mon 9/10/23 Sat 11/11/23 13 days
CH0+130)
433 Drain base, wall and top slab 30 days Sat 23/9/23 Fri 27/10/23 Mon 9/10/23 Sat 11/11/23 13 days
434 [Z2BKD] Covered Drain 1100mm (BKD Eastbound/CH0+325 ‐  15 days Fri 18/8/23 Mon 4/9/23 Sat 26/8/23 Tue 12/9/23 7 days
CH0+360)
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 7
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
435 Drain base, wall and top slab 15 days Fri 18/8/23 Mon 4/9/23 Sat 26/8/23 Tue 12/9/23 7 days
436 [Z2BKD] Covered Drain 1100mm (BKD Eastbound/CH0+080 ‐  30 days Tue 5/9/23 Mon 9/10/23 Wed 13/9/23 Tue 17/10/23 7 days
CH0+176)
437 Drain base, wall and top slab 30 days Tue 5/9/23 Mon 9/10/23 Wed 13/9/23 Tue 17/10/23 7 days
438 [Z2BKD] Covered Drain 1100mm (BKD Eastbound/CH0+176 ‐  22 days Tue 10/10/23 Fri 3/11/23 Wed 18/10/23 Sat 11/11/23 7 days
CH0+238)
439 Drain base, wall and top slab 22 days Tue 10/10/23 Fri 3/11/23 Wed 18/10/23 Sat 11/11/23 7 days
440 [Z2BKD] Covered Drain 600mm (BKD Centre  52 days Wed 17/5/23 Sat 15/7/23 Tue 6/6/23 Fri 4/8/23 17 days
Median/CH0+310 ‐ CH0+360)
441 Underground utility service 7 days Wed 17/5/23 Wed 24/5/23 Tue 6/6/23 Tue 13/6/23 17 days
442 Jack‐in pile (50pts, 150x150mm x 16.2m) 15 days Thu 25/5/23 Sat 10/6/23 Wed 14/6/23 Fri 30/6/23 17 days
443 Drain base, wall and top slab 30 days Mon 12/6/23 Sat 15/7/23 Sat 1/7/23 Fri 4/8/23 17 days
444 [Z2BKD] Covered Drain 600mm (BKD Centre  37 days Thu 6/7/23 Thu 17/8/23 Fri 14/7/23 Fri 25/8/23 7 days
Median/CH0+050 ‐ CH0+090)
445 Underground utility service 7 days Thu 6/7/23 Thu 13/7/23 Fri 14/7/23 Fri 21/7/23 7 days
446 Jack‐in pile (40pts, 150x150mm x 10.5m) 12 days Fri 14/7/23 Thu 27/7/23 Sat 22/7/23 Fri 4/8/23 7 days
447 Drain base, wall and top slab 18 days Fri 28/7/23 Thu 17/8/23 Sat 5/8/23 Fri 25/8/23 7 days
448 [Z2BKD] Staircase and Ramp 174 days Wed 28/6/23 Tue 16/1/24 Tue 24/10/23 Thu 22/2/24 32 days
449 [Z2BKD] S&R at Gerald Drive (CH0+335 ‐ CH0+355) 20 days Wed 28/6/23 Thu 20/7/23 Tue 24/10/23 Wed 15/11/23 101 days
450 [Z2BKD] S&R at MSCP Block 404 112 days Thu 10/8/23 Mon 18/12/23 Sat 4/11/23 Wed 24/1/24 32 days
451 Removal of existing foot path 10 days Thu 10/8/23 Mon 21/8/23 Sat 4/11/23 Wed 15/11/23 74 days
452 Staircase 30 days Tue 10/10/23 Mon 13/11/23 Thu 16/11/23 Wed 20/12/23 32 days
453 Ramp 30 days Tue 14/11/23 Mon 18/12/23 Thu 21/12/23 Wed 24/1/24 32 days
454 [Z2BKD] High Linkway at Block 408A 25 days Tue 19/12/23 Tue 16/1/24 Thu 25/1/24 Thu 22/2/24 32 days
455 [Z2BKD] Road 66 days Sat 28/10/23 Fri 12/1/24 Mon 13/11/23 Sat 20/1/24 7 days
456 [Z2BKD] BKD Westbound/CH0+050 ‐ CH0+280 59 days Sat 28/10/23 Thu 4/1/24 Mon 13/11/23 Fri 19/1/24 13 days
457 Underground utility service 7 days Sat 28/10/23 Sat 4/11/23 Mon 13/11/23 Mon 20/11/23 13 days
458 Subgrade and sub‐base 16 days Mon 6/11/23 Thu 23/11/23 Tue 21/11/23 Fri 8/12/23 13 days
459 Kerb, drop‐inlet chamber and scupper pipe 20 days Fri 24/11/23 Sat 16/12/23 Sat 9/12/23 Mon 1/1/24 13 days
460 Base course and pavement 16 days Mon 18/12/23 Thu 4/1/24 Tue 2/1/24 Fri 19/1/24 13 days
461 [Z2BKD] BKD Eastbound/CH0+080 ‐ CH0+280 59 days Sat 4/11/23 Thu 11/1/24 Mon 13/11/23 Fri 19/1/24 7 days
462 Underground utility service 7 days Sat 4/11/23 Sat 11/11/23 Mon 13/11/23 Mon 20/11/23 7 days
463 Subgrade and sub‐base 16 days Mon 13/11/23 Thu 30/11/23 Tue 21/11/23 Fri 8/12/23 7 days
464 Kerb, drop‐inlet chamber and scupper pipe 20 days Fri 1/12/23 Sat 23/12/23 Sat 9/12/23 Mon 1/1/24 7 days
465 Base course and pavement 16 days Mon 25/12/23 Thu 11/1/24 Tue 2/1/24 Fri 19/1/24 7 days
466 [Z2BKD] BKD Westbound/CH0+280 ‐ CH0+360 53 days Sat 28/10/23 Thu 28/12/23 Wed 22/11/23 Fri 19/1/24 19 days
467 Underground utility service 7 days Sat 28/10/23 Sat 4/11/23 Wed 22/11/23 Wed 29/11/23 21 days
468 Subgrade and sub‐base 14 days Mon 6/11/23 Tue 21/11/23 Thu 30/11/23 Fri 15/12/23 21 days
469 Kerb, drop‐inlet chamber and scupper pipe 16 days Fri 24/11/23 Tue 12/12/23 Sat 16/12/23 Wed 3/1/24 19 days
470 Base course and pavement 14 days Wed 13/12/23 Thu 28/12/23 Thu 4/1/24 Fri 19/1/24 19 days
471 [Z2BKD] BKD Eastbound/CH0+280 ‐ CH0+360 53 days Sat 4/11/23 Thu 4/1/24 Wed 22/11/23 Fri 19/1/24 13 days
472 Underground utility service 7 days Sat 4/11/23 Sat 11/11/23 Wed 22/11/23 Wed 29/11/23 15 days
473 Subgrade and sub‐base 14 days Mon 13/11/23 Tue 28/11/23 Thu 30/11/23 Fri 15/12/23 15 days
474 Kerb, drop‐inlet chamber and scupper pipe 16 days Fri 1/12/23 Tue 19/12/23 Sat 16/12/23 Wed 3/1/24 13 days
475 Base course and pavement 14 days Wed 20/12/23 Thu 4/1/24 Thu 4/1/24 Fri 19/1/24 13 days
476 [Z2BKD] Completion of Road 1 day Fri 12/1/24 Fri 12/1/24 Sat 20/1/24 Sat 20/1/24 7 days
477 [Z2BKD] Ancillary work 28 days Sat 13/1/24 Wed 14/2/24 Mon 22/1/24 Thu 22/2/24 7 days
478 Tree planting & turfing 28 days Sat 13/1/24 Wed 14/2/24 Mon 22/1/24 Thu 22/2/24 7 days
479 Railing 28 days Sat 13/1/24 Wed 14/2/24 Mon 22/1/24 Thu 22/2/24 7 days
480 Lamp post 28 days Sat 13/1/24 Wed 14/2/24 Mon 22/1/24 Thu 22/2/24 7 days
481 [Z2FR] Fernvale Road CH0 ‐ CH0+110 344 days Tue 10/1/23 Wed 14/2/24 Tue 24/1/23 Thu 22/2/24 7 days
482 [Z2FR] Site establishment 15 days Tue 10/1/23 Thu 26/1/23 Tue 24/1/23 Thu 9/2/23 12 days
483 [Z2FR] Removal of existing trees & site clearance 15 days Fri 27/1/23 Mon 13/2/23 Fri 10/2/23 Mon 27/2/23 12 days
484 [Z2FR] Retaining wall  101 days Mon 20/2/23 Fri 16/6/23 Tue 28/2/23 Sat 24/6/23 7 days
485 [Z2FR] RW Type 4 (FR Southbound/CH0+030 ‐ CH0+110) 58 days Mon 20/2/23 Thu 27/4/23 Tue 28/2/23 Fri 5/5/23 7 days
486 ERSS (Sheet Pile) 15 days Mon 20/2/23 Wed 8/3/23 Tue 28/2/23 Thu 16/3/23 7 days
487 Excavation of RW base 8 days Thu 9/3/23 Fri 17/3/23 Fri 17/3/23 Sat 25/3/23 7 days
488 RW base (8.45m wide) 13 days Sat 18/3/23 Sat 1/4/23 Mon 27/3/23 Mon 10/4/23 7 days
489 RW wall (5.5m height) 15 days Mon 3/4/23 Wed 19/4/23 Tue 11/4/23 Thu 27/4/23 7 days
490 ERSS removal and backfill 7 days Thu 20/4/23 Thu 27/4/23 Fri 28/4/23 Fri 5/5/23 7 days
491 [Z2FR] RW Type 4 (FR Northbound/CH0+030 ‐ CH0+110) 86 days Thu 9/3/23 Fri 16/6/23 Fri 17/3/23 Sat 24/6/23 7 days
492 ERSS (Sheet Pile) 15 days Thu 9/3/23 Sat 25/3/23 Fri 17/3/23 Mon 3/4/23 7 days
493 Excavation of RW base 8 days Fri 28/4/23 Sat 6/5/23 Sat 6/5/23 Mon 15/5/23 7 days
494 RW base (8.45m wide) 13 days Mon 8/5/23 Mon 22/5/23 Tue 16/5/23 Tue 30/5/23 7 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 8
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
495 RW wall (5.0m height) 15 days Tue 23/5/23 Thu 8/6/23 Wed 31/5/23 Fri 16/6/23 7 days
496 ERSS removal and backfill 7 days Fri 9/6/23 Fri 16/6/23 Sat 17/6/23 Sat 24/6/23 7 days
497 [Z2FR] Drain  181 days Thu 11/5/23 Thu 7/12/23 Sat 3/6/23 Fri 15/12/23 7 days
498 [Z2FR] Sump 1700x1700mm (E ) 10 days Sat 17/6/23 Wed 28/6/23 Thu 10/8/23 Mon 21/8/23 46 days
499 Sump base, wall and top slab 10 days Sat 17/6/23 Wed 28/6/23 Thu 10/8/23 Mon 21/8/23 46 days
500 [Z2FR] Sump 1700x1700mm (D) 10 days Thu 29/6/23 Mon 10/7/23 Tue 22/8/23 Fri 1/9/23 46 days
501 Sump base, wall and top slab 10 days Thu 29/6/23 Mon 10/7/23 Tue 22/8/23 Fri 1/9/23 46 days
502 [Z2FD] Box culvert 1.1x1.9x34m (D‐E) 66 days Sat 17/6/23 Fri 1/9/23 Wed 9/8/23 Mon 25/9/23 20 days
503 Underground utility services 7 days Sat 17/6/23 Sat 24/6/23 Wed 9/8/23 Wed 16/8/23 45 days
504 Jack‐in pile (17pts, 150x150mm x 10.5m) 14 days Tue 25/7/23 Wed 9/8/23 Thu 17/8/23 Fri 1/9/23 20 days
505 Box culvert base, wall and top slab 20 days Thu 10/8/23 Fri 1/9/23 Sat 2/9/23 Mon 25/9/23 20 days
506 [Z2FR] Covered Drain 1100mm FD Southbound/CH0+030 ‐  94 days Mon 26/6/23 Thu 12/10/23 Mon 18/9/23 Sat 4/11/23 20 days
CH0+110)
