ID Task Task Name Duration Start Finish Predecessors 2023 2024

Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 Construction of Ambur Elevated 482 days 20 Jan '23 31 Mar '24
Corridor & approaches and other
works from Km.66+600 to
Km.71+450 for Krishnagiri
Walajahpet Tollway private
Limited,of NH-46
2 Bill No.1: Site Clearance & 375 days 20 Jan '23 27 Dec '23
Dismantling
3 C&G 110 days 20 Jan '23 29 Apr '23
4 Dismantling - a) 375 days 20 Jan '23 27 Dec '23 3SS
Kerb/Channel Kerb including
foundation
5 Dismantling - b) 60 days 01 Nov '23 27 Dec '23 4FF
Kilometre/5th Km Stone
including foundation
concrete if any.
6 Dismantling - c) 60 days 01 Nov '23 27 Dec '23 4FF
Hect./Boundary stone
including foundation
concrete if any.
7 Dismantling - p) Longitudinal 175 days 20 Jan '23 27 Jun '23 3SS
drain removal including PCC
&RCC
8 Dismantling - r) Sign 90 days 05 Oct '23 27 Dec '23 4FF
boards/bill boards
9 Removal of PGR 210 days 20 Jan '23 28 Jul '23 3SS
10 Bill No.2 : Earth Work 460 days 20 Jan '23 11 Mar '24
11 Excavation 320 days 20 Jan '23 05 Nov '23 3SS
12 Embankment 330 days 20 Jan '23 17 Nov '23 11SS
13 Subgrade 340 days 20 Jan '23 26 Nov '23 12SS
14 Median/Island filling 120 days 26 Nov '23 11 Mar '24 13
15 Bill No.3: Granular Base Course 415 days 20 Jan '23 31 Jan '24
and Subbase
16 GSB 410 days 20 Jan '23 27 Jan '24 13SS
17 WMM 415 days 20 Jan '23 31 Jan '24 13SS
18 Bill No.4: Bituminous Corse 479 days 20 Jan '23 28 Mar '24
19 Prime coat 460 days 20 Jan '23 11 Mar '24 17SS
20 Tack coat 460 days 20 Jan '23 11 Mar '24 19SS
21 DBM VG40 475 days 20 Jan '23 25 Mar '24 20SS
22 BC VG40 475 days 20 Jan '23 25 Mar '24 21SS
23 BC VG30 180 days 17 Oct '23 28 Mar '24 21FF+4 days
24 DBM VG30 350 days 14 May '23 25 Mar '24 21FF
25 Bill No.5: Drain & RE Wall - DRAIN
140 days 20 Jan '23 27 May '23
26 Excavation 125 days 20 Jan '23 14 May '23 16SS
27 RCC M25 140 days 20 Jan '23 27 May '23 26SS
28 Reinforcement 140 days 20 Jan '23 27 May '23 27SS
29 PCC M15 125 days 20 Jan '23 14 May '23 28SS
30 Bill No.5: Drain & RE Wall - RE Wall
310 days 20 Jan '23 27 Oct '23
31 RE wall area 300 days 20 Jan '23 18 Oct '23 27SS
32 Selected Fill in RE wall 310 days 20 Jan '23 27 Oct '23 31SS
33 Filter Media behind RE wall 300 days 20 Jan '23 18 Oct '23 32SS

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
34 Excavation 285 days 20 Jan '23 05 Oct '23 33SS
35 Bill No. 6 : Traffic Signs, 405 days 24 Mar '23 25 Mar '24
Marking and Road
36 Kerb with service road in the 390 days 24 Mar '23 11 Mar '24 31SS+70 days
separator along service road
(0.091 cum for running
meter)
37 Kerb with service road next 390 days 24 Mar '23 11 Mar '24 36SS
to the footpath (0.05 cum for
running meter)
38 Construction of plain cement 390 days 24 Mar '23 11 Mar '24 37SS
concrete kerb M-20 grade-I
section (unit Qty: Concrete
M20 - 0.034 cum/Lm)-Kerb
with Service road
39 Construction of plain cement 390 days 24 Mar '23 11 Mar '24 37SS
concrete kerb M-20 grade-I
section (unit Qty: Concrete
M20 - 0.042 cum/Lm)- Kerb
at seperator towards Main
Carriageway outer edge
40 Providing and laying 390 days 24 Mar '23 11 Mar '24 39SS
foundation (0.215 wide X 0.1
thickness) for Kerb in cement
concrete M15 grade as per
drawing and technical
specification clause 408.
41 Paver Block of 60mm thick 90 days 05 Jan '24 25 Mar '24 40FF+15 days
42 GSB 90 days 05 Jan '24 25 Mar '24 41FF
43 Sand bed for paver blocks 90 days 05 Jan '24 25 Mar '24 42FF
44 Separater Filling b/w MCW & 120 days 09 Dec '23 25 Mar '24 43FF
SR using EMB material
45 PCC M20 at separator b/w 210 days 15 Sep '23 25 Mar '24 44FF
MCW & SR
46 Providing RC Crash barrier 210 days 15 Sep '23 25 Mar '24 45FF
and all accessories as per
specifications (M40)
47 Land scaping below viaduct 60 days 31 Jan '24 25 Mar '24 46FF
48 Delineators including stickers 120 days 09 Dec '23 25 Mar '24 47FF
provided at the place of
WBCB in the edge of the
49 Providing and fixing New 180 days 14 Oct '23 25 Mar '24 48FF
Jersy Crash Barrier (NJCB) as
per drawing and Technical
Specification. (excl. Elevated
Corridor)
50 PCC fill on sides of Jercy 180 days 14 Oct '23 25 Mar '24 48FF
crash barrier
51 Bill No. 8 : Intersection 227 days 02 Sep '23 26 Mar '24
52 Clearing and grubbing 180 days 02 Sep '23 14 Feb '24 50FF-45 days
53 Exc. in Ordinary soil 180 days 08 Sep '23 20 Feb '24 52FF+7 days
54 Embankments 180 days 14 Sep '23 26 Feb '24 53FF+7 days
55 Subgrade 180 days 14 Sep '23 26 Feb '24 54FF
Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
56 Earthen shoulders in 180 days 14 Sep '23 26 Feb '24 55FF
Embankment
57 Granular Sub-base 180 days 21 Sep '23 03 Mar '24 56FF+7 days
58 Wet Mix Macadam 180 days 28 Sep '23 10 Mar '24 57FF+7 days
59 Primer coat over granular 180 days 29 Sep '23 11 Mar '24 58FF+2 days
surface with bitumen
emulsion.
60 (i) On granular surface 180 days 29 Sep '23 11 Mar '24 59FF
treated with primer.
61 Dense Bituminous Macadam 180 days 03 Oct '23 14 Mar '24 60FF+3 days
62 Bituminous Concrete 180 days 09 Oct '23 20 Mar '24 61FF+7 days
63 Painting concrete Kerb 30 days 29 Feb '24 26 Mar '24 62FF+7 days
complete with ordinary paint

64 a) I - Kerb. (unit Qty: 180 days 28 Sep '23 10 Mar '24 58FF
Concrete M20 - 0.067
cum/Lm)
65 a)Pavement bituminous 180 days 28 Sep '23 10 Mar '24 64FF
course
66 b)Non bituminous 180 days 28 Sep '23 10 Mar '24 65FF
67 Bill No.1: Box Culvert widening 80 days 16 Feb '23 29 Apr '23
From Km 66.600 to 68.000 &
Km 69.480 to71.450 (Km
68 Excavation 4 days 16 Feb '23 20 Feb '23 31SS+30 days
69 PCC M15 2 days 20 Feb '23 21 Feb '23 68
70 Foundation (ii) M 30 Grade 7 days 22 Feb '23 28 Feb '23 69
71 Box cell structures (ii) M 35 28 days 28 Feb '23 25 Mar '23 70
Grade
72 Reinforcement 35 days 22 Feb '23 25 Mar '23 69
73 RCC M35 in Parapet wall 14 days 25 Mar '23 06 Apr '23 72
74 Weep holes 100 mm dia PVC pipes35 days 22 Feb '23 25 Mar '23 72SS
75 Filter media 7 days 06 Apr '23 12 Apr '23 73
76 53mm thick layer of mastic 2 days 06 Apr '23 08 Apr '23 73
asphalt over deck slab.
77 Dry Boulder (Flexible) apron 10 days 12 Apr '23 22 Apr '23 75
78 Rigid apron 10 days 12 Apr '23 22 Apr '23 77SS
79 PCC M-15 2 days 12 Apr '23 15 Apr '23 77SS
80 Filter media beneath the 7 days 12 Apr '23 19 Apr '23 77SS
stone pitching
81 Providing and laying stone 7 days 20 Apr '23 26 Apr '23 80
pitching on Embankment
slopes.
82 Earth fill below filter media 2 days 06 Apr '23 08 Apr '23 75SS
83 Mastic pad Mastic pad b/w 2 days 06 Apr '23 08 Apr '23 73
retaining wall&side wall
84 Painting of parapet wall 4 days 26 Apr '23 29 Apr '23 81
85 Dismantling of Top slab for 2 days 16 Feb '23 18 Feb '23 68SS
widening
86 Reinforcement Steel 2 days 16 Feb '23 18 Feb '23 68SS

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
87 Bill No.1: Box Culvert widening 80 days 30 Apr '23 11 Jul '23
From Km 66.600 to 68.000 &
Km 69.480 to71.450 (Km
88 Excavation 4 days 30 Apr '23 05 May '23 84FS+1 day
89 PCC M15 2 days 05 May '23 06 May '23 88
90 Foundation (ii) M 30 Grade 7 days 07 May '23 13 May '23 89
91 Box cell structures (ii) M 35 28 days 13 May '23 07 Jun '23 90
Grade
92 Reinforcement 35 days 07 May '23 07 Jun '23 89
93 RCC M35 in Parapet wall 14 days 07 Jun '23 19 Jun '23 92
94 Weep holes 100 mm dia PVC pipes35 days 07 May '23 07 Jun '23 92SS
95 Filter media 7 days 19 Jun '23 25 Jun '23 93
96 53mm thick layer of mastic 2 days 19 Jun '23 21 Jun '23 93
asphalt over deck slab.
97 Dry Boulder (Flexible) apron 10 days 25 Jun '23 04 Jul '23 95
98 Rigid apron 10 days 25 Jun '23 04 Jul '23 97SS
99 PCC M-15 2 days 25 Jun '23 27 Jun '23 97SS
100 Filter media beneath the 7 days 25 Jun '23 01 Jul '23 97SS
stone pitching
101 Providing and laying stone 7 days 02 Jul '23 08 Jul '23 100
pitching on Embankment
slopes.
102 Earth fill below filter media 2 days 19 Jun '23 21 Jun '23 95SS
103 Mastic pad Mastic pad b/w 2 days 19 Jun '23 21 Jun '23 93
retaining wall&side wall
104 Painting of parapet wall 4 days 08 Jul '23 11 Jul '23 101
105 Dismantling of Top slab for 2 days 30 Apr '23 03 May '23 88SS
widening
106 Reinforcement Steel 2 days 30 Apr '23 03 May '23 88SS
107 Bill No.2: Constructin of Pipe 124 days 20 Jan '23 13 May '23
Culvert From Km 66.600 to
68.000 & Km 69.480 to71.450
108 M20 in head walls 14 days 06 Apr '23 19 Apr '23 73
109 Foundation - (i) M 20 Grade 14 days 06 Apr '23 19 Apr '23 108SS
110 Reinforcement Steel 14 days 06 Apr '23 19 Apr '23 109SS
111 Providing & Painting of 1 day 20 Jan '23 20 Jan '23
structure no., span
arrangement and flow
directions.
112 Dry Boulder apron 7 days 20 Apr '23 26 Apr '23 110
113 Granular filter media 7 days 20 Apr '23 26 Apr '23 112SS
beneath the stone pitching
114 Stone pitching on 7 days 26 Apr '23 03 May '23 113
Embankment slopes
115 Earth fill below filter media 14 days 26 Apr '23 09 May '23 114SS
at quadrant
pitching/Revetment
116 PCC M15 2 days 09 May '23 11 May '23 115
117 RCC M30 in median chamber 2 days 11 May '23 13 May '23 116