507 Underground utility services 7 days Mon 26/6/23 Mon 3/7/23 Mon 18/9/23 Mon 25/9/23 72 days
508 Drain base, wall and top slab 35 days Sat 2/9/23 Thu 12/10/23 Tue 26/9/23 Sat 4/11/23 20 days
509 [Z2FR] Covered Drain 1100mm FD Northbound/CH0+030 ‐  122 days Tue 4/7/23 Wed 22/11/23 Sat 28/10/23 Fri 15/12/23 20 days
CH0+110)
510 Underground utility services 7 days Tue 4/7/23 Tue 11/7/23 Sat 28/10/23 Sat 4/11/23 100 days
511 Drain base, wall and top slab 35 days Fri 13/10/23 Wed 22/11/23 Mon 6/11/23 Fri 15/12/23 20 days
512 [Z2FR] Sump 1700x1700mm (V1) 42 days Thu 11/5/23 Wed 28/6/23 Sat 3/6/23 Thu 6/7/23 7 days
513 Jack‐in pile machine mobilisation 5 days Thu 11/5/23 Tue 16/5/23 Sat 3/6/23 Thu 8/6/23 20 days
514 Jack‐in Pile (0.2x0.2x9.9m) 10 days Wed 17/5/23 Sat 27/5/23 Fri 9/6/23 Tue 20/6/23 20 days
515 Sump base, wall and top slab 10 days Sat 17/6/23 Wed 28/6/23 Mon 26/6/23 Thu 6/7/23 7 days
516 [Z2FR] Sump 1200x1200mm (V2) 37 days Mon 29/5/23 Mon 10/7/23 Wed 21/6/23 Tue 18/7/23 7 days
517 Jack‐in Pile (0.2x0.2x8.3m) 10 days Mon 29/5/23 Thu 8/6/23 Wed 21/6/23 Sat 1/7/23 20 days
518 Sump base, wall and top slab 10 days Thu 29/6/23 Mon 10/7/23 Fri 7/7/23 Tue 18/7/23 7 days
519 [Z2FR] Box culvert 0.6x0.55x12.14m (V2‐V1) 42 days Fri 9/6/23 Thu 27/7/23 Mon 3/7/23 Fri 4/8/23 7 days
520 Jack‐in pile (14pts, 200x200mm x 9.9m) 14 days Fri 9/6/23 Sat 24/6/23 Mon 3/7/23 Tue 18/7/23 20 days
521 Box culvert base, wall and top slab 15 days Tue 11/7/23 Thu 27/7/23 Wed 19/7/23 Fri 4/8/23 7 days
522 [Z2FR] Covered Drain 1100mm FD Northbound/CH0+010 ‐  38 days Mon 26/6/23 Tue 8/8/23 Wed 19/7/23 Wed 16/8/23 7 days
CH0+030)
523 Jack‐in pile (20pts, 150x150mm x 9.1m) 15 days Mon 26/6/23 Wed 12/7/23 Wed 19/7/23 Fri 4/8/23 20 days
524 Drain base, wall and top slab 10 days Fri 28/7/23 Tue 8/8/23 Sat 5/8/23 Wed 16/8/23 7 days
525 [Z2FR] Covered Drain 600mm FD Northbound/CH0+010 ‐  33 days Thu 13/7/23 Sat 19/8/23 Sat 5/8/23 Mon 28/8/23 7 days
CH0+030)
526 Jack‐in Pile (12pts, 0.15x0.15x9.9m) 10 days Thu 13/7/23 Mon 24/7/23 Sat 5/8/23 Wed 16/8/23 20 days
527 Drain base, wall and top slab 10 days Wed 9/8/23 Sat 19/8/23 Thu 17/8/23 Mon 28/8/23 7 days
528 [Z2FR] Sump 1700x1700mm (W1) 20 days Sat 30/9/23 Mon 23/10/23 Mon 9/10/23 Wed 1/11/23 7 days
529 Diversion of foot path 5 days Sat 30/9/23 Thu 5/10/23 Mon 9/10/23 Fri 13/10/23 7 days
530 Jack‐in Pile (0.2x0.2x7.3m) 7 days Fri 6/10/23 Fri 13/10/23 Sat 14/10/23 Sat 21/10/23 7 days
531 Sump base, wall and top slab 8 days Sat 14/10/23 Mon 23/10/23 Tue 24/10/23 Wed 1/11/23 8 days
532 [Z2FR] Sump 1200x1200mm (W2) 16 days Sat 14/10/23 Wed 1/11/23 Mon 23/10/23 Fri 10/11/23 7 days
533 Jack‐in Pile (0.2x0.2x6.5m) 7 days Sat 14/10/23 Sat 21/10/23 Mon 23/10/23 Mon 30/10/23 7 days
534 Sump base, wall and top slab 8 days Tue 24/10/23 Wed 1/11/23 Thu 2/11/23 Fri 10/11/23 8 days
535 [Z2FR] Box culvert 0.6x0.85x12.82m (W2‐W1) 20 days Mon 23/10/23 Tue 14/11/23 Tue 31/10/23 Wed 22/11/23 7 days
536 Jack‐in pile (14pts, 150x150mm x 9.5m) 10 days Mon 23/10/23 Thu 2/11/23 Tue 31/10/23 Fri 10/11/23 7 days
537 Box culvert base, wall and top slab 10 days Fri 3/11/23 Tue 14/11/23 Sat 11/11/23 Wed 22/11/23 7 days
538 [Z2FR] Covered Drain 1100mm FD Southbound/CH0+010 ‐  20 days Fri 3/11/23 Sat 25/11/23 Sat 11/11/23 Mon 4/12/23 7 days
CH0+030)
539 Jack‐in pile (20pts, 150x150mm x 9.1m) 10 days Fri 3/11/23 Tue 14/11/23 Sat 11/11/23 Wed 22/11/23 7 days
540 Drain base, wall and top slab 10 days Wed 15/11/23 Sat 25/11/23 Thu 23/11/23 Mon 4/12/23 7 days
541 [Z2FR] Covered Drain 600mm FD Southbound/CH0+010 ‐  20 days Wed 15/11/23 Thu 7/12/23 Thu 23/11/23 Fri 15/12/23 7 days
CH0+030)
542 Jack‐in Pile (16pts, 0.15x0.15x9.9m) 10 days Wed 15/11/23 Sat 25/11/23 Thu 23/11/23 Mon 4/12/23 7 days
543 Drain base, wall and top slab 10 days Mon 27/11/23 Thu 7/12/23 Tue 5/12/23 Fri 15/12/23 7 days
544 [Z2FR] Staircase and Ramp 140 days Mon 21/8/23 Tue 30/1/24 Tue 29/8/23 Thu 22/2/24 7 days
545 [Z2FR] S&R at Block 407A 35 days Mon 21/8/23 Fri 29/9/23 Tue 29/8/23 Sat 7/10/23 7 days
546 Removal of existing foot path 5 days Mon 21/8/23 Fri 25/8/23 Tue 29/8/23 Sat 2/9/23 7 days
547 Staircase 15 days Sat 26/8/23 Tue 12/9/23 Mon 4/9/23 Wed 20/9/23 7 days
548 Ramp 15 days Wed 13/9/23 Fri 29/9/23 Thu 21/9/23 Sat 7/10/23 7 days
549 [Z2FR] S&R at Block 408A 46 days Fri 8/12/23 Tue 30/1/24 Mon 1/1/24 Thu 22/2/24 20 days
550 Relocation of monument 7 days Fri 8/12/23 Fri 15/12/23 Mon 1/1/24 Mon 8/1/24 20 days
551 Staircase 18 days Sat 16/12/23 Fri 5/1/24 Tue 9/1/24 Mon 29/1/24 20 days
552 Ramp 21 days Sat 6/1/24 Tue 30/1/24 Tue 30/1/24 Thu 22/2/24 20 days
553 [Z2FR] Road 52 days Thu 23/11/23 Mon 22/1/24 Sat 16/12/23 Tue 30/1/24 7 days
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 9
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
554 [Z2FR] FD Southbound/CH0 ‐ CH0+110 39 days Fri 8/12/23 Mon 22/1/24 Sat 16/12/23 Tue 30/1/24 7 days
555 Underground utility service 7 days Fri 8/12/23 Fri 15/12/23 Sat 16/12/23 Sat 23/12/23 7 days
556 Subgrade and sub‐base 10 days Sat 16/12/23 Wed 27/12/23 Mon 25/12/23 Thu 4/1/24 7 days
557 Kerb, drop‐inlet chamber and scupper pipe 12 days Thu 28/12/23 Wed 10/1/24 Fri 5/1/24 Thu 18/1/24 7 days
558 Base course and pavement 10 days Thu 11/1/24 Mon 22/1/24 Fri 19/1/24 Tue 30/1/24 7 days
559 [Z2FR] FD Northbound/CH0 ‐ CH0+110 45 days Thu 23/11/23 Sat 13/1/24 Sat 16/12/23 Tue 30/1/24 14 days
560 Underground utility service 7 days Thu 23/11/23 Thu 30/11/23 Sat 16/12/23 Sat 23/12/23 20 days
561 Subgrade and sub‐base 10 days Fri 1/12/23 Tue 12/12/23 Mon 25/12/23 Thu 4/1/24 20 days
562 Kerb, drop‐inlet chamber and scupper pipe 12 days Wed 20/12/23 Tue 2/1/24 Fri 5/1/24 Thu 18/1/24 14 days
563 Base course and pavement 10 days Wed 3/1/24 Sat 13/1/24 Fri 19/1/24 Tue 30/1/24 14 days
564 [Z2FR] Ancillary work 20 days Tue 23/1/24 Wed 14/2/24 Wed 31/1/24 Thu 22/2/24 7 days
565 Tree planting & turfing 20 days Tue 23/1/24 Wed 14/2/24 Wed 31/1/24 Thu 22/2/24 7 days
566 Railing 20 days Tue 23/1/24 Wed 14/2/24 Wed 31/1/24 Thu 22/2/24 7 days
567 Lamp post 20 days Tue 23/1/24 Wed 14/2/24 Wed 31/1/24 Thu 22/2/24 7 days
568 [Z2] Completion of Zone 2 0 days Thu 22/2/24 Thu 22/2/24 Thu 22/2/24 Thu 22/2/24 1 day 22/2
569 Zone 3 411 days Tue 1/11/22 Fri 23/2/24 Mon 7/11/22 Fri 23/2/24 1 day
570 [Z3] Preliminaries  46 days Thu 17/11/22 Mon 9/1/23 Thu 1/12/22 Mon 23/1/23 12 days
571 [Z3] Utitlity service diversion (by others) 46 days Thu 17/11/22 Mon 9/1/23 Thu 1/12/22 Mon 23/1/23 12 days
572 Starhub (SH) cables (FL/CH0+060 ‐ CH0+100) 45 days Thu 17/11/22 Sat 7/1/23 Thu 1/12/22 Sat 21/1/23 12 days
573 Gas pipe (FL Southbound/CH0+070 ‐ CH0+110) 45 days Thu 17/11/22 Sat 7/1/23 Thu 1/12/22 Sat 21/1/23 12 days
574 Low voltage cable (LV) (FL Southbound/CH0+070 ‐ CH0+110) 45 days Thu 17/11/22 Sat 7/1/23 Thu 1/12/22 Sat 21/1/23 12 days
575 6P6/22KV High voltage (HV) cables (FL Northbound/CH0+080 ‐  45 days Thu 17/11/22 Sat 7/1/23 Thu 1/12/22 Sat 21/1/23 12 days
CH0+110)
576 6P6/22KV High voltage (HV) cables (FL Southbound/CH0+070 ‐  45 days Thu 17/11/22 Sat 7/1/23 Thu 1/12/22 Sat 21/1/23 12 days
CH0+110)
577 6P6/22KV High voltage (HV) cables (BKD Westbound/CH0+360 ‐  45 days Thu 17/11/22 Sat 7/1/23 Thu 1/12/22 Sat 21/1/23 12 days
CH0+540)
578 Low voltage cable (LV) (BKD Westbound/CH0+500 ‐ CH0+540) 45 days Thu 17/11/22 Sat 7/1/23 Thu 1/12/22 Sat 21/1/23 12 days
579 Completion of utility services diversion 1 day Mon 9/1/23 Mon 9/1/23 Mon 23/1/23 Mon 23/1/23 12 days
580 [Z3] Construction 407 days Tue 1/11/22 Sat 17/2/24 Mon 7/11/22 Fri 23/2/24 5 days
581 [Z3] Buangkok Drive CH0+360 ‐ CH0+796 402 days Tue 1/11/22 Mon 12/2/24 Mon 7/11/22 Fri 23/2/24 5 days
582 [Z3BKD] Site establishment 25 days Tue 1/11/22 Tue 29/11/22 Mon 7/11/22 Mon 5/12/22 5 days
583 [Z3BKD] Removal of existing trees & site clearance 15 days Sat 31/12/22 Tue 17/1/23 Fri 6/1/23 Mon 23/1/23 5 days
584 [Z3BKD] Retaining Wall  230 days Wed 18/1/23 Thu 12/10/23 Tue 24/1/23 Wed 8/11/23 5 days
585 [Z3BKD RW Type 6 (BKD Eastbound/CH0+720 ‐ CH0+786) 106 days Wed 18/1/23 Sat 20/5/23 Tue 24/1/23 Sat 17/6/23 5 days
586 Micropile machine mobilisation 5 days Wed 18/1/23 Mon 23/1/23 Tue 24/1/23 Sat 28/1/23 5 days
587 Micropile 18 days Tue 24/1/23 Mon 13/2/23 Mon 30/1/23 Sat 18/2/23 5 days
588 Sheet pile machine mobilisation 5 days Wed 18/1/23 Mon 23/1/23 Mon 20/2/23 Fri 24/2/23 28 days
589 ERSS (with sheet pile) 25 days Tue 14/2/23 Tue 14/3/23 Sat 25/2/23 Sat 25/3/23 10 days
590 Excavation of RW base 10 days Tue 21/3/23 Fri 31/3/23 Mon 27/3/23 Thu 6/4/23 5 days
591 RW base (11.2m wide) 16 days Sat 1/4/23 Wed 19/4/23 Fri 7/4/23 Tue 25/4/23 5 days
592 RW wall (7.5m height) 20 days Thu 20/4/23 Fri 12/5/23 Wed 26/4/23 Thu 18/5/23 5 days
593 ERSS removal and backfill 7 days Sat 13/5/23 Sat 20/5/23 Sat 10/6/23 Sat 17/6/23 24 days
594 [Z3BKD RW Type 5 (BKD Eastbound/CH0+670 ‐ CH0+720) 109 days Tue 14/2/23 Tue 20/6/23 Mon 20/2/23 Mon 26/6/23 5 days
595 Micropile 15 days Tue 14/2/23 Thu 2/3/23 Mon 20/2/23 Wed 8/3/23 5 days
596 ERSS (sheet pile) 25 days Wed 15/3/23 Wed 12/4/23 Sat 8/4/23 Sat 6/5/23 21 days
597 Excavation of RW base 10 days Thu 13/4/23 Mon 24/4/23 Mon 8/5/23 Thu 18/5/23 21 days
598 RW base (6m wide) 12 days Sat 13/5/23 Fri 26/5/23 Fri 19/5/23 Thu 1/6/23 5 days
599 RW wall (5m height) 14 days Sat 27/5/23 Mon 12/6/23 Fri 2/6/23 Sat 17/6/23 5 days
600 ERSS removal and backfill 7 days Tue 13/6/23 Tue 20/6/23 Mon 19/6/23 Mon 26/6/23 5 days
601 [Z3BKD RW Type 6 (BKD Westbound/CH0+720 ‐ CH0+786) 131 days Tue 21/3/23 Sat 19/8/23 Fri 19/5/23 Wed 8/11/23 51 days
602 Micropile 18 days Tue 21/3/23 Mon 10/4/23 Fri 19/5/23 Thu 8/6/23 51 days
603 ERSS (open‐cut) & excavation of RW base 15 days Wed 21/6/23 Fri 7/7/23 Tue 27/6/23 Thu 13/7/23 5 days
604 RW base (11.7m wide) 14 days Sat 8/7/23 Mon 24/7/23 Fri 14/7/23 Sat 29/7/23 5 days
605 RW wall (7.6m height)  16 days Tue 25/7/23 Fri 11/8/23 Mon 31/7/23 Thu 17/8/23 5 days
606 ERSS removal and backfill 7 days Sat 12/8/23 Sat 19/8/23 Wed 1/11/23 Wed 8/11/23 69 days
607 [Z3BKD RW Type 5 (BKD Westbound/CH0+660 ‐ CH0+720) 139 days Tue 11/4/23 Tue 19/9/23 Fri 9/6/23 Mon 25/9/23 5 days
608 Micropile 15 days Tue 11/4/23 Thu 27/4/23 Fri 9/6/23 Mon 26/6/23 51 days
609 ERSS (open‐cut) & excavation of RW base 15 days Sat 8/7/23 Tue 25/7/23 Tue 1/8/23 Thu 17/8/23 20 days
610 RW base (6m wide) 12 days Sat 12/8/23 Fri 25/8/23 Fri 18/8/23 Thu 31/8/23 5 days
611 RW wall (5.2m height) 14 days Sat 26/8/23 Mon 11/9/23 Fri 1/9/23 Sat 16/9/23 5 days
612 ERSS removal and backfill 7 days Tue 12/9/23 Tue 19/9/23 Mon 18/9/23 Mon 25/9/23 5 days
613 [Z3BKD RW Type 6 (BKD/CH0+786 ‐ CH0+796) 170 days Fri 3/3/23 Sat 16/9/23 Thu 9/3/23 Fri 29/9/23 5 days
614 Micropile 15 days Fri 3/3/23 Mon 20/3/23 Thu 9/3/23 Sat 25/3/23 5 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 10
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
615 ERSS (with sheet pile) 25 days Thu 13/4/23 Thu 11/5/23 Fri 19/5/23 Fri 16/6/23 31 days
616 Excavation of RW  base 10 days Fri 28/7/23 Tue 8/8/23 Thu 10/8/23 Mon 21/8/23 11 days
617 RW base (11.2m wide) 13 days Wed 9/8/23 Wed 23/8/23 Tue 22/8/23 Tue 5/9/23 11 days
618 RW wall (7.5m height) 16 days Thu 24/8/23 Mon 11/9/23 Wed 6/9/23 Sat 23/9/23 11 days
619 ERSS removal and backfill 5 days Tue 12/9/23 Sat 16/9/23 Mon 25/9/23 Fri 29/9/23 11 days
620 [Z3BKD RW Type 2 (BKD Westbound/CH0+600 ‐ CH0+660) 45 days Wed 18/1/23 Fri 10/3/23 Thu 26/1/23 Fri 21/4/23 7 days
621 ERSS (open‐cut) & excavation of RW base 12 days Wed 18/1/23 Tue 31/1/23 Thu 26/1/23 Wed 8/2/23 7 days
622 RW base (6.8m wide) 12 days Wed 1/2/23 Tue 14/2/23 Thu 9/2/23 Wed 22/2/23 7 days
623 RW wall (5.6m height)  14 days Wed 15/2/23 Thu 2/3/23 Thu 23/2/23 Fri 10/3/23 7 days
624 ERSS removal and backfill 7 days Fri 3/3/23 Fri 10/3/23 Fri 14/4/23 Fri 21/4/23 36 days
625 [Z3BKD RW Type 1 (BKD Westbound/CH0+535 ‐ CH0+600) 63 days Wed 1/2/23 Fri 14/4/23 Thu 23/2/23 Sat 29/4/23 13 days
626 ERSS (open‐cut) & excavation of RW base 14 days Wed 1/2/23 Thu 16/2/23 Thu 23/2/23 Fri 10/3/23 19 days
627 RW base (6m wide) 14 days Fri 3/3/23 Sat 18/3/23 Sat 11/3/23 Mon 27/3/23 7 days
628 RW wall (4.8m height) 16 days Mon 20/3/23 Thu 6/4/23 Tue 28/3/23 Fri 14/4/23 7 days
629 ERSS removal and backfill 7 days Fri 7/4/23 Fri 14/4/23 Sat 22/4/23 Sat 29/4/23 13 days
630 [Z3BKD RW Type 1 (BKD Westbound/CH0+360 ‐ CH0+470) 79 days Fri 17/2/23 Fri 19/5/23 Thu 23/3/23 Sat 27/5/23 7 days
631 ERSS (open‐cut) & excavation of RW base 20 days Fri 17/2/23 Sat 11/3/23 Thu 23/3/23 Fri 14/4/23 29 days
632 RW base (6m wide) 14 days Fri 7/4/23 Sat 22/4/23 Sat 15/4/23 Mon 1/5/23 7 days
633 RW wall (3.1m height) 16 days Mon 24/4/23 Thu 11/5/23 Tue 2/5/23 Fri 19/5/23 7 days
634 ERSS removal and backfill 7 days Fri 12/5/23 Fri 19/5/23 Sat 20/5/23 Sat 27/5/23 7 days
635 [Z3BKD RW Type 1 (BKD Westbound/CH0+470 ‐ CH0+505) 35 days Sat 20/5/23 Thu 29/6/23 Mon 29/5/23 Fri 7/7/23 7 days
636 ERSS (open‐cut) & excavation of RW base 8 days Sat 20/5/23 Mon 29/5/23 Mon 29/5/23 Tue 6/6/23 7 days
637 RW base (6m wide) 10 days Tue 30/5/23 Fri 9/6/23 Wed 7/6/23 Sat 17/6/23 7 days
638 RW wall (4.9m height) 12 days Sat 10/6/23 Fri 23/6/23 Mon 19/6/23 Sat 1/7/23 7 days
639 ERSS removal and backfill 5 days Sat 24/6/23 Thu 29/6/23 Mon 3/7/23 Fri 7/7/23 7 days
640 [Z3BKD] RW Type 4 (BKD Eastbound/CH0+360 ‐ CH0+515) 67 days Sat 20/5/23 Sat 5/8/23 Sat 17/6/23 Sat 23/9/23 24 days
641 ERSS (with sheet pile) 22 days Sat 20/5/23 Wed 14/6/23 Sat 17/6/23 Wed 12/7/23 24 days
642 Excavation of RW base 10 days Thu 15/6/23 Mon 26/6/23 Thu 13/7/23 Mon 24/7/23 24 days
643 RW base (8.45m wide) 13 days Tue 27/6/23 Tue 11/7/23 Tue 25/7/23 Tue 8/8/23 24 days
644 RW wall (3.8m height) 15 days Wed 12/7/23 Fri 28/7/23 Wed 9/8/23 Fri 25/8/23 24 days
645 ERSS removal and backfill 7 days Sat 29/7/23 Sat 5/8/23 Sat 16/9/23 Sat 23/9/23 42 days
646 [Z3BKD] RW Type 4 (BKD Eastbound/CH0+535 ‐ CH0+600) 71 days Thu 15/6/23 Tue 5/9/23 Fri 14/7/23 Thu 19/10/23 25 days
647 ERSS (with sheet pile) 22 days Thu 15/6/23 Mon 10/7/23 Fri 14/7/23 Tue 8/8/23 25 days
648 Excavation of RW base 10 days Tue 11/7/23 Fri 21/7/23 Tue 15/8/23 Fri 25/8/23 30 days
649 RW base (8.45m wide) 12 days Sat 29/7/23 Fri 11/8/23 Sat 26/8/23 Fri 8/9/23 24 days
650 RW wall (3.2m height) 14 days Sat 12/8/23 Mon 28/8/23 Sat 9/9/23 Mon 25/9/23 24 days
651 ERSS removal and backfill 7 days Tue 29/8/23 Tue 5/9/23 Thu 12/10/23 Thu 19/10/23 38 days
652 [Z3BKD] RW Type 4 (BKD Eastbound/CH0+515 ‐ CH0+535) 40 days Mon 28/8/23 Thu 12/10/23 Wed 6/9/23 Sat 21/10/23 8 days
653 ERSS (with sheet pile) 10 days Mon 28/8/23 Thu 7/9/23 Wed 6/9/23 Sat 16/9/23 8 days
654 Excavation of RW base 7 days Fri 8/9/23 Fri 15/9/23 Mon 18/9/23 Mon 25/9/23 8 days
655 RW base (8.45m wide) 8 days Sat 16/9/23 Mon 25/9/23 Tue 26/9/23 Wed 4/10/23 8 days
656 RW wall (3.2m height) 10 days Tue 26/9/23 Fri 6/10/23 Thu 5/10/23 Mon 16/10/23 8 days
657 ERSS removal and backfill 5 days Sat 7/10/23 Thu 12/10/23 Tue 17/10/23 Sat 21/10/23 8 days
658 [Z3BKD] Drain 182 days Sat 15/4/23 Mon 13/11/23 Mon 1/5/23 Fri 8/12/23 13 days
659 [Z3BKD] Sump 2100x2100mm (M2) 10 days Sat 15/4/23 Wed 26/4/23 Mon 29/5/23 Thu 8/6/23 37 days
660 Sump base, wall and top slab 10 days Sat 15/4/23 Wed 26/4/23 Mon 29/5/23 Thu 8/6/23 37 days