118 Reinforcement Steel 2 days 11 May '23 13 May '23 117SS

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
119 Bill No. 3 : Construction of PUP 106 days 20 Jan '23 26 Apr '23
at Km 71.120
120 Mastic Pad 1 day 15 Mar '23 16 Mar '23 68SS+30 days
121 Tar paper bearings 1 day 15 Mar '23 16 Mar '23 120SS
122 20mm thick premoulded 1 day 16 Mar '23 17 Mar '23 121
asphalt filler
123 Strip seal 1 day 17 Mar '23 17 Mar '23 122
124 a. Drainage Spout including 3 days 18 Mar '23 20 Mar '23 123
125 b. Runner pipe 150 PVC 2 days 20 Mar '23 22 Mar '23 124
126 Approach Slab - PCC M15 2 days 22 Mar '23 24 Mar '23 125
127 Approach Slab - RCC M35 7 days 24 Mar '23 30 Mar '23 126
128 Approach Slab - Reinf. 7 days 24 Mar '23 30 Mar '23 127SS
129 (a) Crash barrier RCC M40 14 days 30 Mar '23 11 Apr '23 128
130 Crash barrier Reinf. 14 days 30 Mar '23 11 Apr '23 129SS
131 Painting of crash barrier 4 days 11 Apr '23 16 Apr '23 130
132 50mm thick bituminous 1 day 30 Mar '23 31 Mar '23 128
concrete over the Deck
133 50mm thick bituminous 1 day 31 Mar '23 01 Apr '23 132
concrete inside the box
structure
134 Painting structure no., span 1 day 01 Apr '23 02 Apr '23 133
arrangement
135 RE Wall 106 days 20 Jan '23 26 Apr '23
136 Back filling in RE wall 40 days 20 Jan '23 25 Feb '23 3SS
137 RCC M20 in coping beam 21 days 09 Feb '23 28 Feb '23 136FF+3 days
138 Coping beam Reinf. 21 days 09 Feb '23 28 Feb '23 137SS
139 PCC M15 in friction slab 30 days 28 Feb '23 26 Mar '23 138
with crash barrier
140 RCC M40 in precast crash 45 days 25 Feb '23 06 Apr '23 136
barrier
141 RCC M40 in friction slab 45 days 10 Mar '23 19 Apr '23 140SS+14 days
142 Friction slab with crash 45 days 10 Mar '23 19 Apr '23 141SS
barrier Reinf.
143 150mm dia PVC 30 days 20 Jan '23 16 Feb '23 136SS
Perforated pipe
144 100 dia PVC inside crash 45 days 10 Mar '23 19 Apr '23 141SS
barrier.
145 Painting of crash barrier 7 days 20 Apr '23 26 Apr '23 144
146 Neoprene joint 21 days 09 Feb '23 28 Feb '23 138SS
metal/Mastic pad around
coping beam
147 Filter media behind RE 40 days 20 Jan '23 25 Feb '23 136SS
wall
148 Bill No. 4 : Construction of 83 days 08 Feb '23 24 Apr '23
New Box Culvert @ Km 68.226
149 Service Road BHS 51 days 08 Feb '23 25 Mar '23
168 Main Carriageway 32 days 26 Mar '23 24 Apr '23
175 Bill No. 5 : Construction of 123 days 28 Jul '23 19 Nov '23
Flyover @ Km 68.308

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 5
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
176 Expansion Joint - (I) Providing 7 days 27 Oct '23 02 Nov '23 32
20mm thick asphalt filler at
the junctions of crash barrier

177 PCC M15 in approach slabs 2 days 02 Nov '23 04 Nov '23 176
178 RCC M30 in approach slabs 7 days 04 Nov '23 10 Nov '23 177
179 Reinforcement Steel in 7 days 04 Nov '23 10 Nov '23 178SS
approach slabs.
180 Painting of crash barrier with 7 days 10 Nov '23 19 Nov '23 179
yellow & black strips
181 RE wall 122 days 28 Jul '23 19 Nov '23
182 Earthwork in excavation 30 days 28 Jul '23 24 Aug '23 31FS-90 days
183 Back filling in RE wall 45 days 28 Jul '23 06 Sep '23 182SS
foundations
184 PCC M15 in levelling pad 2 days 24 Aug '23 26 Aug '23 182
185 RCC M20 in coping beam 7 days 18 Oct '23 24 Oct '23 31
186 Reinforcement Steel for 7 days 18 Oct '23 24 Oct '23 185SS
coping beam
187 PCC M15 in friction slab 4 days 31 Oct '23 03 Nov '23 186FS+7 days
with crash barrier
188 RCC M40 in precast crash 14 days 03 Nov '23 19 Nov '23 187
barrier
189 RCC M40 in friction slab 14 days 03 Nov '23 19 Nov '23 187
190 Reinforcement Steel in 14 days 03 Nov '23 19 Nov '23 187
friction slab with crash
barrier.
191 Filter media behind RE 45 days 06 Sep '23 18 Oct '23 31FF
wall
192 150mm dia PVC 14 days 06 Oct '23 18 Oct '23 31FF
Perforated pipe wrapped
with Geotextile
193 Bill No. 7 : Construction of PUP 142 days 25 Feb '23 03 Jul '23
@ Km 69.290
194 Excavation - in Ordinary Soil 2 days 25 Feb '23 27 Feb '23 36SS-30 days
195 PCC M-15 in leveling course 1 day 27 Feb '23 28 Feb '23 194
196 Box Structure (i) Grade M 30 60 days 28 Feb '23 23 Apr '23 195
197 Reinforcement Steel 60 days 28 Feb '23 23 Apr '23 195
198 Filter media 30 days 23 Apr '23 21 May '23 197
199 a. Drainage Spout 7 days 21 May '23 27 May '23 198
200 b. Runner pipe 100 DIA PVC 1 day 21 May '23 22 May '23 199SS
201 PCC M15 in approach slabs 1 day 08 Jun '23 09 Jun '23 198FS+21 days
202 RCC M35 in Approach Slabs 1 day 18 Jun '23 19 Jun '23 203
203 Reinforcement Steel in 10 days 09 Jun '23 18 Jun '23 201
Approach slabs
204 50mm thick layer of mastic 1 day 01 Jul '23 01 Jul '23 202FF+14 days
asphalt over top slab after
applying tack coat.
205 50mm thick layer of mastic 1 day 02 Jul '23 02 Jul '23 204
asphalt inside box after
applying tack coat.

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 6
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
206 Painting structure no., span 1 day 02 Jul '23 03 Jul '23 205
arrangement and flow
directions.
207 Bill No. 8 : Construction of 482 days 20 Jan '23 31 Mar '24
Ambur Elevated Corridor From
km 68+330 to km 69+480
208 SEGMENT-02 (P3B, P4, P5 & P6A)111 days 20 Jan '23 30 Apr '23
209 Super Structure - Spine Beam23 days 20 Jan '23 10 Feb '23
210 Staging arrangement 5 days 20 Jan '23 24 Jan '23 11SS
211 Bottom Sheet Placing 4 days 24 Jan '23 28 Jan '23 210
212 Reinforcement Placing 11 days 29 Jan '23 07 Feb '23 211
213 Placement of Void Former 2 days 01 Feb '23 03 Feb '23 212SS+4 days
214 Sheathing duct 5 days 03 Feb '23 07 Feb '23 213
215 PMC & PIMA Inspection 1 day 07 Feb '23 08 Feb '23 214
216 IE Inspection 1 day 08 Feb '23 09 Feb '23 215
217 Concreting 1 day 09 Feb '23 10 Feb '23 216
218 Super Structure - 27 days 11 Feb '23 07 Mar '23
Cantilever Wing Slab-RHS
219 RHS - Levelling of Bed 3 days 11 Feb '23 13 Feb '23 217FS+1 day
220 RHS - Staging arrangement7 days 14 Feb '23 20 Feb '23 219
221 RHS - Wing beam form work 5 days 15 Feb '23 20 Feb '23 220FF
222 10 days
RHS - Reinforcement for Ribs 15 Feb '23 24 Feb '23 221SS
223 RHS - Wing slab form work11 days 16 Feb '23 26 Feb '23 222SS+1 day
224 13 days
RHS - Reinforcement for slab 18 Feb '23 01 Mar '23 223SS+2 days
225 RHS - Sheathing duct 3 days 02 Mar '23 04 Mar '23 224
226 RHS - PMC & PIMA Inspection1 day 04 Mar '23 05 Mar '23 225
227 RHS - IE Inspection 1 day 05 Mar '23 06 Mar '23 226
228 RHS - Concreting 1 day 06 Mar '23 07 Mar '23 227
229 Super Structure - 27 days 07 Mar '23 31 Mar '23
Cantilever Wing Slab-LHS
230 LHS - Levelling of Bed 4 days 07 Mar '23 10 Mar '23 228
231 LHS - Staging arrangement 8 days 10 Mar '23 17 Mar '23 230
232 LHS - Wing beam form work6 days 12 Mar '23 17 Mar '23 231SS+2 days
233 10 days
LHS - Reinforcement for Ribs 12 Mar '23 21 Mar '23 232SS
234 LHS - Wing slab form work11 days 13 Mar '23 23 Mar '23 233SS+1 day
235 LHS-Reinforcement for slab13 days 15 Mar '23 26 Mar '23 234SS+2 days
236 LHS - Sheathing duct 3 days 26 Mar '23 29 Mar '23 235
237 LHS - PMC & PIMA Inspection1 day 29 Mar '23 30 Mar '23 236
238 LHS - IE Inspection 1 day 30 Mar '23 31 Mar '23 237
239 Concreting 1 day 31 Mar '23 01 Apr '23 238
240 Pre Stressing 8 days 23 Apr '23 30 Apr '23 239FS+24 days
241 SEGMENT-03 (P6B, P7, P8 & P9A)111 days 23 Feb '23 04 Jun '23
242 Super Structure - Spine Beam28 days 23 Feb '23 20 Mar '23
243 Levelling of Bed 1 day 23 Feb '23 24 Feb '23 239SS-40 days
244 Staging arrangement 7 days 25 Feb '23 03 Mar '23 243SS+2 days
245 Bottom Sheet Placing 4 days 03 Mar '23 07 Mar '23 244
246 Reinforcement Placing 11 days 07 Mar '23 17 Mar '23 245
247 Placement of Void Former 2 days 11 Mar '23 13 Mar '23 246SS+5 days
248 Sheathing duct 6 days 12 Mar '23 17 Mar '23 247SS+1 day