661 [Z3BKD] Sump 1200x1200mm (F3) 25 days Sat 15/4/23 Sat 13/5/23 Mon 29/5/23 Thu 13/7/23 37 days
662 Jack‐in pile (4pts, 0.2x0.2x18.2m) 10 days Sat 15/4/23 Wed 26/4/23 Mon 29/5/23 Thu 8/6/23 37 days
663 Sump base, wall and top slab 15 days Thu 27/4/23 Sat 13/5/23 Tue 27/6/23 Thu 13/7/23 52 days
664 [Z3BKD] Box culvert 0.6x1.3x18.5m (F3‐M2) 40 days Thu 27/4/23 Mon 12/6/23 Fri 9/6/23 Mon 31/7/23 37 days
665 Jack‐in pile (20pts, 0.15x0.15x17.7m) 15 days Thu 27/4/23 Sat 13/5/23 Fri 9/6/23 Mon 26/6/23 37 days
666 Utility services 10 days Mon 15/5/23 Thu 25/5/23 Mon 3/7/23 Thu 13/7/23 42 days
667 Box culvert base, wall and top slab 15 days Fri 26/5/23 Mon 12/6/23 Fri 14/7/23 Mon 31/7/23 42 days
668 [Z3BKD] Sump 2100x2100mm (M) 35 days Mon 15/5/23 Fri 23/6/23 Tue 27/6/23 Fri 11/8/23 37 days
669 Jack‐in pile (4pts, 0.2x0.2x18.4m) 10 days Mon 15/5/23 Thu 25/5/23 Tue 27/6/23 Fri 7/7/23 37 days
670 Sump base, wall and top slab 10 days Tue 13/6/23 Fri 23/6/23 Tue 1/8/23 Fri 11/8/23 42 days
671 [Z3BKD] Sump 1700x1700mm (M1) 20 days Fri 30/6/23 Sat 22/7/23 Sat 8/7/23 Wed 23/8/23 7 days
672 Jack‐in pile (4pts, 0.2x0.2x15.9m) 10 days Fri 30/6/23 Tue 11/7/23 Sat 8/7/23 Wed 19/7/23 7 days
673 Sump base, wall and top slab 10 days Wed 12/7/23 Sat 22/7/23 Sat 12/8/23 Wed 23/8/23 27 days
674 [Z3BKD] Box culvert 1.1x1.2x16m (M1‐M) 60 days Wed 12/7/23 Tue 19/9/23 Thu 20/7/23 Fri 8/12/23 7 days
675 Jack‐in pile (16pts, 0.2x0.2x17.05m) 15 days Wed 12/7/23 Fri 28/7/23 Thu 20/7/23 Sat 5/8/23 7 days
676 Box culvert base, wall and top slab 20 days Mon 28/8/23 Tue 19/9/23 Thu 16/11/23 Fri 8/12/23 69 days
677 [Z3BKD] Sump 1700x1700mm (K3) 10 days Mon 24/7/23 Thu 3/8/23 Thu 24/8/23 Mon 4/9/23 27 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 11
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
678 Sump base, wall and top slab 10 days Mon 24/7/23 Thu 3/8/23 Thu 24/8/23 Mon 4/9/23 27 days
679 [Z3BKD] Sump 1200x1200mm (F1) 20 days Sat 29/7/23 Mon 21/8/23 Mon 7/8/23 Fri 15/9/23 7 days
680 Jack‐in pile (4pts, 0.2x0.2x 14.6m) 10 days Sat 29/7/23 Wed 9/8/23 Mon 7/8/23 Thu 17/8/23 7 days
681 Sump base, wall and top slab 10 days Thu 10/8/23 Mon 21/8/23 Tue 5/9/23 Fri 15/9/23 22 days
682 [Z3BKD] Box culvert 0.6x1.1x14.2m (F1‐K3) 45 days Thu 10/8/23 Sat 30/9/23 Fri 18/8/23 Mon 9/10/23 7 days
683 Jack‐in pile (16pts, 0.15x0.15x17.2m) 15 days Thu 10/8/23 Sat 26/8/23 Fri 18/8/23 Mon 4/9/23 7 days
684 Utility services 10 days Mon 28/8/23 Thu 7/9/23 Tue 5/9/23 Fri 15/9/23 7 days
685 Box culvert base, wall and top slab 20 days Fri 8/9/23 Sat 30/9/23 Sat 16/9/23 Mon 9/10/23 7 days
686 [Z3BKD] Sump 1200x1200mm (I1) 20 days Wed 20/9/23 Thu 12/10/23 Tue 26/9/23 Fri 20/10/23 5 days
687 Jack‐in pile (0.2x0.2x12.7m) 10 days Wed 20/9/23 Sat 30/9/23 Tue 26/9/23 Fri 6/10/23 5 days
688 Sump base, wall and top slab 10 days Mon 2/10/23 Thu 12/10/23 Tue 10/10/23 Fri 20/10/23 7 days
689 [Z3BKD] Sump 2100x2100mm (I) 10 days Fri 13/10/23 Tue 24/10/23 Sat 21/10/23 Wed 1/11/23 7 days
690 Sump base, wall and top slab 10 days Fri 13/10/23 Tue 24/10/23 Sat 21/10/23 Wed 1/11/23 7 days
691 [Z3BKD] Box culvert 1.1x2.6x17.7m (I1‐I) 37 days Mon 2/10/23 Mon 13/11/23 Sat 7/10/23 Sat 18/11/23 5 days
692 Jack‐in pile (18pts, 0.2x0.2x 18.5m) 12 days Mon 2/10/23 Sat 14/10/23 Sat 7/10/23 Fri 20/10/23 5 days
693 Utility services 10 days Mon 16/10/23 Thu 26/10/23 Sat 21/10/23 Wed 1/11/23 5 days
694 Box culvert base, wall and top slab 15 days Fri 27/10/23 Mon 13/11/23 Thu 2/11/23 Sat 18/11/23 5 days
695 [Z3BKD] Covered Drain 1400mm (BKD Westbound/CH0+600 ‐ 20 days Sat 15/4/23 Mon 8/5/23 Mon 1/5/23 Tue 23/5/23 13 days
CH0+670)
696 Drain base, wall and top slab 20 days Sat 15/4/23 Mon 8/5/23 Mon 1/5/23 Tue 23/5/23 13 days
697 [Z3BKD] Covered Drain 1400mm (BKD Westbound/CH0+535 ‐ 18 days Tue 9/5/23 Mon 29/5/23 Wed 24/5/23 Tue 13/6/23 13 days
CH0+600)
698 Drain base, wall and top slab 18 days Tue 9/5/23 Mon 29/5/23 Wed 24/5/23 Tue 13/6/23 13 days
699 [Z3BKD] Covered Drain 1100mm (BKD Westbound/CH0+360 ‐ 25 days Tue 30/5/23 Tue 27/6/23 Wed 14/6/23 Wed 12/7/23 13 days
CH0+470)
700 Drain base, wall and top slab 25 days Tue 30/5/23 Tue 27/6/23 Wed 14/6/23 Wed 12/7/23 13 days
701 [Z3BKD] Covered Drain 1100mm (BKD Westbound/CH0+470 ‐ 14 days Fri 30/6/23 Sat 15/7/23 Tue 19/9/23 Wed 4/10/23 69 days
CH0+510)
702 Drain base, wall and top slab 14 days Fri 30/6/23 Sat 15/7/23 Tue 19/9/23 Wed 4/10/23 69 days
703 [Z3BKD] Concealed Drain 1100mm (BKD Eastbound/CH0+670  20 days Mon 17/7/23 Tue 8/8/23 Thu 5/10/23 Fri 27/10/23 69 days
‐ CH0+700)
704 Drain base, wall and top slab 20 days Mon 17/7/23 Tue 8/8/23 Thu 5/10/23 Fri 27/10/23 69 days
705 [Z3BKD] Concealed Drain 1400mm (BKD Eastbound/CH0+700  10 days Wed 9/8/23 Sat 19/8/23 Sat 28/10/23 Wed 8/11/23 69 days
‐ CH0+720)
706 Drain base, wall and top slab 10 days Wed 9/8/23 Sat 19/8/23 Sat 28/10/23 Wed 8/11/23 69 days
707 [Z3BKD] Concealed Drain 1400mm (BKD  12 days Wed 20/9/23 Tue 3/10/23 Thu 9/11/23 Wed 22/11/23 43 days
Westbound/CH0+670 ‐ CH0+720)
708 Drain base, wall and top slab 12 days Wed 20/9/23 Tue 3/10/23 Thu 9/11/23 Wed 22/11/23 43 days
709 [Z3BKD] Concealed Drain 1400mm (BKD  14 days Wed 4/10/23 Thu 19/10/23 Thu 23/11/23 Fri 8/12/23 43 days
Westbound/CH0+720 ‐ CH0+796)
710 Drain base, wall and top slab 14 days Wed 4/10/23 Thu 19/10/23 Thu 23/11/23 Fri 8/12/23 43 days
711 [Z3BKD] Covered Drain 1100mm (BKD Eastbound/CH0+360 ‐  22 days Mon 7/8/23 Thu 31/8/23 Mon 25/9/23 Thu 19/10/23 42 days
CH0+515)
712 Drain base, wall and top slab 22 days Mon 7/8/23 Thu 31/8/23 Mon 25/9/23 Thu 19/10/23 42 days
713 [Z3BKD] Covered Drain 1100mm (BKD Eastbound/CH0+535 ‐  14 days Wed 6/9/23 Thu 21/9/23 Fri 20/10/23 Sat 4/11/23 38 days
CH0+600)
714 Drain base, wall and top slab 14 days Wed 6/9/23 Thu 21/9/23 Fri 20/10/23 Sat 4/11/23 38 days
715 [Z3BKD] Concealed Drain 1400mm (BKD Eastbound/CH0+720  14 days Fri 22/9/23 Sat 7/10/23 Fri 17/11/23 Sat 2/12/23 48 days
‐ CH0+796)
716 Drain base, wall and top slab 14 days Fri 22/9/23 Sat 7/10/23 Fri 17/11/23 Sat 2/12/23 48 days
717 [Z3BKD] Covered Drain 1100mm (BKD Eastbound/CH0+515 ‐  12 days Fri 13/10/23 Thu 26/10/23 Mon 23/10/23 Sat 4/11/23 8 days
CH0+535)
718 Drain base, wall and top slab 12 days Fri 13/10/23 Thu 26/10/23 Mon 23/10/23 Sat 4/11/23 8 days
719 [Z3BKD] Covered Drain 600mm (BKD Centre  48 days Fri 30/6/23 Thu 24/8/23 Sat 8/7/23 Fri 1/9/23 7 days
Median/CH0+360 ‐ CH0+506)
720 Jack‐in pile (146pts, 0.15x0.15x 16.2m) 20 days Fri 30/6/23 Sat 22/7/23 Sat 8/7/23 Mon 31/7/23 7 days
721 Drain base, wall and top slab 28 days Mon 24/7/23 Thu 24/8/23 Tue 1/8/23 Fri 1/9/23 7 days
722 [Z3BKD] Covered Drain 600mm (BKD Centre  42 days Fri 25/8/23 Thu 12/10/23 Sat 2/9/23 Fri 20/10/23 7 days
Median/CH0+522 ‐ CH0+623)
723 Jack‐in pile (102pts, 0.15x0.15x 16.2m) 20 days Fri 25/8/23 Sat 16/9/23 Sat 2/9/23 Mon 25/9/23 7 days
724 Drain base, wall and top slab 22 days Mon 18/9/23 Thu 12/10/23 Tue 26/9/23 Fri 20/10/23 7 days
725 [Z3BKD] Covered Drain 600mm (BKD Centre  47 days Mon 18/9/23 Fri 10/11/23 Sat 30/9/23 Sat 18/11/23 7 days
Median/CH0+652 ‐ CH0+792)
726 Jack‐in pile (140pts, 0.15x0.15x 11.5m) 18 days Mon 18/9/23 Sat 7/10/23 Sat 30/9/23 Fri 20/10/23 11 days
727 Drain base, wall and top slab 25 days Fri 13/10/23 Fri 10/11/23 Sat 21/10/23 Sat 18/11/23 7 days
728 [Z3BKD] Bus Shelter 64 days Thu 30/11/23 Mon 12/2/24 Fri 12/1/24 Fri 23/2/24 10 days
729 [Z3BKD] Bus Shelter No.2  37 days Thu 30/11/23 Thu 11/1/24 Fri 12/1/24 Fri 23/2/24 37 days
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 12
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
730 Structure 36 days Thu 30/11/23 Wed 10/1/24 Fri 12/1/24 Thu 22/2/24 37 days
735 M&E  10 days Sat 30/12/23 Wed 10/1/24 Mon 12/2/24 Thu 22/2/24 37 days
738 Completion of Bus Shelter No.2  1 day Thu 11/1/24 Thu 11/1/24 Fri 23/2/24 Fri 23/2/24 37 days
739 [Z3BKD] Bus Shelter No.3 37 days Thu 30/11/23 Thu 11/1/24 Fri 12/1/24 Fri 23/2/24 37 days
740 Structure 36 days Thu 30/11/23 Wed 10/1/24 Fri 12/1/24 Thu 22/2/24 37 days
745 M&E  10 days Sat 30/12/23 Wed 10/1/24 Mon 12/2/24 Thu 22/2/24 37 days
748 Completion of Bus Shelter No.3 1 day Thu 11/1/24 Thu 11/1/24 Fri 23/2/24 Fri 23/2/24 37 days
749 [Z3BKD] Bus Shelter No.6 37 days Tue 26/12/23 Tue 6/2/24 Fri 12/1/24 Fri 23/2/24 15 days
750 Structure 36 days Tue 26/12/23 Mon 5/2/24 Fri 12/1/24 Thu 22/2/24 15 days
755 M&E  10 days Thu 25/1/24 Mon 5/2/24 Mon 12/2/24 Thu 22/2/24 15 days
758 Completion of Bus Shelter No.6 1 day Tue 6/2/24 Tue 6/2/24 Fri 23/2/24 Fri 23/2/24 15 days
759 [Z3BKD] Bus Shelter No.7 37 days Mon 1/1/24 Mon 12/2/24 Fri 12/1/24 Fri 23/2/24 10 days
760 Structure 36 days Mon 1/1/24 Sat 10/2/24 Fri 12/1/24 Thu 22/2/24 10 days
765 M&E  10 days Wed 31/1/24 Sat 10/2/24 Mon 12/2/24 Thu 22/2/24 10 days
768 Completion of Bus Shelter No.7 1 day Mon 12/2/24 Mon 12/2/24 Fri 23/2/24 Fri 23/2/24 10 days
769 [Z3BKD] Staircase and Ramp 84 days Mon 7/8/23 Sat 11/11/23 Sat 21/10/23 Fri 26/1/24 65 days
770 [Z3BKD] Ramp at MSCP Block 408 28 days Mon 7/8/23 Thu 7/9/23 Sat 21/10/23 Wed 22/11/23 65 days
771 [Z3BKD] High Linkway at Block 409A 28 days Fri 8/9/23 Tue 10/10/23 Thu 23/11/23 Mon 25/12/23 65 days
772 [Z3BKD] S&R at Seletar Spring Condominium 28 days Wed 11/10/23 Sat 11/11/23 Tue 26/12/23 Fri 26/1/24 65 days
773 [Z3BKD] Road 66 days Fri 27/10/23 Thu 11/1/24 Mon 6/11/23 Fri 26/1/24 8 days
774 [Z3BKD] BKD Eastbound/CH0+360 ‐ CH0+540 39 days Fri 27/10/23 Mon 11/12/23 Mon 6/11/23 Wed 3/1/24 8 days
775 Underground utility service 7 days Fri 27/10/23 Fri 3/11/23 Mon 6/11/23 Mon 13/11/23 8 days
776 Subgrade and sub‐base 10 days Sat 4/11/23 Wed 15/11/23 Tue 14/11/23 Fri 24/11/23 8 days
777 Kerb, drop‐inlet chamber and scupper pipe 12 days Thu 16/11/23 Wed 29/11/23 Sat 25/11/23 Fri 8/12/23 8 days
778 Base course and pavement 10 days Thu 30/11/23 Mon 11/12/23 Sat 23/12/23 Wed 3/1/24 20 days
779 [Z3BKD] BKD Westbound/CH0+360 ‐ CH0+540 39 days Fri 27/10/23 Mon 11/12/23 Sat 9/12/23 Fri 26/1/24 37 days
780 Underground utility service 7 days Fri 27/10/23 Fri 3/11/23 Sat 9/12/23 Sat 16/12/23 37 days
781 Subgrade and sub‐base 10 days Sat 4/11/23 Wed 15/11/23 Mon 18/12/23 Thu 28/12/23 37 days
782 Kerb, drop‐inlet chamber and scupper pipe 12 days Thu 16/11/23 Wed 29/11/23 Fri 29/12/23 Thu 11/1/24 37 days
783 Base course and pavement 10 days Thu 30/11/23 Mon 11/12/23 Tue 16/1/24 Fri 26/1/24 40 days
784 [Z3BKD] BKD Eastbound/CH0+540 ‐ CH0+670 39 days Tue 14/11/23 Thu 28/12/23 Mon 20/11/23 Mon 15/1/24 5 days
785 Underground utility service 7 days Tue 14/11/23 Tue 21/11/23 Mon 20/11/23 Mon 27/11/23 5 days
786 Subgrade and sub‐base 10 days Wed 22/11/23 Sat 2/12/23 Tue 28/11/23 Fri 8/12/23 5 days
787 Kerb, drop‐inlet chamber and scupper pipe 12 days Mon 4/12/23 Sat 16/12/23 Sat 9/12/23 Fri 22/12/23 5 days
788 Base course and pavement 10 days Mon 18/12/23 Thu 28/12/23 Thu 4/1/24 Mon 15/1/24 15 days
789 [Z3BKD] BKD Westbound/CH0+540 ‐ CH0+670 39 days Tue 14/11/23 Thu 28/12/23 Wed 13/12/23 Fri 26/1/24 25 days
790 Underground utility service 7 days Tue 14/11/23 Tue 21/11/23 Wed 13/12/23 Wed 20/12/23 25 days
791 Subgrade and sub‐base 10 days Wed 22/11/23 Sat 2/12/23 Thu 21/12/23 Mon 1/1/24 25 days
792 Kerb, drop‐inlet chamber and scupper pipe 12 days Mon 4/12/23 Sat 16/12/23 Tue 2/1/24 Mon 15/1/24 25 days
793 Base course and pavement 10 days Mon 18/12/23 Thu 28/12/23 Tue 16/1/24 Fri 26/1/24 25 days
794 [Z3BKD] BKD Eastbound/CH0+670 ‐ CH0+796 44 days Wed 22/11/23 Thu 11/1/24 Mon 4/12/23 Fri 26/1/24 10 days
795 Underground utility service 7 days Wed 22/11/23 Wed 29/11/23 Mon 4/12/23 Mon 11/12/23 10 days
796 Subgrade and sub‐base 10 days Mon 4/12/23 Thu 14/12/23 Tue 12/12/23 Fri 22/12/23 7 days
797 Kerb, drop‐inlet chamber and scupper pipe 12 days Mon 18/12/23 Sat 30/12/23 Sat 23/12/23 Fri 5/1/24 5 days
798 Base course and pavement 10 days Mon 1/1/24 Thu 11/1/24 Tue 16/1/24 Fri 26/1/24 13 days
799 [Z3BKD] BKD Westbound/CH0+670 ‐ CH0+796 39 days Wed 22/11/23 Fri 5/1/24 Sat 9/12/23 Fri 26/1/24 15 days
800 Underground utility service 7 days Wed 22/11/23 Wed 29/11/23 Sat 9/12/23 Sat 16/12/23 15 days
801 Subgrade and sub‐base 10 days Thu 30/11/23 Mon 11/12/23 Mon 18/12/23 Thu 28/12/23 15 days
802 Kerb, drop‐inlet chamber and scupper pipe 12 days Tue 12/12/23 Mon 25/12/23 Fri 29/12/23 Thu 11/1/24 15 days
803 Base course and pavement 10 days Tue 26/12/23 Fri 5/1/24 Tue 16/1/24 Fri 26/1/24 18 days
804 [Z3BKD] Ancillary work 24 days Fri 12/1/24 Thu 8/2/24 Sat 27/1/24 Fri 23/2/24 13 days
805 Tree planting & turfing 24 days Fri 12/1/24 Thu 8/2/24 Sat 27/1/24 Fri 23/2/24 13 days
806 Railing 24 days Fri 12/1/24 Thu 8/2/24 Sat 27/1/24 Fri 23/2/24 13 days
807 Lamp post 24 days Fri 12/1/24 Thu 8/2/24 Sat 27/1/24 Fri 23/2/24 13 days
808 [Z3] Fernvale Link CH0 ‐ CH0+100 340 days Wed 18/1/23 Sat 17/2/24 Tue 30/5/23 Fri 23/2/24 5 days
809 [Z3FL] Site establishment 15 days Wed 18/1/23 Fri 3/2/23 Wed 5/7/23 Fri 21/7/23 144 days
810 [Z3FL] Removal of existing trees, road kerb and railing 15 days Sat 4/2/23 Tue 21/2/23 Sat 22/7/23 Tue 8/8/23 144 days
811 [Z3FL] Retaining wall 62 days Tue 11/7/23 Wed 20/9/23 Wed 9/8/23 Thu 19/10/23 25 days
812 [Z3FL] RW Type 4 (FL Southbound/CH0+035 ‐ CH0+100) 62 days Tue 11/7/23 Wed 20/9/23 Wed 9/8/23 Thu 19/10/23 25 days
813 ERSS (Sheet Pile) 15 days Tue 11/7/23 Thu 27/7/23 Wed 9/8/23 Fri 25/8/23 25 days
814 Excavation of RW base 10 days Fri 28/7/23 Tue 8/8/23 Sat 26/8/23 Wed 6/9/23 25 days
815 RW base (8.45m wide) 14 days Wed 9/8/23 Thu 24/8/23 Thu 7/9/23 Fri 22/9/23 25 days
816 RW wall (4.5m height) 16 days Fri 25/8/23 Tue 12/9/23 Sat 23/9/23 Wed 11/10/23 25 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 13
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
817 ERSS removal and backfill 7 days Wed 13/9/23 Wed 20/9/23 Thu 12/10/23 Thu 19/10/23 25 days
818 [Z3FL] Drain 164 days Sat 20/5/23 Mon 27/11/23 Tue 30/5/23 Sat 16/12/23 8 days
819 [Z3FL]Sump 1700x1700mm (X1) 18 days Sat 20/5/23 Fri 9/6/23 Tue 30/5/23 Tue 20/6/23 8 days
820 Jack‐in Pile (0.2x0.2x19.6m) 8 days Sat 20/5/23 Mon 29/5/23 Tue 30/5/23 Wed 7/6/23 8 days
821 Sump base, wall and top slab 10 days Tue 30/5/23 Fri 9/6/23 Fri 9/6/23 Tue 20/6/23 9 days
822 [Z3FL] Sump 1200x1200mm (X2) 20 days Tue 30/5/23 Wed 21/6/23 Thu 8/6/23 Sat 1/7/23 8 days
823 Jack‐in Pile (0.2x0.2x18.6m) 8 days Tue 30/5/23 Wed 7/6/23 Thu 8/6/23 Fri 16/6/23 8 days
824 Sump base, wall and top slab 10 days Sat 10/6/23 Wed 21/6/23 Wed 21/6/23 Sat 1/7/23 9 days
825 [Z3FL] Box culvert 0.6x1.4x12.5m (X2‐X1) 22 days Thu 8/6/23 Mon 3/7/23 Sat 17/6/23 Thu 13/7/23 8 days
826 Jack‐in pile (14pts, 0.15x0.15x 18.6m) 10 days Thu 8/6/23 Mon 19/6/23 Sat 17/6/23 Wed 28/6/23 8 days
827 Box culvert base, wall and top slab 10 days Thu 22/6/23 Mon 3/7/23 Mon 3/7/23 Thu 13/7/23 9 days
828 [Z3FL] Sump 1700x1700mm (G) 22 days Tue 20/6/23 Fri 14/7/23 Thu 29/6/23 Tue 25/7/23 8 days
829 Jack‐in pile (4pts, 0.2x0.2x 18.5m) 8 days Tue 20/6/23 Wed 28/6/23 Thu 29/6/23 Fri 7/7/23 8 days
830 Sump base, wall and top slab 10 days Tue 4/7/23 Fri 14/7/23 Fri 14/7/23 Tue 25/7/23 9 days
831 [Z3FL] Sump 1700x1700mm (H) 8 days Thu 21/9/23 Fri 29/9/23 Mon 23/10/23 Tue 31/10/23 27 days
832 Sump base, wall and top slab 8 days Thu 21/9/23 Fri 29/9/23 Mon 23/10/23 Tue 31/10/23 27 days
833 [Z3FL] Box culvert 1.1x2.3x29m (G‐H) 25 days Thu 21/9/23 Thu 19/10/23 Fri 20/10/23 Fri 17/11/23 25 days