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 7
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
249 PMC & PIMA Inspection 1 day 18 Mar '23 18 Mar '23 248
250 IE Inspection 1 day 18 Mar '23 19 Mar '23 249
251 Concreting 1 day 19 Mar '23 20 Mar '23 250
252 Super Structure - 27 days 21 Mar '23 15 Apr '23
Cantilever Wing Slab-RHS
253 RHS - Levelling of Bed 2 days 21 Mar '23 23 Mar '23 251FS+1 day
254 RHS - Staging arrangement8 days 23 Mar '23 30 Mar '23 253
255 6 days
RHS - Wing beam form work 25 Mar '23 30 Mar '23 254SS+2 days
256 11 days
RHS - Reinforcement for Ribs 25 Mar '23 03 Apr '23 255SS
257 RHS - Wing slab form work12 days 26 Mar '23 05 Apr '23 256SS+1 day
258 13 days
RHS - Reinforcement for slab 28 Mar '23 09 Apr '23 257SS+3 days
259 RHS - Sheathing duct 3 days 09 Apr '23 11 Apr '23 258
260 1 day
RHS - PMC & PIMA Inspection 11 Apr '23 12 Apr '23 259
261 RHS - IE Inspection 1 day 12 Apr '23 13 Apr '23 260
262 RHS - Concreting 1 day 13 Apr '23 15 Apr '23 261
263 Super Structure - 23 days 15 Apr '23 06 May '23
Cantilever Wing Slab-LHS
264 LHS - Levelling of Bed 2 days 15 Apr '23 17 Apr '23 262
265 LHS - Staging arrangement 8 days 17 Apr '23 24 Apr '23 264
266 LHS - Wing beam form work6 days 19 Apr '23 24 Apr '23 265SS+2 days
267 10 days
LHS - Reinforcement for Ribs 19 Apr '23 27 Apr '23 266SS
268 LHS - Wing slab form work11 days 20 Apr '23 29 Apr '23 267SS+1 day
269 LHS-Reinforcement for slab12 days 20 Apr '23 02 May '23 268SS+1 day
270 LHS - Sheathing duct 3 days 02 May '23 05 May '23 269
271 1 day
LHS - PMC & PIMA Inspection 05 May '23 06 May '23 270
272 LHS - IE Inspection 1 day 06 May '23 06 May '23 271
273 LHS - Concreting 1 day 07 May '23 07 May '23 272
274 Pre Stressing 8 days 28 May '23 04 Jun '23 272FS+24 days
275 SEGMENT-04 (P9B, P10, P11 190 days 20 Jan '23 10 Jul '23
& P12A)
276 Sub-Structure 22 days 20 Jan '23 09 Feb '23
277 P10 Pier Cap Reinforcement 4 days 20 Jan '23 23 Jan '23 3SS
278 P10 Pier Cap Shuttering 1 day 23 Jan '23 24 Jan '23 277
279 P10 Pier Cap Concreting 1 day 24 Jan '23 25 Jan '23 278
280 4 days
P11 Pier 3rd lift Reinforcement 25 Jan '23 29 Jan '23 279
281 P11 Pier 3rd lift Shuttering 3 days 29 Jan '23 01 Feb '23 280
282 P11 Pier 3rd lift Concreting 1 day 01 Feb '23 02 Feb '23 281
283 P12A Pier Cap Reinforcement 4 days 02 Feb '23 05 Feb '23 282
284 P12A Pier Cap Shuttering 3 days 06 Feb '23 08 Feb '23 283
285 P12A Pier Cap Concreting 1 day 08 Feb '23 09 Feb '23 284
286 Super Structure - Spine Beam29 days 30 Mar '23 26 Apr '23
287 Levelling of Bed 2 days 30 Mar '23 01 Apr '23 258SS+2 days
288 Staging arrangement 7 days 01 Apr '23 07 Apr '23 287
289 Bottom Sheet Placing 5 days 07 Apr '23 11 Apr '23 288
290 Reinforcement Placing 11 days 11 Apr '23 22 Apr '23 289
291 Placement of Void Former 3 days 16 Apr '23 19 Apr '23 290SS+4 days
292 Sheathing duct 6 days 18 Apr '23 23 Apr '23 291FS-1 day
293 PMC & PIMA Inspection 1 day 23 Apr '23 24 Apr '23 292

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 8
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
294 IE Inspection 1 day 24 Apr '23 25 Apr '23 293
295 Concreting 1 day 25 Apr '23 26 Apr '23 294
296 Super Structure - 27 days 26 Apr '23 21 May '23
Cantilever Wing Slab-RHS
297 RHS - Levelling of Bed 3 days 26 Apr '23 28 Apr '23 295
298 RHS - Staging arrangement8 days 28 Apr '23 06 May '23 297
299 6 days
RHS - Wing beam form work 30 Apr '23 06 May '23 298SS+2 days
300 10 days
RHS - Reinforcement for Ribs 30 Apr '23 10 May '23 299SS
301 RHS - Wing slab form work11 days 02 May '23 12 May '23 300SS+1 day
302 13 days
RHS - Reinforcement for slab 04 May '23 15 May '23 301SS+2 days
303 RHS - Sheathing duct 3 days 15 May '23 18 May '23 302
304 1 day
RHS - PMC & PIMA Inspection 18 May '23 19 May '23 303
305 RHS - IE Inspection 1 day 19 May '23 20 May '23 304
306 RHS - Concreting 1 day 20 May '23 21 May '23 305
307 Super Structure - 24 days 21 May '23 11 Jun '23
Cantilever Wing Slab-LHS
308 LHS - Levelling of Bed 3 days 21 May '23 23 May '23 306
309 LHS - Staging arrangement 8 days 23 May '23 30 May '23 308
310 LHS - Wing beam form work6 days 25 May '23 30 May '23 309SS+2 days
311 10 days
LHS - Reinforcement for Ribs 25 May '23 03 Jun '23 310SS
312 LHS - Wing slab form work11 days 26 May '23 05 Jun '23 311SS+1 day
313 LHS-Reinforcement for slab12 days 27 May '23 07 Jun '23 312SS+1 day
314 LHS - Sheathing duct 3 days 07 Jun '23 09 Jun '23 313
315 1 day
LHS - PMC & PIMA Inspection 09 Jun '23 10 Jun '23 314
316 LHS - IE Inspection 1 day 10 Jun '23 11 Jun '23 315
317 Concreting 1 day 11 Jun '23 12 Jun '23 316
318 Pre Stressing 8 days 03 Jul '23 10 Jul '23 317FS+24 days
319 SEGMENT-05 (P12B, P13, 214 days 02 Feb '23 13 Aug '23
P14 & P15A)
320 Sub structure 41 days 02 Feb '23 10 Mar '23
321 4 days
P12B Pier 3rd lift Reinforcement 02 Feb '23 05 Feb '23 3SS+14 days
322 P12B Pier 3rd lift Shuttering2 days 06 Feb '23 07 Feb '23 321
323 P12B Pier 3rd lift Concreting1 day 07 Feb '23 08 Feb '23 322
324 P12B Pier Cap Reinforcement 4 days 08 Feb '23 12 Feb '23 323
325 P12B Pier Cap Shuttering 2 days 12 Feb '23 13 Feb '23 324
326 P12B Pier Cap Concreting 1 day 14 Feb '23 14 Feb '23 325
327 4 days 02 Feb '23
P13 Pier 3rd lift Reinforcement 05 Feb '23 321SS
328 P13 Pier 3rd lift Shuttering 2 days 06 Feb '23 07 Feb '23 327
329 P13 Pier 3rd lift Concreting 1 day 07 Feb '23 08 Feb '23 328
330 P13 Pier Cap Reinforcement 4 days 08 Feb '23 12 Feb '23 329
331 P13 Pier Cap Shuttering 2 days 12 Feb '23 13 Feb '23 330
332 P13 Pier Cap Concreting 1 day 14 Feb '23 15 Feb '23 326
333 4 days 14 Feb '23
P14 Pier 2nd lift Reinforcement 17 Feb '23 331
334 P14 Pier 2nd lift Shuttering 2 days 17 Feb '23 19 Feb '23 333
335 P14 Pier 2nd lift Concreting 1 day 19 Feb '23 20 Feb '23 334
336 4 days 20 Feb '23
P14 Pier 3rd lift Reinforcement 23 Feb '23 335
337 P14 Pier 3rd lift Shuttering 2 days 23 Feb '23 25 Feb '23 336
338 P14 Pier 3rd lift Concreting 1 day 25 Feb '23 26 Feb '23 337