834 Jack‐in pile (29pts, 0.2x0.2x18.4m) 10 days Thu 21/9/23 Mon 2/10/23 Fri 20/10/23 Tue 31/10/23 25 days
835 Box culvert base, wall and top slab 15 days Tue 3/10/23 Thu 19/10/23 Wed 1/11/23 Fri 17/11/23 25 days
836 [Z3FL] Covered Drain 1100mm FL Northbound/CH0+010 ‐  33 days Thu 29/6/23 Sat 5/8/23 Sat 8/7/23 Tue 15/8/23 8 days
CH0+100)
837 Jack‐in Pile (76pts, 0.15x0.15x22.6m) 15 days Thu 29/6/23 Sat 15/7/23 Sat 8/7/23 Tue 25/7/23 8 days
838 Drain base, wall and top slab 18 days Mon 17/7/23 Sat 5/8/23 Wed 26/7/23 Tue 15/8/23 8 days
839 [Z3FL] Covered Drain 600mm FL Northbound/CH0 ‐ CH0+020) 33 days Mon 17/7/23 Wed 23/8/23 Sat 23/9/23 Sat 21/10/23 51 days

840 Jack‐in Pile (12pts, 0.15x0.15x18.6m) 10 days Mon 17/7/23 Thu 27/7/23 Sat 23/9/23 Wed 4/10/23 59 days


841 Drain base, wall and top slab 15 days Mon 7/8/23 Wed 23/8/23 Thu 5/10/23 Sat 21/10/23 51 days
842 [Z3FL] Sump 1700x1700mm (Y1) 20 days Wed 13/9/23 Thu 5/10/23 Tue 3/10/23 Wed 25/10/23 17 days
843 Jack‐in Pile (0.2x0.2x18.6m) 10 days Wed 13/9/23 Sat 23/9/23 Tue 3/10/23 Fri 13/10/23 17 days
844 Sump base, wall and top slab 10 days Mon 25/9/23 Thu 5/10/23 Sat 14/10/23 Wed 25/10/23 17 days
845 [Z3FL] Sump 1200x1200mm (Y2) 20 days Mon 25/9/23 Tue 17/10/23 Sat 14/10/23 Mon 6/11/23 17 days
846 Jack‐in Pile (0.2x0.2x17.9m) 10 days Mon 25/9/23 Thu 5/10/23 Sat 14/10/23 Wed 25/10/23 17 days
847 Sump base, wall and top slab 10 days Fri 6/10/23 Tue 17/10/23 Thu 26/10/23 Mon 6/11/23 17 days
848 [Z3FL] Box culvert 0.6x1.5x10.6m (Y2‐Y1) 20 days Fri 6/10/23 Sat 28/10/23 Thu 26/10/23 Fri 17/11/23 17 days
849 Jack‐in pile (11pts, 0.15x0.15x 18.3m) 10 days Fri 6/10/23 Tue 17/10/23 Thu 26/10/23 Mon 6/11/23 17 days
850 Box culvert base, wall and top slab 10 days Wed 18/10/23 Sat 28/10/23 Tue 7/11/23 Fri 17/11/23 17 days
851 [Z3FL]Covered Drain 1100mm FL Southbound/CH0+035 ‐  25 days Fri 20/10/23 Fri 17/11/23 Sat 18/11/23 Sat 16/12/23 25 days
CH0+100)
852 Drain base, wall and top slab 25 days Fri 20/10/23 Fri 17/11/23 Sat 18/11/23 Sat 16/12/23 25 days
853 [Z3FL] Covered Drain 1100mm FL Southbound/CH0+010 ‐  20 days Wed 18/10/23 Thu 9/11/23 Tue 7/11/23 Wed 29/11/23 17 days
CH0+035)
854 Jack‐in pile (16pts, 0.15x0.15x8.8m) 10 days Wed 18/10/23 Sat 28/10/23 Tue 7/11/23 Fri 17/11/23 17 days
855 Drain base, wall and top slab 10 days Mon 30/10/23 Thu 9/11/23 Sat 18/11/23 Wed 29/11/23 17 days
856 [Z3FL] Covered Drain 600mm FL Southbound/CH0 ‐ CH0+020) 25 days Mon 30/10/23 Mon 27/11/23 Sat 18/11/23 Sat 16/12/23 17 days

857 Jack‐in Pile (18pts, 0.15x0.15x18.6m) 10 days Mon 30/10/23 Thu 9/11/23 Sat 18/11/23 Wed 29/11/23 17 days


858 Drain base, wall and top slab 15 days Fri 10/11/23 Mon 27/11/23 Thu 30/11/23 Sat 16/12/23 17 days
859 [Z3FL] Ramp 100 days Mon 7/8/23 Thu 30/11/23 Wed 16/8/23 Fri 23/2/24 8 days
860 [Z3FL] S&R at Block 413 18 days Mon 7/8/23 Sat 26/8/23 Wed 16/8/23 Tue 5/9/23 8 days
861 Ramp 18 days Mon 7/8/23 Sat 26/8/23 Wed 16/8/23 Tue 5/9/23 8 days
862 [Z3FL] S&R at Block 415A 82 days Mon 28/8/23 Thu 30/11/23 Sat 16/9/23 Fri 23/2/24 17 days
863 Diversion of footpath 14 days Mon 28/8/23 Tue 12/9/23 Sat 16/9/23 Mon 2/10/23 17 days
864 Ramp 18 days Fri 10/11/23 Thu 30/11/23 Sat 3/2/24 Fri 23/2/24 73 days
865 [Z3FL] Road 49 days Thu 30/11/23 Thu 25/1/24 Mon 18/12/23 Wed 31/1/24 5 days
866 [Z3FL] FL Northbound/CH0 ‐ CH0+100 49 days Thu 30/11/23 Thu 25/1/24 Mon 18/12/23 Wed 31/1/24 5 days
867 Underground utility service 7 days Thu 30/11/23 Thu 7/12/23 Mon 18/12/23 Mon 25/12/23 15 days
868 Subgrade and sub‐base 10 days Fri 15/12/23 Tue 26/12/23 Tue 26/12/23 Fri 5/1/24 9 days
869 Kerb, drop‐inlet chamber and scupper pipe 12 days Mon 1/1/24 Sat 13/1/24 Sat 6/1/24 Fri 19/1/24 5 days
870 Base course and pavement 10 days Mon 15/1/24 Thu 25/1/24 Sat 20/1/24 Wed 31/1/24 5 days
871 [Z3FL] FL Southbound/CH0 ‐ CH0+100 49 days Thu 30/11/23 Thu 25/1/24 Mon 18/12/23 Wed 31/1/24 5 days
872 Underground utility service 7 days Thu 30/11/23 Thu 7/12/23 Mon 18/12/23 Mon 25/12/23 15 days
873 Subgrade and sub‐base 10 days Fri 15/12/23 Tue 26/12/23 Tue 26/12/23 Fri 5/1/24 9 days
874 Kerb, drop‐inlet chamber and scupper pipe 12 days Mon 1/1/24 Sat 13/1/24 Sat 6/1/24 Fri 19/1/24 5 days
875 Base course and pavement 10 days Mon 15/1/24 Thu 25/1/24 Sat 20/1/24 Wed 31/1/24 5 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 14
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
876 [Z3FL] Ancillary work 20 days Fri 26/1/24 Sat 17/2/24 Thu 1/2/24 Fri 23/2/24 5 days
877 Tree planting& turfing 20 days Fri 26/1/24 Sat 17/2/24 Thu 1/2/24 Fri 23/2/24 5 days
878 Railing 20 days Fri 26/1/24 Sat 17/2/24 Thu 1/2/24 Fri 23/2/24 5 days
879 Lamp post 20 days Fri 26/1/24 Sat 17/2/24 Thu 1/2/24 Fri 23/2/24 5 days
880 [Z3] Completion of Zone 3 0 days Fri 23/2/24 Fri 23/2/24 Fri 23/2/24 Fri 23/2/24 1 day 23/2
881 Zone 4 Vehicular Bridge Construction  460 days Mon 5/9/22 Fri 23/2/24 Sat 17/9/22 Fri 23/2/24 1 day
882  [Z4] Preliminaries 205 days Mon 5/9/22 Mon 1/5/23 Sat 17/9/22 Sat 23/9/23 11 days
883 Hydrographic & Side Scan Sonar Survey at Sungei Punggol  40 days Mon 5/9/22 Thu 20/10/22 Sat 17/9/22 Wed 2/11/22 11 days
884 Submission / Approval PUB for Bridge Method Statement  80 days Mon 5/9/22 Tue 6/12/22 Sat 17/9/22 Mon 19/12/22 11 days
885 Submission / Approval Nparks for Works Near PCN 80 days Mon 5/9/22 Tue 6/12/22 Sat 17/9/22 Mon 19/12/22 11 days
886 Submission / Approval LTA Pot Bearing 55 days Mon 5/9/22 Mon 7/11/22 Sat 28/1/23 Sat 1/4/23 125 days
887 Fabrication, Testing & Delivery of Pot Bearing 150 days Tue 8/11/22 Mon 1/5/23 Mon 3/4/23 Sat 23/9/23 125 days
888 [Z4] Construction 351 days Wed 7/12/22 Fri 19/1/24 Tue 20/12/22 Fri 23/2/24 11 days
889 Preparation of Site Access  25 days Wed 7/12/22 Wed 4/1/23 Tue 20/12/22 Tue 17/1/23 11 days
890 Moblization & Pile Load Test 55 days Thu 5/1/23 Thu 9/3/23 Wed 18/1/23 Wed 22/3/23 11 days
891 Bore Pile (On‐shore) P12 to P22 21 days Fri 10/3/23 Mon 3/4/23 Thu 23/3/23 Sat 15/4/23 11 days
892 Moblization & Setting Up for Marine Bore Pile Works 30 days Fri 10/3/23 Thu 13/4/23 Thu 23/3/23 Wed 26/4/23 11 days
893 Bore Pile (Marine) P25, P26, P29, P30 (RCD Method) 45 days Fri 14/4/23 Mon 5/6/23 Thu 27/4/23 Sat 17/6/23 11 days
894 Bore Pile (On‐shore) P1 to P11 30 days Tue 4/4/23 Mon 8/5/23 Mon 8/5/23 Sat 10/6/23 29 days
895 Bore Pile (Marine) P23, P24, P27, P28 (RCD Method) 45 days Tue 6/6/23 Thu 27/7/23 Mon 19/6/23 Wed 9/8/23 11 days
896 Pier Cross Head P1 & P2 Falsework & Casting 45 days Fri 30/6/23 Mon 21/8/23 Thu 3/8/23 Sat 23/9/23 29 days
897 Pile Cap A1 & A2 40 days Tue 9/5/23 Fri 23/6/23 Mon 12/6/23 Thu 27/7/23 29 days
898 Abutment Wall A1 & A2 45 days Sat 24/6/23 Tue 15/8/23 Thu 3/8/23 Sat 23/9/23 34 days
899 Beam Launching (24 Precast Beams) 30 days Tue 22/8/23 Mon 25/9/23 Mon 25/9/23 Sat 28/10/23 29 days
900 Deck Slab Casting 75 days Fri 8/9/23 Mon 4/12/23 Fri 13/10/23 Mon 8/1/24 30 days
901 Single Planter Trough Wall / Slab Cover 45 days Tue 31/10/23 Thu 21/12/23 Tue 5/12/23 Thu 25/1/24 30 days
902 Dual Planter Trough with Noise Barrier & Parapet Wall  45 days Fri 24/11/23 Mon 15/1/24 Fri 29/12/23 Mon 19/2/24 30 days
903 Ancillary Works (Pipes & Lamp Post, Railing, Painting etc) 42 days Fri 24/11/23 Thu 11/1/24 Fri 29/12/23 Thu 15/2/24 30 days
904 Approach Slab A1 & A2 (Piling & Slab Casting) 60 days Fri 8/9/23 Thu 16/11/23 Fri 8/12/23 Thu 15/2/24 78 days
905 Premix & Road Marking 7 days Fri 12/1/24 Fri 19/1/24 Fri 16/2/24 Fri 23/2/24 30 days
906 [Z4] Completion of Zone 4 Vehicular Bridge Construction  0 days Fri 23/2/24 Fri 23/2/24 Fri 23/2/24 Fri 23/2/24 1 day 23/2
907 Zone 5  400 days Tue 1/11/22 Sat 10/2/24 Mon 7/11/22 Thu 25/4/24 5 days
908 [Z5] Buangkok Drive CH0+883 ‐ CH1+344 399 days Tue 1/11/22 Thu 8/2/24 Mon 7/11/22 Thu 25/4/24 5 days
909 [Z5BKD] Site establishment 26 days Tue 1/11/22 Wed 30/11/22 Mon 7/11/22 Tue 6/12/22 5 days
910 [Z5BKD] Site clearance and tree removal 27 days Thu 1/12/22 Sat 31/12/22 Mon 2/1/23 Wed 1/2/23 27 days
911 [Z5BKD] Retaining Wall  188 days Fri 20/1/23 Sat 26/8/23 Fri 17/3/23 Fri 29/9/23 29 days
912 [Z5BKD RW Type 6A (BKD Eastbound/CH0+905 ‐ CH0+992) 116 days Tue 28/2/23 Wed 12/7/23 Fri 24/3/23 Sat 5/8/23 21 days
913 ERSS (open‐cut) 15 days Tue 28/2/23 Thu 16/3/23 Fri 24/3/23 Mon 10/4/23 21 days
914 Excavation of RW base 12 days Thu 23/3/23 Wed 5/4/23 Mon 17/4/23 Sat 29/4/23 21 days
915 Jack‐in Pile 27 days Thu 6/4/23 Sat 6/5/23 Mon 1/5/23 Wed 31/5/23 21 days
916 RW base (11.2m wide) 20 days Mon 8/5/23 Tue 30/5/23 Thu 1/6/23 Fri 23/6/23 21 days
917 RW wall (6.8m height) 30 days Wed 31/5/23 Tue 4/7/23 Sat 24/6/23 Fri 28/7/23 21 days
918 Formwork removal and backfill 7 days Wed 5/7/23 Wed 12/7/23 Sat 29/7/23 Sat 5/8/23 21 days
919 [Z5BKD RW Type 6A(BKD Westbound/CH0+905 ‐ CH0+930) 88 days Tue 7/2/23 Fri 19/5/23 Tue 4/4/23 Mon 28/8/23 48 days
920 ERSS (open‐cut) 10 days Tue 7/2/23 Fri 17/2/23 Tue 4/4/23 Fri 14/4/23 48 days
921 Excavation of RW base 10 days Sat 18/2/23 Wed 1/3/23 Sat 15/4/23 Wed 26/4/23 48 days
922 Jack‐in Pile 20 days Thu 2/3/23 Fri 24/3/23 Thu 27/4/23 Fri 19/5/23 48 days
923 RW base (11.2m wide) 16 days Sat 25/3/23 Wed 12/4/23 Sat 20/5/23 Wed 7/6/23 48 days
924 RW wall (6.9m height) 25 days Thu 13/4/23 Thu 11/5/23 Thu 8/6/23 Thu 6/7/23 48 days
925 Formwork removal and backfill 7 days Fri 12/5/23 Fri 19/5/23 Mon 21/8/23 Mon 28/8/23 86 days
926 [Z5BKD RW Type 5A (BKD Westbound/CH0+930 ‐ CH1+010) 148 days Fri 20/1/23 Tue 11/7/23 Fri 17/3/23 Tue 5/9/23 48 days
927 ERSS (open‐cut) 15 days Fri 20/1/23 Mon 6/2/23 Fri 17/3/23 Mon 3/4/23 48 days
928 Excavation of RW base 10 days Thu 2/3/23 Mon 13/3/23 Fri 2/6/23 Tue 13/6/23 79 days
929 Jack‐in Pile 20 days Sat 25/3/23 Mon 17/4/23 Wed 14/6/23 Thu 6/7/23 69 days
930 RW base (6m wide) 15 days Fri 12/5/23 Mon 29/5/23 Fri 7/7/23 Mon 24/7/23 48 days
931 RW wall (6m height) 30 days Tue 30/5/23 Mon 3/7/23 Tue 25/7/23 Mon 28/8/23 48 days
932 Formwork removal and backfill 7 days Tue 4/7/23 Tue 11/7/23 Tue 29/8/23 Tue 5/9/23 48 days
933 [Z5BKD RW Type 6A (BKD Eastbound/CH0+886 ‐ CH0+905) 70 days Wed 7/6/23 Sat 26/8/23 Tue 11/7/23 Fri 29/9/23 29 days
934 ERSS (open‐cut) 8 days Wed 7/6/23 Thu 15/6/23 Tue 11/7/23 Wed 19/7/23 29 days
935 Excavation of RW base 10 days Fri 16/6/23 Tue 27/6/23 Thu 20/7/23 Mon 31/7/23 29 days
936 Jack‐in Pile 15 days Wed 28/6/23 Fri 14/7/23 Tue 1/8/23 Thu 17/8/23 29 days
937 RW base (11.2m wide) 12 days Sat 15/7/23 Fri 28/7/23 Fri 18/8/23 Thu 31/8/23 29 days
938 RW wall (6.8m height) 18 days Sat 29/7/23 Fri 18/8/23 Fri 1/9/23 Thu 21/9/23 29 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 15
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
939 Formwork removal and backfill 7 days Sat 19/8/23 Sat 26/8/23 Fri 22/9/23 Fri 29/9/23 29 days
940 [Z5BKD RW Type 6A(BKD Westbound/CH0+886 ‐ CH0+905) 70 days Wed 7/6/23 Sat 26/8/23 Tue 11/7/23 Fri 29/9/23 29 days
941 ERSS (open‐cut) 8 days Wed 7/6/23 Thu 15/6/23 Tue 11/7/23 Wed 19/7/23 29 days
942 Excavation of RW base 10 days Fri 16/6/23 Tue 27/6/23 Thu 20/7/23 Mon 31/7/23 29 days
943 Jack‐in Pile 15 days Wed 28/6/23 Fri 14/7/23 Tue 1/8/23 Thu 17/8/23 29 days
944 RW base (11.2m wide) 12 days Sat 15/7/23 Fri 28/7/23 Fri 18/8/23 Thu 31/8/23 29 days
945 RW wall (6.9m height) 18 days Sat 29/7/23 Fri 18/8/23 Fri 1/9/23 Thu 21/9/23 29 days
946 Formwork removal and backfill 7 days Sat 19/8/23 Sat 26/8/23 Fri 22/9/23 Fri 29/9/23 29 days
947 [Z5BKD] Drain 236 days Fri 20/1/23 Sat 21/10/23 Thu 2/2/23 Wed 15/11/23 11 days
948 [Z5BKD] Sump 2700x2700mm (P1) 161 days Fri 20/1/23 Wed 26/7/23 Thu 2/2/23 Sat 19/8/23 11 days
949 Divert exisitng 1.8m open drain 21 days Fri 20/1/23 Mon 13/2/23 Thu 2/2/23 Sat 25/2/23 11 days
950 Mobilisation of jack‐in pile machine 7 days Fri 20/1/23 Fri 27/1/23 Sat 18/2/23 Sat 25/2/23 25 days
951 Jack‐in pile (0.2x0.2x 19.1m) 12 days Tue 14/2/23 Mon 27/2/23 Mon 27/2/23 Sat 11/3/23 11 days
952 Sump base, wall and top slab 12 days Thu 13/7/23 Wed 26/7/23 Mon 7/8/23 Sat 19/8/23 21 days
953 [Z5BKD] Sump 2100x2100mm (P) 12 days Thu 27/7/23 Wed 9/8/23 Mon 21/8/23 Sat 2/9/23 21 days
954 Sump base, wall and top slab 12 days Thu 27/7/23 Wed 9/8/23 Mon 21/8/23 Sat 2/9/23 21 days
955 [Z5BKD] Concealed Drain 1100mm (P‐P1) 185 days Fri 20/1/23 Wed 23/8/23 Mon 27/2/23 Sat 16/9/23 21 days
956 Micropile machine mobilisation 7 days Fri 20/1/23 Fri 27/1/23 Mon 27/2/23 Mon 6/3/23 32 days
957 Micropile (8pts, 0.3x0.3x19.1m) 15 days Sat 28/1/23 Tue 14/2/23 Tue 7/3/23 Thu 23/3/23 32 days
958 Drain base, wall and top slab 12 days Thu 10/8/23 Wed 23/8/23 Mon 4/9/23 Sat 16/9/23 21 days
959 [Z5BKD] Sump 2100x2100mm (O1) 48 days Thu 13/7/23 Wed 6/9/23 Wed 6/9/23 Sat 30/9/23 21 days
960 Jack‐in pile (0.2x0.2x 12.7m) 10 days Thu 13/7/23 Mon 24/7/23 Wed 6/9/23 Sat 16/9/23 47 days
961 Sump base, wall and top slab 12 days Thu 24/8/23 Wed 6/9/23 Mon 18/9/23 Sat 30/9/23 21 days
962 [Z5BKD] Sump 2100x2100mm (R) 12 days Thu 7/9/23 Wed 20/9/23 Mon 2/10/23 Sat 14/10/23 21 days
963 Sump base, wall and top slab 12 days Thu 7/9/23 Wed 20/9/23 Mon 2/10/23 Sat 14/10/23 21 days
964 [Z5BKD] Box culvert 1.1x3x40m (R‐O1‐P) 62 days Tue 25/7/23 Wed 4/10/23 Mon 2/10/23 Sat 28/10/23 21 days
965 Jack‐in pile (40pts, 0.2x0.2x 15.5m) 12 days Tue 25/7/23 Mon 7/8/23 Mon 2/10/23 Sat 14/10/23 59 days
966 Box culvert base, wall and top slab 12 days Thu 21/9/23 Wed 4/10/23 Mon 16/10/23 Sat 28/10/23 21 days
967 [Z5BKD] Covered Drain 1100mm (BKD Eastbound/CH0+962 ‐  15 days Thu 5/10/23 Sat 21/10/23 Mon 30/10/23 Wed 15/11/23 21 days
CH0+983)
968 Drain base, wall and top slab 15 days Thu 5/10/23 Sat 21/10/23 Mon 30/10/23 Wed 15/11/23 21 days
969 [Z5BKD] Covered Drain 1100mm (BKD Centre Median/CH0+896  40 days Mon 28/8/23 Thu 12/10/23 Sat 30/9/23 Wed 15/11/23 29 days
‐ CH0+998)
970 Jack‐in pile (102pts, 0.15x0.15x 14.75m) 25 days Mon 28/8/23 Mon 25/9/23 Sat 30/9/23 Sat 28/10/23 29 days
971 Drain base, wall and top slab 15 days Tue 26/9/23 Thu 12/10/23 Mon 30/10/23 Wed 15/11/23 29 days
972 [Z5BKD] Sump 1700x1700mm (Q1) 20 days Tue 28/2/23 Wed 22/3/23 Mon 13/3/23 Mon 24/4/23 11 days
973 Jack‐in pile (0.2x0.2x 24.4m) 10 days Tue 28/2/23 Fri 10/3/23 Mon 13/3/23 Thu 23/3/23 11 days
974 Sump base, wall and top slab 10 days Sat 11/3/23 Wed 22/3/23 Thu 13/4/23 Mon 24/4/23 28 days
975 [Z5BKD] Sump 2700x2700mm (Q) 52 days Tue 28/2/23 Fri 28/4/23 Sat 18/3/23 Thu 11/5/23 11 days
976 Divert exisitng 1.8m open drain 20 days Tue 28/2/23 Wed 22/3/23 Sat 18/3/23 Mon 10/4/23 16 days
977 Jack‐in pile (0.2x0.2x 27.1m) 12 days Wed 29/3/23 Tue 11/4/23 Tue 11/4/23 Mon 24/4/23 11 days
978 Sump base, wall and top slab 15 days Wed 12/4/23 Fri 28/4/23 Tue 25/4/23 Thu 11/5/23 11 days
979 [Z5BKD] Box culvert 1.1x1.2x23m (Q1‐Q) 57 days Sat 11/3/23 Tue 16/5/23 Fri 24/3/23 Mon 29/5/23 11 days
980 Jack‐in pile (24pts, 0.2x0.2x 27.3m) 15 days Sat 11/3/23 Tue 28/3/23 Fri 24/3/23 Mon 10/4/23 11 days
981 Box culvert base, wall and top slab 15 days Sat 29/4/23 Tue 16/5/23 Fri 12/5/23 Mon 29/5/23 11 days
982 [Z5BKD] Covered Drain 1800mm (BKD Eastbound/CH1+095 ‐  30 days Wed 17/5/23 Tue 20/6/23 Tue 30/5/23 Mon 3/7/23 11 days
CH1+290)
983 Drain top slab 30 days Wed 17/5/23 Tue 20/6/23 Tue 30/5/23 Mon 3/7/23 11 days
984 [Z5BKD] Covered Drain 600mm (BKD Centre Median/CH1+160 ‐  102 days Wed 12/4/23 Tue 8/8/23 Wed 24/5/23 Mon 21/8/23 11 days