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 9
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
339 4 days
P14 Pier Cap Reinforcement 26 Feb '23 01 Mar '23 338
340 P14 Pier Cap Shuttering 2 days 02 Mar '23 03 Mar '23 339
341 P14 Pier Cap Concreting 1 day 03 Mar '23 04 Mar '23 340
342 P15A Pier 2nd lift 4 days 14 Feb '23 17 Feb '23 333SS
Reinforcement
343 P15A Pier 2nd lift Shuttering2 days 17 Feb '23 19 Feb '23 342
344 P15A Pier 2nd lift Concreting1 day 19 Feb '23 20 Feb '23 343
345 P15A Pier 3rd lift 4 days 20 Feb '23 23 Feb '23 344
Reinforcement
346 P15A Pier 3rd lift Shuttering2 days
23 Feb '23 25 Feb '23 345
347 P15A Pier 3rd lift Concreting1 day
25 Feb '23 26 Feb '23 346
348 P15A Pier Cap Reinforcement4 days 04 Mar '23 08 Mar '23 341
349 P15A Pier Cap Shuttering 2 days 08 Mar '23 09 Mar '23 348
350 P15A Pier Cap Concreting 1 day 10 Mar '23 10 Mar '23 349
351 Super Structure - Spine Beam27 days 07 May '23 30 May '23
352 Levelling of Bed 2 days 07 May '23 08 May '23 299
353 Staging arrangement 7 days 08 May '23 14 May '23 352
354 Bottom Sheet Placing 5 days 15 May '23 19 May '23 353
355 Reinforcement Placing 11 days 19 May '23 29 May '23 354
356 Placement of Void Former 3 days 22 May '23 24 May '23 355SS+3 days
357 Sheathing duct 6 days 23 May '23 28 May '23 356SS+1 day
358 PMC & PIMA Inspection 1 day 28 May '23 29 May '23 357
359 IE Inspection 1 day 29 May '23 30 May '23 358
360 Concreting 1 day 30 May '23 30 May '23 359
361 Super Structure - 27 days 31 May '23 23 Jun '23
Cantilever Wing Slab-RHS
362 RHS - Levelling of Bed 3 days 31 May '23 02 Jun '23 360
363 RHS - Staging arrangement8 days 02 Jun '23 09 Jun '23 362
364 RHS - Wing beam form work 6 days 04 Jun '23 09 Jun '23 363SS+2 days
365 10 days 04 Jun '23
RHS - Reinforcement for Ribs 13 Jun '23 364SS
366 RHS - Wing slab form work11 days 05 Jun '23 15 Jun '23 365SS+1 day
367 13 days 07 Jun '23
RHS - Reinforcement for slab 18 Jun '23 366SS+2 days
368 RHS - Sheathing duct 3 days 18 Jun '23 21 Jun '23 367
369 RHS - PMC & PIMA Inspection1 day 21 Jun '23 22 Jun '23 368
370 RHS - IE Inspection 1 day 22 Jun '23 23 Jun '23 369
371 RHS - Concreting 1 day 23 Jun '23 23 Jun '23 370
372 Super Structure - 24 days 24 Jun '23 15 Jul '23
Cantilever Wing Slab-LHS
373 LHS - Levelling of Bed 3 days 24 Jun '23 26 Jun '23 371
374 LHS - Staging arrangement 8 days 26 Jun '23 03 Jul '23 373
375 LHS - Wing beam form work6 days 28 Jun '23 03 Jul '23 374SS+2 days
376 10 days 28 Jun '23
LHS - Reinforcement for Ribs 07 Jul '23 375SS
377 LHS - Wing slab form work11 days 29 Jun '23 09 Jul '23 376SS+1 day
378 LHS-Reinforcement for slab12 days 30 Jun '23 10 Jul '23 377SS+1 day
379 LHS - Sheathing duct 3 days 10 Jul '23 13 Jul '23 378
380 LHS - PMC & PIMA Inspection1 day 13 Jul '23 14 Jul '23 379
381 LHS - IE Inspection 1 day 14 Jul '23 15 Jul '23 380
382 Concreting 1 day 15 Jul '23 16 Jul '23 381
383 Pre Stressing 8 days 06 Aug '23 13 Aug '23 382FS+24 days
Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 10
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
384 SEGMENT-06 (P15B, P16, 264 days 23 Jan '23 18 Sep '23
P17 & P18A)
385 Substructure (P15B) 21 days 26 Feb '23 17 Mar '23
386 4 days
P15B Pier 3rd lift Reinforcement 26 Feb '23 01 Mar '23 347
387 P15B Pier 3rd lift Shuttering2 days 02 Mar '23 03 Mar '23 386
388 P15B Pier 3rd lift Concreting1 day 03 Mar '23 04 Mar '23 387
389 P15B Pier Cap Reinforcement 4 days 10 Mar '23 14 Mar '23 350
390 P15B Pier Cap Shuttering 2 days 14 Mar '23 16 Mar '23 389
391 P15B Pier Cap Concreting 1 day 16 Mar '23 17 Mar '23 390
392 Substructure (P16) 28 days 04 Mar '23 29 Mar '23
393 4 days 04 Mar '23
P16 Pier 1st lift Reinforcement 08 Mar '23 388
394 P16 Pier 1st lift Shuttering 2 days 08 Mar '23 09 Mar '23 393
395 P16 Pier 1st lift Concreting 1 day 10 Mar '23 10 Mar '23 394
396 4 days 10 Mar '23
P16 Pier 2nd lift Reinforcement 14 Mar '23 395
397 P16 Pier 2nd lift Shuttering 2 days 14 Mar '23 16 Mar '23 396
398 P16 Pier 2nd lift Concreting 1 day 16 Mar '23 17 Mar '23 397
399 4 days 17 Mar '23
P16 Pier 3rd lift Reinforcement 20 Mar '23 398
400 P16 Pier 3rd lift Shuttering 2 days 20 Mar '23 22 Mar '23 399
401 P16 Pier 3rd lift Concreting 1 day 22 Mar '23 23 Mar '23 400
402 P16 Pier Cap Reinforcement 4 days 23 Mar '23 26 Mar '23 401
403 P16 Pier Cap Shuttering 2 days 26 Mar '23 28 Mar '23 402
404 P16 Pier Cap Concreting 1 day 28 Mar '23 29 Mar '23 403
405 Foundation (P17) 6 days 23 Jan '23 29 Jan '23
406 Footing Reinforcement 5 days 23 Jan '23 28 Jan '23 3SS+4 days
407 Footing Concreting 1 day 29 Jan '23 29 Jan '23 406
408 Substructure (P17) 28 days 04 Mar '23 29 Mar '23
409 4 days 04 Mar '23
P17 Pier 1st lift Reinforcement 08 Mar '23 393SS
410 P17 Pier 1st lift Shuttering 2 days 08 Mar '23 09 Mar '23 409
411 P17 Pier 1st lift Concreting 1 day 10 Mar '23 10 Mar '23 410
412 4 days 10 Mar '23
P17 Pier 2nd lift Reinforcement 14 Mar '23 411
413 P17 Pier 2nd lift Shuttering 2 days 14 Mar '23 16 Mar '23 412
414 P17 Pier 2nd lift Concreting 1 day 16 Mar '23 17 Mar '23 413
415 4 days 17 Mar '23
P17 Pier 3rd lift Reinforcement 20 Mar '23 414
416 P17 Pier 3rd lift Shuttering 2 days 20 Mar '23 22 Mar '23 415
417 P17 Pier 3rd lift Concreting 1 day 22 Mar '23 23 Mar '23 416
418 P17 Pier Cap Reinforcement 4 days 23 Mar '23 26 Mar '23 417
419 P17 Pier Cap Shuttering 2 days 26 Mar '23 28 Mar '23 418
420 P17 Pier Cap Concreting 1 day 28 Mar '23 29 Mar '23 419
421 Foundation (P18 A&B) 8 days 23 Jan '23 31 Jan '23
422 Exc. 2 days 23 Jan '23 25 Jan '23 3SS+4 days
423 PCC 1 day 25 Jan '23 27 Jan '23 422
424 Footing Reinforcement 4 days 27 Jan '23 30 Jan '23 423
425 Footing Concreting 1 day 30 Jan '23 31 Jan '23 424
426 Substructure (P18A) 28 days 23 Mar '23 18 Apr '23
427 P18A Pier 1st lift 4 days 23 Mar '23 26 Mar '23 401
Reinforcement
428 P18A Pier 1st lift Shuttering 2 days 26 Mar '23 28 Mar '23 427
429 P18A Pier 1st lift Concreting1 day 28 Mar '23 29 Mar '23 428

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 11
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
430 P18A Pier 2nd lift 4 days 29 Mar '23 02 Apr '23 429
Reinforcement
431 P18A Pier 2nd lift Shuttering2 days 02 Apr '23 03 Apr '23 430
432 P18A Pier 2nd lift Concreting1 day 03 Apr '23 04 Apr '23 431
433 P18A Pier 3rd lift 4 days 04 Apr '23 08 Apr '23 432
Reinforcement
434 P18A Pier 3rd lift Shuttering2 days
08 Apr '23 10 Apr '23 433
435 P18A Pier 3rd lift Concreting1 day
10 Apr '23 10 Apr '23 434
436 P18A Pier Cap Reinforcement4 days 11 Apr '23 15 Apr '23 435
437 P18A Pier Cap Shuttering 2 days 15 Apr '23 17 Apr '23 436
438 P18A Pier Cap Concreting 1 day 17 Apr '23 18 Apr '23 437
439 Super Structure - Spine Beam29 days 09 Jun '23 05 Jul '23
440 Levelling of Bed 2 days 09 Jun '23 11 Jun '23 3SS+155 days
441 Staging arrangement 7 days 11 Jun '23 17 Jun '23 440
442 Bottom Sheet Placing 5 days 17 Jun '23 22 Jun '23 441
443 Reinforcement Placing 11 days 22 Jun '23 01 Jul '23 442
444 Placement of Void Former 3 days 25 Jun '23 28 Jun '23 443SS+4 days
445 Sheathing duct 6 days 27 Jun '23 02 Jul '23 444FS-1 day
446 PMC & PIMA Inspection 1 day 02 Jul '23 03 Jul '23 445
447 IE Inspection 1 day 03 Jul '23 04 Jul '23 446
448 Concreting 1 day 04 Jul '23 05 Jul '23 447
449 Super Structure - 28 days 05 Jul '23 30 Jul '23
Cantilever Wing Slab-RHS
450 RHS - Levelling of Bed 3 days 05 Jul '23 08 Jul '23 448
451 RHS - Staging arrangement8 days 08 Jul '23 15 Jul '23 450
452 RHS - Wing beam form work 6 days 10 Jul '23 15 Jul '23 451SS+2 days
453 10 days 10 Jul '23
RHS - Reinforcement for Ribs 18 Jul '23 452SS
454 RHS - Wing slab form work11 days 11 Jul '23 21 Jul '23 453SS+2 days
455 13 days 13 Jul '23
RHS - Reinforcement for slab 25 Jul '23 454SS+2 days
456 RHS - Sheathing duct 3 days 25 Jul '23 27 Jul '23 455
457 RHS - PMC & PIMA Inspection1 day 27 Jul '23 28 Jul '23 456
458 RHS - IE Inspection 1 day 28 Jul '23 29 Jul '23 457
459 RHS - Concreting 1 day 29 Jul '23 30 Jul '23 458
460 Super Structure - 23 days 30 Jul '23 19 Aug '23
Cantilever Wing Slab-LHS
461 LHS - Levelling of Bed 3 days 30 Jul '23 02 Aug '23 459
462 LHS - Staging arrangement 8 days 01 Aug '23 08 Aug '23 461SS+2 days
463 LHS - Wing beam form work6 days 03 Aug '23 08 Aug '23 462SS+2 days
464 10 days 03 Aug '23
LHS - Reinforcement for Ribs 11 Aug '23 463SS
465 LHS - Wing slab form work11 days 03 Aug '23 13 Aug '23 464SS+1 day
466 LHS-Reinforcement for slab12 days 04 Aug '23 15 Aug '23 465SS+1 day
467 LHS - Sheathing duct 3 days 15 Aug '23 18 Aug '23 466
468 LHS - PMC & PIMA Inspection1 day 18 Aug '23 18 Aug '23 467
469 LHS - IE Inspection 1 day 19 Aug '23 19 Aug '23 468
470 LHS - Concreting 1 day 19 Aug '23 20 Aug '23 469
471 Pre Stressing 8 days 11 Sep '23 18 Sep '23 470FS+24 days
472 SEGMENT-10 (A2, P29, P28 & P27B)
278 days 19 Feb '23 28 Oct '23
473 Foundation (A2) 10 days 19 Feb '23 28 Feb '23
474 Exc. 3 days 19 Feb '23 21 Feb '23 425FS+21 days
Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 12
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
475 PCC 1 day 22 Feb '23 22 Feb '23 474
476 Footing Reinforcement 5 days 22 Feb '23 27 Feb '23 475
477 Footing Concreting 1 day 27 Feb '23 28 Feb '23 476
478 Substructure 28 days 11 Apr '23 07 May '23
479 A2 Pier 1st lift Reinforcement4 days 11 Apr '23 15 Apr '23 435
480 A2 Pier 1st lift Shuttering 2 days 15 Apr '23 17 Apr '23 479
481 A2 Pier 1st lift Concreting 1 day 17 Apr '23 18 Apr '23 480
482 A2 Pier 2nd lift Reinforcement4 days 18 Apr '23 21 Apr '23 481
483 A2 Pier 2nd lift Shuttering 2 days 21 Apr '23 23 Apr '23 482
484 A2 Pier 2nd lift Concreting 1 day 23 Apr '23 24 Apr '23 483
485 A2 Pier 3rd lift Reinforcement4 days 24 Apr '23 27 Apr '23 484
486 A2 Pier 3rd lift Shuttering 2 days 28 Apr '23 29 Apr '23 485
487 A2 Pier 3rd lift Concreting 1 day 29 Apr '23 30 Apr '23 486
488 A2 Pier Cap Reinforcement 4 days 30 Apr '23 05 May '23 487
489 A2 Pier Cap Shuttering 2 days 05 May '23 06 May '23 488
490 A2 Pier Cap Concreting 1 day 07 May '23 07 May '23 489
491 Foundation (P29) 10 days 28 Feb '23 09 Mar '23
492 P29 Exc. 3 days 28 Feb '23 02 Mar '23 477
493 P29 PCC 1 day 02 Mar '23 03 Mar '23 492
494 P29 Footing Reinforcement 5 days 03 Mar '23 08 Mar '23 493
495 P29 Footing Concreting 1 day 08 Mar '23 09 Mar '23 494
496 Substructure 35 days 11 Apr '23 14 May '23
497 4 days
P29 Pier 1st lift Reinforcement 11 Apr '23 15 Apr '23 479SS
498 P29 Pier 1st lift Shuttering 2 days 15 Apr '23 17 Apr '23 497
499 P29 Pier 1st lift Concreting 1 day 17 Apr '23 18 Apr '23 498
500 4 days
P29 Pier 2nd lift Reinforcement 18 Apr '23 21 Apr '23 499
501 P29 Pier 2nd lift Shuttering 2 days 21 Apr '23 23 Apr '23 500
502 P29 Pier 2nd lift Concreting 1 day 23 Apr '23 24 Apr '23 501
503 4 days
P29 Pier 3rd lift Reinforcement 24 Apr '23 27 Apr '23 502
504 P29 Pier 3rd lift Shuttering 2 days 28 Apr '23 29 Apr '23 503
505 P29 Pier 3rd lift Concreting 1 day 29 Apr '23 30 Apr '23 504
506 P29 Pier Cap Reinforcement 4 days 07 May '23 11 May '23 490
507 P29 Pier Cap Shuttering 2 days 11 May '23 13 May '23 506
508 P29 Pier Cap Concreting 1 day 13 May '23 14 May '23 507
509 Foundation (P28) 10 days 09 Mar '23 17 Mar '23
510 P28 Exc. 3 days 09 Mar '23 11 Mar '23 495
511 P28 PCC 1 day 11 Mar '23 12 Mar '23 510
512 P28 Footing Reinforcement 5 days 12 Mar '23 17 Mar '23 511
513 P28 Footing Concreting 1 day 17 Mar '23 17 Mar '23 512
514 Substructure (P28) 28 days 30 Apr '23 26 May '23
515 4 days
P28 Pier 1st lift Reinforcement 30 Apr '23 05 May '23 505
516 P28 Pier 1st lift Shuttering 2 days 05 May '23 06 May '23 515
517 P28 Pier 1st lift Concreting 1 day 07 May '23 07 May '23 516
518 4 days
P28 Pier 2nd lift Reinforcement 07 May '23 11 May '23 517
519 P28 Pier 2nd lift Shuttering 2 days 11 May '23 13 May '23 518
520 P28 Pier 2nd lift Concreting 1 day 13 May '23 14 May '23 519
521 4 days
P28 Pier 3rd lift Reinforcement 14 May '23 17 May '23 520
522 P28 Pier 3rd lift Shuttering 2 days 17 May '23 19 May '23 521

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 13
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
523 P28 Pier 3rd lift Concreting 1 day
19 May '23 20 May '23 522
524 P28 Pier Cap Reinforcement 4 days
20 May '23 23 May '23 508FS+7 days
525 P28 Pier Cap Shuttering 2 days 23 May '23 25 May '23 524
526 P28 Pier Cap Concreting 1 day 25 May '23 26 May '23 525
527 Foundation (P27B) 10 days 18 Mar '23 26 Mar '23
528 P27B Exc. 3 days 18 Mar '23 20 Mar '23 513
529 P27B PCC 1 day 20 Mar '23 21 Mar '23 528
530 5 days 21 Mar '23
P27B Footing Reinforcement 25 Mar '23 529
531 P27B Footing Concreting 1 day 26 Mar '23 26 Mar '23 530
532 Substructure (P27B) 35 days 30 Apr '23 01 Jun '23
533 P27B Pier 1st lift 4 days 30 Apr '23 05 May '23 515SS
Reinforcement
534 P27B Pier 1st lift Shuttering 2 days 05 May '23 06 May '23 533
535 P27B Pier 1st lift Concreting1 day 07 May '23 07 May '23 534
536 P27B Pier 2nd lift 4 days 07 May '23 11 May '23 535
Reinforcement
537 P27B Pier 2nd lift Shuttering2 days 11 May '23 13 May '23 536
538 P27B Pier 2nd lift Concreting1 day 13 May '23 14 May '23 537
539 P27B Pier 3rd lift 4 days 14 May '23 17 May '23 538
Reinforcement
540 P27B Pier 3rd lift Shuttering2 days
17 May '23 19 May '23 539
541 P27B Pier 3rd lift Concreting1 day
19 May '23 20 May '23 540
542 P27B Pier Cap Reinforcement4 days 26 May '23 30 May '23 526
543 P27B Pier Cap Shuttering 2 days 30 May '23 31 May '23 542
544 P27B Pier Cap Concreting 1 day 31 May '23 01 Jun '23 543
545 Super Structure - Spine Beam29 days 16 Jul '23 10 Aug '23
546 Levelling of Bed 2 days 16 Jul '23 17 Jul '23 544FS+50 days
547 Staging arrangement 7 days 18 Jul '23 24 Jul '23 546SS+2 days
548 Bottom Sheet Placing 5 days 24 Jul '23 28 Jul '23 547
549 Reinforcement Placing 11 days 28 Jul '23 07 Aug '23 548
550 Placement of Void Former 3 days 01 Aug '23 03 Aug '23 549SS+4 days
551 Sheathing duct 6 days 03 Aug '23 08 Aug '23 550FS-1 day
552 PMC & PIMA Inspection 1 day 08 Aug '23 09 Aug '23 551
553 IE Inspection 1 day 09 Aug '23 10 Aug '23 552
554 Concreting 1 day 10 Aug '23 10 Aug '23 553
555 Super Structure - 27 days 11 Aug '23 03 Sep '23
Cantilever Wing Slab-RHS
556 RHS - Levelling of Bed 3 days 11 Aug '23 13 Aug '23 554
557 RHS - Staging arrangement8 days 13 Aug '23 20 Aug '23 556
558 RHS - Wing beam form work 6 days 15 Aug '23 20 Aug '23 557SS+2 days
559 10 days 15 Aug '23
RHS - Reinforcement for Ribs 24 Aug '23 558SS
560 RHS - Wing slab form work11 days 16 Aug '23 26 Aug '23 559SS+1 day
561 13 days 18 Aug '23
RHS - Reinforcement for slab 29 Aug '23 560SS+2 days
562 RHS - Sheathing duct 3 days 29 Aug '23 01 Sep '23 561
563 RHS - PMC & PIMA Inspection1 day 01 Sep '23 02 Sep '23 562
564 RHS - IE Inspection 1 day 02 Sep '23 03 Sep '23 563
565 RHS - Concreting 1 day 03 Sep '23 03 Sep '23 564
566 Super Structure - 26 days 04 Sep '23 28 Sep '23
Cantilever Wing Slab-LHS