CH1+290)
985 Jack‐in pile (130pts, 0.15x0.15x 18.5m) 35 days Wed 12/4/23 Mon 22/5/23 Wed 24/5/23 Mon 3/7/23 36 days
986 Drain base, wall and top slab 42 days Wed 21/6/23 Tue 8/8/23 Tue 4/7/23 Mon 21/8/23 11 days
987 [Z5BKD] Covered Drain 1800mm (BKD Eastbound/CH0+992 ‐  169 days Thu 23/3/23 Thu 5/10/23 Sat 20/5/23 Wed 18/10/23 11 days
CH1+095)
988 Construction of temporary drain 20 days Thu 23/3/23 Fri 14/4/23 Sat 20/5/23 Mon 12/6/23 50 days
989 Diversion and demolish of existing drain 20 days Sat 15/4/23 Mon 8/5/23 Tue 13/6/23 Wed 5/7/23 50 days
990 Jack‐in pile (104pts, 0.2x0.2x 18.4m) 40 days Tue 9/5/23 Fri 23/6/23 Thu 6/7/23 Mon 21/8/23 50 days
991 Drain base, wall and top slab 40 days Wed 9/8/23 Sat 23/9/23 Tue 22/8/23 Fri 6/10/23 11 days
992 Removal of temporary drain 10 days Mon 25/9/23 Thu 5/10/23 Sat 7/10/23 Wed 18/10/23 11 days
993 [Z5BKD] Covered Drain 1100mm (BKD Westbound/CH0+982 ‐  195 days Fri 20/1/23 Mon 4/9/23 Wed 1/3/23 Fri 13/10/23 34 days
CH1+290)
994 Jack‐in pile (308pts, 0.15x0.15x 20.5m) 75 days Fri 20/1/23 Mon 17/4/23 Wed 1/3/23 Fri 26/5/23 34 days
995 Underground utility service 15 days Tue 18/4/23 Thu 4/5/23 Sat 27/5/23 Tue 13/6/23 34 days
996 Drain base, wall and top slab 105 days Fri 5/5/23 Mon 4/9/23 Wed 14/6/23 Fri 13/10/23 34 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 16
D/248/22
PROPOSED ROAD, VEHICULAR BRIDGE, BUS SHELTERS AND LINKWAYS AT HOUGANG TOWN
MASTER CONSTRUCTION PROGRAMME
ID Task Name Duration Early Start Early Finish Late Start Late Finish Total 022 2023
Float Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
997 [Z5BKD] Covered Drain 1100mm (BKD Westbound/CH0+896 ‐  28 days Tue 5/9/23 Fri 6/10/23 Sat 14/10/23 Wed 15/11/23 34 days
CH0+982)
998 Drain base, wall and top slab 28 days Tue 5/9/23 Fri 6/10/23 Sat 14/10/23 Wed 15/11/23 34 days
999 [Z5BKD] Covered Drain 2.5m wide (BKD Eastbound/CH0+872 ‐  20 days Tue 28/2/23 Wed 22/3/23 Fri 24/3/23 Sat 15/4/23 21 days
CH0+924)
1000 Drain base, wall and top slab 20 days Tue 28/2/23 Wed 22/3/23 Fri 24/3/23 Sat 15/4/23 21 days
1001 [Z5BKD] Bus Shelter 62 days Wed 29/11/23 Thu 8/2/24 Tue 19/12/23 Thu 25/4/24 17 days
1002 [Z5BKD] Bus Shelter No.5 62 days Wed 29/11/23 Thu 8/2/24 Wed 14/2/24 Thu 25/4/24 66 days
1003 Structure 61 days Wed 29/11/23 Wed 7/2/24 Wed 14/2/24 Wed 24/4/24 66 days
1004 Underground utility service 10 days Wed 29/11/23 Sat 9/12/23 Wed 14/2/24 Sat 24/2/24 66 days
1005 Bus Shelter Footing 15 days Mon 11/12/23 Wed 27/12/23 Mon 26/2/24 Wed 13/3/24 66 days
1006 RHS column and roof  21 days Thu 28/12/23 Sat 20/1/24 Thu 14/3/24 Sat 6/4/24 66 days
1007 Safety bollards, bench and information panel  15 days Mon 22/1/24 Wed 7/2/24 Mon 8/4/24 Wed 24/4/24 66 days
1008 Bus stop pole and refuse bin  15 days Mon 22/1/24 Wed 7/2/24 Mon 8/4/24 Wed 24/4/24 66 days
1009 M&E  15 days Mon 22/1/24 Wed 7/2/24 Mon 8/4/24 Wed 24/4/24 66 days
1010 OG box and light fitting 15 days Mon 22/1/24 Wed 7/2/24 Mon 8/4/24 Wed 24/4/24 66 days
1011 Lightning protection system 15 days Mon 22/1/24 Wed 7/2/24 Mon 8/4/24 Wed 24/4/24 66 days
1012 Completion of Bus Shelter No.5 1 day Thu 8/2/24 Thu 8/2/24 Thu 25/4/24 Thu 25/4/24 66 days
1013 [Z5BKD] Bus Shelter No.4 47 days Wed 29/11/23 Mon 22/1/24 Tue 19/12/23 Sat 10/2/24 17 days
1014 Structure 46 days Wed 29/11/23 Sat 20/1/24 Tue 19/12/23 Fri 9/2/24 17 days
1015 Underground utility service 10 days Wed 29/11/23 Sat 9/12/23 Tue 19/12/23 Fri 29/12/23 17 days
1016 Bus Shelter Footing 12 days Mon 11/12/23 Sat 23/12/23 Sat 30/12/23 Fri 12/1/24 17 days
1017 RHS column and roof  14 days Mon 25/12/23 Tue 9/1/24 Sat 13/1/24 Mon 29/1/24 17 days
1018 Safety bollards, bench and information panel  10 days Wed 10/1/24 Sat 20/1/24 Tue 30/1/24 Fri 9/2/24 17 days
1019 Bus stop pole and refuse bin  10 days Wed 10/1/24 Sat 20/1/24 Tue 30/1/24 Fri 9/2/24 17 days
1020 M&E  11 days Wed 10/1/24 Mon 22/1/24 Tue 30/1/24 Sat 10/2/24 17 days
1021 OG box and light fitting 10 days Wed 10/1/24 Sat 20/1/24 Tue 30/1/24 Fri 9/2/24 17 days
1022 Lighning protection system 10 days Wed 10/1/24 Sat 20/1/24 Tue 30/1/24 Fri 9/2/24 17 days
1023 Completion of Bus Shelter No.4 1 day Mon 22/1/24 Mon 22/1/24 Sat 10/2/24 Sat 10/2/24 17 days
1024 [Z5BKD] Ramp 110 days Mon 28/8/23 Tue 2/1/24 Fri 6/10/23 Sat 10/2/24 34 days
1025 [Z5BKD] 4m wide maintenance ramp (BKD Eastbound/CH0+872 ‐  55 days Mon 28/8/23 Mon 30/10/23 Fri 6/10/23 Fri 8/12/23 34 days
CH1+005)
1026 [Z5BKD] 4m wide maintenance ramp (BKD Westbound/CH0+872  55 days Tue 31/10/23 Tue 2/1/24 Sat 9/12/23 Sat 10/2/24 34 days
‐ CH1+020)
1027 [Z5BKD] Road 74 days Fri 6/10/23 Sat 30/12/23 Thu 19/10/23 Fri 12/1/24 11 days
1028 [Z5BKD] BKD Eastbound/CH1+020 ‐ CH1+344 62 days Fri 6/10/23 Sat 16/12/23 Thu 19/10/23 Fri 29/12/23 11 days
1029 Underground utility service 10 days Fri 6/10/23 Tue 17/10/23 Thu 19/10/23 Mon 30/10/23 11 days
1030 Subgrade and sub‐base 16 days Wed 18/10/23 Sat 4/11/23 Tue 31/10/23 Fri 17/11/23 11 days
1031 Kerb, drop‐inlet chamber and scupper pipe 20 days Mon 6/11/23 Tue 28/11/23 Sat 18/11/23 Mon 11/12/23 11 days
1032 Base course and pavement 16 days Wed 29/11/23 Sat 16/12/23 Tue 12/12/23 Fri 29/12/23 11 days
1033 [Z5BKD] BKD Westbound/CH1+020 ‐ CH1+344 62 days Fri 6/10/23 Sat 16/12/23 Thu 26/10/23 Fri 12/1/24 17 days
1034 Underground utility service 10 days Fri 6/10/23 Tue 17/10/23 Thu 26/10/23 Mon 6/11/23 17 days
1035 Subgrade and sub‐base 16 days Wed 18/10/23 Sat 4/11/23 Tue 7/11/23 Fri 24/11/23 17 days
1036 Kerb, drop‐inlet chamber and scupper pipe 20 days Mon 6/11/23 Tue 28/11/23 Sat 25/11/23 Mon 18/12/23 17 days
1037 Base course and pavement 16 days Wed 29/11/23 Sat 16/12/23 Tue 26/12/23 Fri 12/1/24 23 days
1038 [Z5BKD] BKD Eastbound/CH0+833 ‐ CH1+020 60 days Mon 23/10/23 Sat 30/12/23 Thu 16/11/23 Fri 12/1/24 11 days
1039 Underground utility service 10 days Mon 23/10/23 Thu 2/11/23 Thu 16/11/23 Mon 27/11/23 21 days
1040 Subgrade and sub‐base 12 days Mon 6/11/23 Sat 18/11/23 Tue 28/11/23 Mon 11/12/23 19 days
1041 Kerb, drop‐inlet chamber and scupper pipe 16 days Wed 29/11/23 Sat 16/12/23 Tue 12/12/23 Fri 29/12/23 11 days
1042 Base course and pavement 12 days Mon 18/12/23 Sat 30/12/23 Sat 30/12/23 Fri 12/1/24 11 days
1043 [Z5BKD] BKD Westbound/CH0+833 ‐ CH1+020 50 days Mon 23/10/23 Tue 19/12/23 Thu 16/11/23 Fri 12/1/24 21 days
1044 Underground utility service 10 days Mon 23/10/23 Thu 2/11/23 Thu 16/11/23 Mon 27/11/23 21 days
1045 Subgrade and sub‐base 12 days Fri 3/11/23 Thu 16/11/23 Tue 28/11/23 Mon 11/12/23 21 days
1046 Kerb, drop‐inlet chamber and scupper pipe 16 days Fri 17/11/23 Tue 5/12/23 Tue 12/12/23 Fri 29/12/23 21 days
1047 Base course and pavement 12 days Wed 6/12/23 Tue 19/12/23 Sat 30/12/23 Fri 12/1/24 21 days
1048 [Z5BKD] Ancillary work 25 days Mon 1/1/24 Mon 29/1/24 Sat 13/1/24 Sat 10/2/24 11 days
1049 Tree planting & turfing 25 days Mon 1/1/24 Mon 29/1/24 Sat 13/1/24 Sat 10/2/24 11 days
1050 Railing 25 days Mon 1/1/24 Mon 29/1/24 Sat 13/1/24 Sat 10/2/24 11 days
1051 Lamp post 25 days Mon 1/1/24 Mon 29/1/24 Sat 13/1/24 Sat 10/2/24 11 days
1052 [Z5] Completion of Zone 5 0 days Sat 10/2/24 Sat 10/2/24 Sat 10/2/24 Sat 10/2/24 1 day 10/2
1053 Completion of all physical works (2 months before Project Completion) 0 days Sat 24/2/24 Sat 24/2/24 Sat 24/2/24 Sat 24/2/24 0 days 24/2
1054 Road & Bridge Opening/Handover (2 months) 52 days Mon 26/2/24 Thu 25/4/24 Mon 26/2/24 Thu 25/4/24 0 days
1055 Project Completion 0 days Thu 25/4/24 Thu 25/4/24 Thu 25/4/24 Thu 25/4/24 0 days 25/4

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Date: Thu 27/10/22 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 17