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 14
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
567 LHS - Levelling of Bed 3 days 04 Sep '23 06 Sep '23 565
568 LHS - Staging arrangement 8 days 06 Sep '23 13 Sep '23 567
569 LHS - Wing beam form work6 days 08 Sep '23 13 Sep '23 568SS+2 days
570 10 days
LHS - Reinforcement for Ribs 08 Sep '23 17 Sep '23 569SS
571 LHS - Wing slab form work11 days 09 Sep '23 20 Sep '23 570SS+1 day
572 LHS-Reinforcement for slab13 days 11 Sep '23 23 Sep '23 571SS+2 days
573 LHS - Sheathing duct 3 days 23 Sep '23 26 Sep '23 572
574 LHS - PMC & PIMA Inspection1 day 26 Sep '23 27 Sep '23 573
575 LHS - IE Inspection 1 day 27 Sep '23 28 Sep '23 574
576 LHS - Concreting 1 day 28 Sep '23 28 Sep '23 575
577 Pre Stressing 8 days 21 Oct '23 28 Oct '23 576FS+24 days
578 SEGMENT-09 (27A, P26, P25 277 days 26 Mar '23 05 Dec '23
& P24B)
579 Substructure (P27A) 27 days 20 May '23 13 Jun '23
580 P27A Pier 1st lift 4 days 20 May '23 23 May '23 541
Reinforcement
581 P27A Pier 1st lift Shuttering 2 days 23 May '23 25 May '23 580
582 P27A Pier 1st lift Concreting1 day 25 May '23 26 May '23 581
583 P27A Pier 2nd lift 4 days 26 May '23 30 May '23 582
Reinforcement
584 P27A Pier 2nd lift Shuttering2 days 30 May '23 31 May '23 583
585 P27A Pier 2nd lift Concreting1 day 31 May '23 01 Jun '23 584
586 P27A Pier 3rd lift 4 days 01 Jun '23 05 Jun '23 585
Reinforcement
587 P27A Pier 3rd lift Shuttering2 days
05 Jun '23 07 Jun '23 586
588 P27A Pier 3rd lift Concreting1 day07 Jun '23 07 Jun '23 587
589 P27A Pier Cap Reinforcement 4 days 07 Jun '23 10 Jun '23 543FS+7 days
590 P27A Pier Cap Shuttering 2 days 10 Jun '23 12 Jun '23 589
591 P27A Pier Cap Concreting 1 day 12 Jun '23 13 Jun '23 590
592 Foundation (P26) 10 days 26 Mar '23 04 Apr '23
593 P26 Exc. 3 days 26 Mar '23 29 Mar '23 531
594 P26 PCC 1 day 29 Mar '23 30 Mar '23 593
595 P26 Footing Reinforcement 5 days 30 Mar '23 03 Apr '23 594
596 P26 Footing Concreting 1 day 03 Apr '23 04 Apr '23 595
597 Substructure (P26) 34 days 20 May '23 19 Jun '23
598 4 days 20 May '23
P26 Pier 1st lift Reinforcement 23 May '23 580SS
599 P26 Pier 1st lift Shuttering 2 days 23 May '23 25 May '23 598
600 P26 Pier 1st lift Concreting 1 day 25 May '23 26 May '23 599
601 4 days 26 May '23
P26 Pier 2nd lift Reinforcement 30 May '23 600
602 P26 Pier 2nd lift Shuttering 2 days 30 May '23 31 May '23 601
603 P26 Pier 2nd lift Concreting 1 day 31 May '23 01 Jun '23 602
604 4 days 01 Jun '23
P26 Pier 3rd lift Reinforcement 05 Jun '23 603
605 P26 Pier 3rd lift Shuttering 2 days 05 Jun '23 07 Jun '23 604
606 P26 Pier 3rd lift Concreting 1 day 07 Jun '23 07 Jun '23 605
607 P26 Pier Cap Reinforcement 4 days 13 Jun '23 16 Jun '23 591
608 P26 Pier Cap Shuttering 2 days 16 Jun '23 18 Jun '23 607
609 P26 Pier Cap Concreting 1 day 18 Jun '23 19 Jun '23 608
610 Foundation (P25) 10 days 08 Apr '23 18 Apr '23
611 P25 Exc. 3 days 08 Apr '23 10 Apr '23 596FS+4 days
Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 15
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
612 P25 PCC 1 day 11 Apr '23 11 Apr '23 611
613 P25 Footing Reinforcement 5 days 11 Apr '23 17 Apr '23 612
614 P25 Footing Concreting 1 day 17 Apr '23 18 Apr '23 613
615 Substructure (P25) 28 days 07 Jun '23 01 Jul '23
616 4 days
P25 Pier 1st lift Reinforcement 07 Jun '23 10 Jun '23 606FS-1 day
617 P25 Pier 1st lift Shuttering 2 days 10 Jun '23 12 Jun '23 616
618 P25 Pier 1st lift Concreting 1 day 12 Jun '23 13 Jun '23 617
619 4 days
P25 Pier 2nd lift Reinforcement 13 Jun '23 16 Jun '23 618
620 P25 Pier 2nd lift Shuttering 2 days 16 Jun '23 18 Jun '23 619
621 P25 Pier 2nd lift Concreting 1 day 18 Jun '23 19 Jun '23 620
622 4 days
P25 Pier 3rd lift Reinforcement 19 Jun '23 23 Jun '23 621
623 P25 Pier 3rd lift Shuttering 2 days 23 Jun '23 24 Jun '23 622
624 P25 Pier 3rd lift Concreting 1 day 24 Jun '23 25 Jun '23 623
625 P25 Pier Cap Reinforcement 4 days 25 Jun '23 29 Jun '23 609FS+7 days
626 P25 Pier Cap Shuttering 2 days 29 Jun '23 01 Jul '23 625
627 P25 Pier Cap Concreting 1 day 01 Jul '23 01 Jul '23 626
628 Foundation (P24 A&B) 10 days 21 Apr '23 30 Apr '23
629 P24 A&B Exc. 3 days 21 Apr '23 24 Apr '23 614FS+4 days
630 P24 A&B PCC 1 day 24 Apr '23 25 Apr '23 629
631 P24 A&B Footing Reinforcement 5 days 25 Apr '23 29 Apr '23 630
632 P24 A&B Footing Concreting1 day 29 Apr '23 30 Apr '23 631
633 Substructure (P24B) 35 days 07 Jun '23 08 Jul '23
634 P24B Pier 1st lift 4 days 07 Jun '23 10 Jun '23 616SS
Reinforcement
635 P24B Pier 1st lift Shuttering 2 days 10 Jun '23 12 Jun '23 634
636 P24B Pier 1st lift Concreting1 day 12 Jun '23 13 Jun '23 635
637 P24B Pier 2nd lift 4 days 13 Jun '23 16 Jun '23 636
Reinforcement
638 P24B Pier 2nd lift Shuttering2 days 16 Jun '23 18 Jun '23 637
639 P24B Pier 2nd lift Concreting1 day 18 Jun '23 19 Jun '23 638
640 P24B Pier 3rd lift 4 days 19 Jun '23 23 Jun '23 639
Reinforcement
641 P24B Pier 3rd lift Shuttering2 days
23 Jun '23 24 Jun '23 640
642 P24B Pier 3rd lift Concreting1 day
24 Jun '23 25 Jun '23 641
643 P24B Pier Cap Reinforcement4 days 02 Jul '23 05 Jul '23 627
644 P24B Pier Cap Shuttering 2 days 05 Jul '23 07 Jul '23 643
645 P24B Pier Cap Concreting 1 day 07 Jul '23 08 Jul '23 644
646 Super Structure - Spine Beam26 days 24 Aug '23 16 Sep '23
647 Levelling of Bed 2 days 24 Aug '23 26 Aug '23 3SS+240 days
648 Staging arrangement 7 days 26 Aug '23 01 Sep '23 647SS+2 days
649 Bottom Sheet Placing 5 days 01 Sep '23 05 Sep '23 648
650 Reinforcement Placing 11 days 04 Sep '23 14 Sep '23 649SS+4 days
651 Placement of Void Former 3 days 05 Sep '23 08 Sep '23 650SS+1 day
652 Sheathing duct 6 days 08 Sep '23 13 Sep '23 651
653 PMC& PIMA Inspection 1 day 13 Sep '23 14 Sep '23 652
654 IE Inspection 1 day 14 Sep '23 15 Sep '23 653
655 Concreting 1 day 15 Sep '23 16 Sep '23 654
656 Super Structure - 26 days 16 Sep '23 11 Oct '23
Cantilever Wing Slab-RHS
Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 16
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
657 RHS - Levelling of Bed 3 days 16 Sep '23 20 Sep '23 655
658 RHS - Staging arrangement8 days 18 Sep '23 26 Sep '23 657SS+2 days
659 RHS - Wing beam form work 6 days 21 Sep '23 26 Sep '23 658SS+2 days
660 10 days
RHS - Reinforcement for Ribs 21 Sep '23 29 Sep '23 659SS
661 RHS - Wing slab form work11 days 21 Sep '23 01 Oct '23 660SS+1 day
662 13 days
RHS - Reinforcement for slab 23 Sep '23 06 Oct '23 661SS+2 days
663 RHS - Sheathing duct 3 days 06 Oct '23 08 Oct '23 662
664 RHS - PMC& PIMA Inspection 1 day 08 Oct '23 09 Oct '23 663
665 RHS - IE Inspection 1 day 09 Oct '23 10 Oct '23 664
666 RHS - Concreting 1 day 10 Oct '23 11 Oct '23 665
667 Super Structure - 25 days 11 Oct '23 02 Nov '23
Cantilever Wing Slab-LHS
668 LHS - Levelling of Bed 3 days 11 Oct '23 14 Oct '23 666
669 LHS - Staging arrangement 8 days 14 Oct '23 21 Oct '23 668
670 LHS - Wing beam form work6 days 16 Oct '23 21 Oct '23 669SS+2 days
671 10 days
LHS - Reinforcement for Ribs 16 Oct '23 24 Oct '23 670SS
672 LHS - Wing slab form work11 days 16 Oct '23 26 Oct '23 671SS+1 day
673 LHS-Reinforcement for slab12 days 18 Oct '23 29 Oct '23 672SS+2 days
674 LHS - Sheathing duct 3 days 29 Oct '23 31 Oct '23 673
675 LHS - PMC& PIMA Inspection 1 day 01 Nov '23 01 Nov '23 674
676 LHS - IE Inspection 1 day 01 Nov '23 02 Nov '23 675
677 LHS - Concreting 1 day 02 Nov '23 03 Nov '23 676
678 Pre Stressing 8 days 28 Nov '23 05 Dec '23 677FS+24 days
679 SEGMENT-08 (24A, P23, P22 274 days 05 May '23 08 Jan '24
& P21B)
680 Substructure 28 days 25 Jun '23 20 Jul '23
681 P24A Pier 1st lift 4 days 25 Jun '23 29 Jun '23 642
Reinforcement
682 P24A Pier 1st lift Shuttering 2 days 29 Jun '23 01 Jul '23 681
683 P24A Pier 1st lift Concreting1 day 01 Jul '23 01 Jul '23 682
684 P24A Pier 2nd lift 4 days 02 Jul '23 05 Jul '23 683
Reinforcement
685 P24A Pier 2nd lift Shuttering2 days 05 Jul '23 07 Jul '23 684
686 P24A Pier 2nd lift Concreting1 day 07 Jul '23 08 Jul '23 685
687 P24A Pier 3rd lift 4 days 08 Jul '23 11 Jul '23 686
Reinforcement
688 P24A Pier 3rd lift Shuttering2 days
11 Jul '23 13 Jul '23 687
689 P24A Pier 3rd lift Concreting1 day13 Jul '23 14 Jul '23 688
690 P24A Pier Cap Reinforcement 4 days 14 Jul '23 17 Jul '23 645FS+7 days
691 P24A Pier Cap Shuttering 2 days 18 Jul '23 19 Jul '23 690
692 P24A Pier Cap Concreting 1 day 19 Jul '23 20 Jul '23 691
693 Foundation (P23) 10 days 05 May '23 14 May '23
694 P23 Exc. 3 days 05 May '23 07 May '23 632FS+4 days
695 P23 PCC 1 day 07 May '23 08 May '23 694
696 P23 Footing Reinforcement 5 days 08 May '23 13 May '23 695
697 P23 Footing Concreting 1 day 13 May '23 14 May '23 696
698 Substructure (P23) 35 days 25 Jun '23 26 Jul '23
699 4 days 25 Jun '23
P23 Pier 1st lift Reinforcement 29 Jun '23 681SS
700 P23 Pier 1st lift Shuttering 2 days 29 Jun '23 01 Jul '23 699

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 17
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
701 P23 Pier 1st lift Concreting 1 day 01 Jul '23 01 Jul '23 700
702 4 days
P23 Pier 2nd lift Reinforcement 02 Jul '23 05 Jul '23 701
703 P23 Pier 2nd lift Shuttering 2 days 05 Jul '23 07 Jul '23 702
704 P23 Pier 2nd lift Concreting 1 day 07 Jul '23 08 Jul '23 703
705 4 days
P23 Pier 3rd lift Reinforcement 08 Jul '23 11 Jul '23 704
706 P23 Pier 3rd lift Shuttering 2 days 11 Jul '23 13 Jul '23 705
707 P23 Pier 3rd lift Concreting 1 day 13 Jul '23 14 Jul '23 706
708 4 days
P23 Pier Cap Reinforcement 20 Jul '23 24 Jul '23 692
709 P23 Pier Cap Shuttering 2 days 24 Jul '23 25 Jul '23 708
710 P23 Pier Cap Concreting 1 day 26 Jul '23 26 Jul '23 709
711 Foundation (P22) 10 days 14 May '23 22 May '23
712 P22 Exc. 3 days 14 May '23 16 May '23 697
713 P22 PCC 1 day 16 May '23 17 May '23 712
714 P22 Footing Reinforcement 5 days 17 May '23 22 May '23 713
715 P22 Footing Concreting 1 day 22 May '23 22 May '23 714
716 Substructure (P25) 28 days 14 Jul '23 08 Aug '23
717 4 days
P22 Pier 1st lift Reinforcement 14 Jul '23 17 Jul '23 707
718 P22 Pier 1st lift Shuttering 2 days 18 Jul '23 19 Jul '23 717
719 P22 Pier 1st lift Concreting 1 day 19 Jul '23 20 Jul '23 718
720 4 days
P22 Pier 2nd lift Reinforcement 20 Jul '23 24 Jul '23 719
721 P22 Pier 2nd lift Shuttering 2 days 24 Jul '23 25 Jul '23 720
722 P22 Pier 2nd lift Concreting 1 day 26 Jul '23 26 Jul '23 721
723 4 days
P22 Pier 3rd lift Reinforcement 26 Jul '23 30 Jul '23 722
724 P22 Pier 3rd lift Shuttering 2 days 30 Jul '23 01 Aug '23 723
725 P22 Pier 3rd lift Concreting 1 day 01 Aug '23 02 Aug '23 724
726 P22 Pier Cap Reinforcement 4 days 02 Aug '23 05 Aug '23 710FS+7 days
727 P22 Pier Cap Shuttering 2 days 05 Aug '23 07 Aug '23 726
728 P22 Pier Cap Concreting 1 day 07 Aug '23 08 Aug '23 727
729 Foundation (P21 A&B) 10 days 23 May '23 31 May '23
730 P21 A&B Exc. 3 days 23 May '23 25 May '23 715
731 P21 A&B PCC 1 day 25 May '23 26 May '23 730
732 P21 A&B Footing Reinforcement 5 days 26 May '23 30 May '23 731
733 P21 A&B Footing Concreting1 day 31 May '23 31 May '23 732
734 Substructure (P24B) 35 days 14 Jul '23 14 Aug '23
735 P21 A&B Pier 1st lift 4 days 14 Jul '23 17 Jul '23 717SS
Reinforcement
736 2 days
P21 A&B Pier 1st lift Shuttering 18 Jul '23 19 Jul '23 735
737 1 day
P21 A&B Pier 1st lift Concreting 19 Jul '23 20 Jul '23 736
738 P21 A&B Pier 2nd lift 4 days 20 Jul '23 24 Jul '23 737
Reinforcement
739 2 days
P21 A&B Pier 2nd lift Shuttering 24 Jul '23 25 Jul '23 738
740 1 day
P21 A&B Pier 2nd lift Concreting 26 Jul '23 26 Jul '23 739
741 P21 A&B Pier 3rd lift 4 days 26 Jul '23 30 Jul '23 740
Reinforcement
742 2 days
P21 A&B Pier 3rd lift Shuttering 30 Jul '23 01 Aug '23 741
743 1 day
P21 A&B Pier 3rd lift Concreting 01 Aug '23 02 Aug '23 742
744 P21 A&B Pier Cap 4 days 08 Aug '23 11 Aug '23 728
Reinforcement
745 2 days
P21 A&B Pier Cap Shuttering 11 Aug '23 13 Aug '23 744
Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 18
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
746 1 day
P21 A&B Pier Cap Concreting 13 Aug '23 14 Aug '23 745
747 Super Structure - Spine Beam29 days 25 Sep '23 22 Oct '23
748 Levelling of Bed 2 days 25 Sep '23 27 Sep '23 3SS+275 days
749 Staging arrangement 7 days 27 Sep '23 04 Oct '23 748SS+2 days
750 Bottom Sheet Placing 5 days 04 Oct '23 08 Oct '23 749
751 Reinforcement Placing 11 days 08 Oct '23 18 Oct '23 750
752 Placement of Void Former 3 days 12 Oct '23 15 Oct '23 751SS+4 days
753 Sheathing duct 6 days 14 Oct '23 19 Oct '23 752FS-1 day
754 PMC&PIMA Inspection 1 day 19 Oct '23 20 Oct '23 753
755 IE Inspection 1 day 20 Oct '23 21 Oct '23 754
756 Concreting 1 day 21 Oct '23 22 Oct '23 755
757 Super Structure - 27 days 22 Oct '23 18 Nov '23
Cantilever Wing Slab-RHS
758 RHS - Levelling of Bed 3 days 22 Oct '23 24 Oct '23 756
759 RHS - Staging arrangement8 days 24 Oct '23 31 Oct '23 758
760 RHS - Wing beam form work 6 days 26 Oct '23 31 Oct '23 759SS+2 days
761 10 days 26 Oct '23
RHS - Reinforcement for Ribs 04 Nov '23 760SS
762 RHS - Wing slab form work11 days 27 Oct '23 06 Nov '23 761SS+1 day
763 13 days 29 Oct '23
RHS - Reinforcement for slab 09 Nov '23 762SS+2 days
764 RHS - Sheathing duct 3 days 09 Nov '23 15 Nov '23 763
765 RHS - PMC&PIMA Inspection 1 day 15 Nov '23 16 Nov '23 764
766 RHS - IE Inspection 1 day 16 Nov '23 17 Nov '23 765
767 RHS - Concreting 1 day 17 Nov '23 18 Nov '23 766
768 Super Structure - 25 days 18 Nov '23 10 Dec '23
Cantilever Wing Slab-LHS
769 LHS - Levelling of Bed 3 days 18 Nov '23 20 Nov '23 767
770 LHS - Staging arrangement 8 days 20 Nov '23 27 Nov '23 769
771 LHS - Wing beam form work6 days 22 Nov '23 27 Nov '23 770SS+2 days
772 10 days 22 Nov '23
LHS - Reinforcement for Ribs 01 Dec '23 771SS
773 LHS - Wing slab form work11 days 23 Nov '23 03 Dec '23 772SS+1 day
774 LHS-Reinforcement for slab12 days 25 Nov '23 05 Dec '23 773SS+2 days
775 LHS - Sheathing duct 3 days 06 Dec '23 08 Dec '23 774
776 LHS - PMC&PIMA Inspection 1 day 08 Dec '23 09 Dec '23 775
777 LHS - IE Inspection 1 day 09 Dec '23 10 Dec '23 776
778 LHS - Concreting 1 day 10 Dec '23 11 Dec '23 777
779 Pre Stressing 8 days 01 Jan '24 08 Jan '24 778FS+24 days
780 SEGMENT-07 (21A, P20, P19 279 days 04 Jun '23 12 Feb '24
& P18B)
781 Substructure (P21A) 28 days 02 Aug '23 26 Aug '23
782 P21 A Pier 1st lift 4 days 02 Aug '23 05 Aug '23 743
Reinforcement
783 P21 A Pier 1st lift Shuttering2 days 05 Aug '23 07 Aug '23 782
784 P21 A Pier 1st lift Concreting1 day 07 Aug '23 08 Aug '23 783
785 P21 A Pier 2nd lift 4 days 08 Aug '23 11 Aug '23 784
Reinforcement
786 2 days
P21 A Pier 2nd lift Shuttering 11 Aug '23 13 Aug '23 785
787 1 day
P21 A Pier 2nd lift Concreting 13 Aug '23 14 Aug '23 786
788 P21 A Pier 3rd lift 4 days 14 Aug '23 18 Aug '23 787
Reinforcement

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 19
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
789 P21 A Pier 3rd lift Shuttering2 days 18 Aug '23 19 Aug '23 788
790 P21 A Pier 3rd lift Concreting1 day 19 Aug '23 20 Aug '23 789
791 4 days
P21 A Pier Cap Reinforcement 20 Aug '23 24 Aug '23 746FS+7 days
792 P21 A Pier Cap Shuttering 2 days 24 Aug '23 26 Aug '23 791
793 P21 A Pier Cap Concreting 1 day 26 Aug '23 26 Aug '23 792
794 Foundation (P20) 10 days 04 Jun '23 13 Jun '23
795 P20 Exc. 3 days 04 Jun '23 07 Jun '23 733FS+4 days
796 P20 PCC 1 day 07 Jun '23 07 Jun '23 795
797 P20 Footing Reinforcement 5 days 08 Jun '23 12 Jun '23 796
798 P20 Footing Concreting 1 day 12 Jun '23 13 Jun '23 797
799 Substructure (P20) 35 days 02 Aug '23 02 Sep '23
800 4 days
P20 Pier 1st lift Reinforcement 02 Aug '23 05 Aug '23 782SS
801 P20 Pier 1st lift Shuttering 2 days 05 Aug '23 07 Aug '23 800
802 P20 Pier 1st lift Concreting 1 day 07 Aug '23 08 Aug '23 801
803 4 days
P20 Pier 2nd lift Reinforcement 08 Aug '23 11 Aug '23 802
804 P20 Pier 2nd lift Shuttering 2 days 11 Aug '23 13 Aug '23 803
805 P20 Pier 2nd lift Concreting 1 day 13 Aug '23 14 Aug '23 804
806 4 days
P20 Pier 3rd lift Reinforcement 14 Aug '23 18 Aug '23 805
807 P20 Pier 3rd lift Shuttering 2 days 18 Aug '23 19 Aug '23 806
808 P20 Pier 3rd lift Concreting 1 day 19 Aug '23 20 Aug '23 807
809 P20 Pier Cap Reinforcement 4 days 27 Aug '23 30 Aug '23 793
810 P20 Pier Cap Shuttering 2 days 30 Aug '23 01 Sep '23 809
811 P20 Pier Cap Concreting 1 day 01 Sep '23 02 Sep '23 810
812 Foundation (P19) 10 days 13 Jun '23 22 Jun '23
813 P19 Exc. 3 days 13 Jun '23 15 Jun '23 798
814 P19 PCC 1 day 16 Jun '23 16 Jun '23 813
815 P19 Footing Reinforcement 5 days 16 Jun '23 21 Jun '23 814
816 P19 Footing Concreting 1 day 21 Jun '23 22 Jun '23 815
817 Substructure (P19) 28 days 20 Aug '23 14 Sep '23
818 4 days
P19 Pier 1st lift Reinforcement 20 Aug '23 24 Aug '23 808
819 P19 Pier 1st lift Shuttering 2 days 24 Aug '23 26 Aug '23 818
820 P19 Pier 1st lift Concreting 1 day 26 Aug '23 26 Aug '23 819
821 4 days
P19 Pier 2nd lift Reinforcement 27 Aug '23 30 Aug '23 820
822 P19 Pier 2nd lift Shuttering 2 days 30 Aug '23 01 Sep '23 821
823 P19 Pier 2nd lift Concreting 1 day 01 Sep '23 02 Sep '23 822
824 4 days
P19 Pier 3rd lift Reinforcement 02 Sep '23 05 Sep '23 823
825 P19 Pier 3rd lift Shuttering 2 days 05 Sep '23 07 Sep '23 824
826 P19 Pier 3rd lift Concreting 1 day 07 Sep '23 08 Sep '23 825
827 P19 Pier Cap Reinforcement 4 days 08 Sep '23 11 Sep '23 811FS+7 days
828 P19 Pier Cap Shuttering 2 days 12 Sep '23 13 Sep '23 827
829 P19 Pier Cap Concreting 1 day 13 Sep '23 14 Sep '23 828
830 Foundation (P18 A&B) 4 days 21 Jun '23 24 Jun '23
831 P18 A&B Exc. 1 day 21 Jun '23 22 Jun '23 815
832 P18 A&B PCC 1 day 22 Jun '23 23 Jun '23 831
833 P18 A&B Footing Reinforcement 1 day 23 Jun '23 23 Jun '23 832
834 P18 A&B Footing Concreting1 day 24 Jun '23 24 Jun '23 833
835 Substructure (P18B) 32 days 20 Aug '23 18 Sep '23

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 20
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
836 P18 B Pier 1st lift 4 days 20 Aug '23 24 Aug '23 818SS
Reinforcement
837 P18 B Pier 1st lift Shuttering2 days 24 Aug '23 26 Aug '23 836
838 P18 B Pier 1st lift Concreting1 day 26 Aug '23 26 Aug '23 837
839 P18 B Pier 2nd lift 4 days 27 Aug '23 30 Aug '23 838
Reinforcement
840 2 days
P18 B Pier 2nd lift Shuttering 30 Aug '23 01 Sep '23 839
841 1 day
P18 B Pier 2nd lift Concreting 01 Sep '23 02 Sep '23 840
842 P18 B Pier 3rd lift 4 days 02 Sep '23 05 Sep '23 841
Reinforcement
843 P18 B Pier 3rd lift Shuttering2 days
05 Sep '23 07 Sep '23 842
844 P18 B Pier 3rd lift Concreting1 day
07 Sep '23 08 Sep '23 843
845 4 days 12 Sep '23
P18 B Pier Cap Reinforcement 15 Sep '23 827
846 P18 B Pier Cap Shuttering 2 days 15 Sep '23 17 Sep '23 845
847 P18 B Pier Cap Concreting 1 day 17 Sep '23 18 Sep '23 846
848 Super Structure - Spine Beam29 days 02 Nov '23 01 Dec '23
849 Levelling of Bed 2 days 02 Nov '23 04 Nov '23 748FS+40 days
850 Staging arrangement 7 days 04 Nov '23 10 Nov '23 849SS+2 days
851 Bottom Sheet Placing 5 days 10 Nov '23 18 Nov '23 850
852 Reinforcement Placing 11 days 18 Nov '23 27 Nov '23 851
853 Placement of Void Former 3 days 21 Nov '23 24 Nov '23 852SS+4 days
854 Sheathing duct 6 days 23 Nov '23 28 Nov '23 853FS-1 day
855 PMC&PIMA Inspection 1 day 28 Nov '23 29 Nov '23 854
856 IE Inspection 1 day 29 Nov '23 30 Nov '23 855
857 Concreting 1 day 30 Nov '23 01 Dec '23 856
858 Super Structure - 27 days 01 Dec '23 25 Dec '23
Cantilever Wing Slab-RHS
859 RHS - Levelling of Bed 3 days 01 Dec '23 04 Dec '23 857
860 RHS - Staging arrangement8 days 04 Dec '23 11 Dec '23 859
861 RHS - Wing beam form work 6 days 06 Dec '23 11 Dec '23 860SS+2 days
862 10 days 06 Dec '23
RHS - Reinforcement for Ribs 14 Dec '23 861SS
863 RHS - Wing slab form work11 days 06 Dec '23 16 Dec '23 862SS+1 day
864 13 days 08 Dec '23
RHS - Reinforcement for slab 20 Dec '23 863SS+2 days
865 RHS - Sheathing duct 3 days 20 Dec '23 22 Dec '23 864
866 RHS - PMC&PIMA Inspection 1 day 22 Dec '23 23 Dec '23 865
867 RHS - IE Inspection 1 day 23 Dec '23 24 Dec '23 866
868 RHS - Concreting 1 day 24 Dec '23 25 Dec '23 867
869 Super Structure - 22 days 25 Dec '23 14 Jan '24
Cantilever Wing Slab-LHS
870 LHS - Levelling of Bed 3 days 25 Dec '23 28 Dec '23 868
871 LHS - Staging arrangement 8 days 27 Dec '23 03 Jan '24 870SS+2 days
872 LHS - Wing beam form work6 days 28 Dec '23 02 Jan '24 871SS+1 day
873 10 days 28 Dec '23
LHS - Reinforcement for Ribs 06 Jan '24 872SS
874 LHS - Wing slab form work11 days 29 Dec '23 07 Jan '24 873SS+1 day
875 LHS-Reinforcement for slab12 days 30 Dec '23 09 Jan '24 874SS+1 day
876 LHS - Sheathing duct 3 days 09 Jan '24 12 Jan '24 875
877 LHS - PMC&PIMA Inspection 1 day 12 Jan '24 13 Jan '24 876
878 LHS - IE Inspection 1 day 13 Jan '24 14 Jan '24 877
879 LHS - Concreting 1 day 14 Jan '24 14 Jan '24 878

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 21
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
880 Pre Stressing 8 days 05 Feb '24 12 Feb '24 879FS+24 days
881 SEGMENT-01 (A1, P1, P2 & P3A) 193 days 08 Oct '23 31 Mar '24
882 Foundation (P2) 10 days 08 Oct '23 17 Oct '23
883 P2 Exc. 3 days 08 Oct '23 11 Oct '23 847FS+21 days
884 P2 PCC 1 day 11 Oct '23 12 Oct '23 883
885 P2 Footing Reinforcement 5 days 12 Oct '23 16 Oct '23 884
886 P2 Footing Concreting 1 day 16 Oct '23 17 Oct '23 885
887 Substructure (P17) 28 days 24 Oct '23 20 Nov '23
888 P2 Pier 1st lift Reinforcement4 days 24 Oct '23 27 Oct '23 886FS+7 days
889 P2 Pier 1st lift Shuttering 2 days 27 Oct '23 29 Oct '23 888
890 P2 Pier 1st lift Concreting 1 day 29 Oct '23 30 Oct '23 889
891 P2 Pier 2nd lift Reinforcement4 days 30 Oct '23 02 Nov '23 890
892 P2 Pier 2nd lift Shuttering 2 days 02 Nov '23 04 Nov '23 891
893 P2 Pier 2nd lift Concreting 1 day 04 Nov '23 05 Nov '23 892
894 P2 Pier 3rd lift Reinforcement4 days 05 Nov '23 08 Nov '23 893
895 P2 Pier 3rd lift Shuttering 2 days 09 Nov '23 10 Nov '23 894
896 P2 Pier 3rd lift Concreting 1 day 10 Nov '23 14 Nov '23 895
897 P2 Pier Cap Reinforcement 4 days 14 Nov '23 18 Nov '23 896
898 P2 Pier Cap Shuttering 2 days 18 Nov '23 19 Nov '23 897
899 P2 Pier Cap Concreting 1 day 20 Nov '23 20 Nov '23 898
900 Foundation (P1) 10 days 24 Oct '23 01 Nov '23
901 P1 Exc. 3 days 24 Oct '23 26 Oct '23 886FS+7 days
902 P1 PCC 1 day 26 Oct '23 27 Oct '23 901
903 P1 Footing Reinforcement 5 days 27 Oct '23 31 Oct '23 902
904 P1 Footing Concreting 1 day 01 Nov '23 01 Nov '23 903
905 Substructure (P1) 28 days 04 Nov '23 02 Dec '23
906 P1 Pier 1st lift Reinforcement4 days 04 Nov '23 08 Nov '23 904FS+3 days
907 P1 Pier 1st lift Shuttering 2 days 08 Nov '23 09 Nov '23 906
908 P1 Pier 1st lift Concreting 1 day 09 Nov '23 10 Nov '23 907
909 P1 Pier 2nd lift Reinforcement4 days 10 Nov '23 17 Nov '23 908
910 P1 Pier 2nd lift Shuttering 2 days 17 Nov '23 19 Nov '23 909
911 P1 Pier 2nd lift Concreting 1 day 19 Nov '23 19 Nov '23 910
912 P1 Pier 3rd lift Reinforcement4 days 20 Nov '23 23 Nov '23 911
913 P1 Pier 3rd lift Shuttering 2 days 23 Nov '23 25 Nov '23 912
914 P1 Pier 3rd lift Concreting 1 day 25 Nov '23 26 Nov '23 913
915 P1 Pier Cap Reinforcement 4 days 26 Nov '23 29 Nov '23 914
916 P1 Pier Cap Shuttering 2 days 29 Nov '23 01 Dec '23 915
917 P1 Pier Cap Concreting 1 day 01 Dec '23 02 Dec '23 916
918 Foundation (A1) 10 days 08 Nov '23 19 Nov '23
919 A1 Exc. 3 days 08 Nov '23 10 Nov '23 904FS+7 days
920 A1 PCC 1 day 10 Nov '23 14 Nov '23 919
921 A1 Footing Reinforcement 5 days 14 Nov '23 19 Nov '23 920
922 A1 Footing Concreting 1 day 19 Nov '23 19 Nov '23 921
923 Substructure (A1) 28 days 25 Nov '23 20 Dec '23
924 A1 Pier 1st lift Reinforcement4 days 25 Nov '23 28 Nov '23 913
925 A1 Pier 1st lift Shuttering 2 days 28 Nov '23 30 Nov '23 924
926 A1 Pier 1st lift Concreting 1 day 30 Nov '23 01 Dec '23 925
927 A1 Pier 2nd lift Reinforcement4 days 01 Dec '23 05 Dec '23 926

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 22
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
928 A1 Pier 2nd lift Shuttering 2 days
05 Dec '23 06 Dec '23 927
929 A1 Pier 2nd lift Concreting 1 day06 Dec '23 07 Dec '23 928
930 4 days 07 Dec '23
A1 Pier 3rd lift Reinforcement 11 Dec '23 929
931 A1 Pier 3rd lift Shuttering 2 days 11 Dec '23 13 Dec '23 930
932 A1 Pier 3rd lift Concreting 1 day 13 Dec '23 13 Dec '23 931
933 A1 Pier Cap Reinforcement 4 days 14 Dec '23 17 Dec '23 932
934 A1 Pier Cap Shuttering 2 days 17 Dec '23 19 Dec '23 933
935 A1 Pier Cap Concreting 1 day 19 Dec '23 20 Dec '23 934
936 Super Structure - Spine Beam29 days 08 Dec '23 03 Jan '24
937 Levelling of Bed 2 days 08 Dec '23 10 Dec '23 776SS
938 Staging arrangement 7 days 10 Dec '23 16 Dec '23 937SS+2 days
939 Bottom Sheet Placing 5 days 16 Dec '23 21 Dec '23 938
940 Reinforcement Placing 11 days 21 Dec '23 30 Dec '23 939
941 Placement of Void Former 3 days 24 Dec '23 27 Dec '23 940SS+4 days
942 Sheathing duct 6 days 26 Dec '23 31 Dec '23 941FS-1 day
943 PMC&PIMA Inspection 1 day 31 Dec '23 01 Jan '24 942
944 IE Inspection 1 day 01 Jan '24 02 Jan '24 943
945 Concreting 1 day 02 Jan '24 03 Jan '24 944
946 Super Structure - 27 days 03 Jan '24 27 Jan '24
Cantilever Wing Slab-RHS
947 RHS - Levelling of Bed 3 days 03 Jan '24 06 Jan '24 945
948 RHS - Staging arrangement8 days 06 Jan '24 13 Jan '24 947
949 RHS - Wing beam form work 6 days 07 Jan '24 13 Jan '24 948SS+2 days
950 RHS - Reinforcement for Ribs10 days 07 Jan '24 16 Jan '24 949SS
951 RHS - Wing slab form work11 days 08 Jan '24 18 Jan '24 950SS+1 day
952 RHS - Reinforcement for slab13 days 10 Jan '24 22 Jan '24 951SS+2 days
953 RHS - Sheathing duct 3 days 22 Jan '24 24 Jan '24 952
954 RHS - PMC&PIMA Inspection 1 day 24 Jan '24 25 Jan '24 953
955 RHS - IE Inspection 1 day 25 Jan '24 26 Jan '24 954
956 RHS - Concreting 1 day 26 Jan '24 27 Jan '24 955
957 Super Structure - 176 days 24 Oct '23 31 Mar '24
Cantilever Wing Slab-LHS
958 LHS - Levelling of Bed 3 days 27 Jan '24 30 Jan '24 956
959 LHS - Staging arrangement 8 days 30 Jan '24 06 Feb '24 958
960 LHS - Wing beam form work6 days 31 Jan '24 06 Feb '24 959SS+2 days
961 LHS - Reinforcement for Ribs10 days 31 Jan '24 09 Feb '24 960SS
962 LHS - Wing slab form work11 days 01 Feb '24 11 Feb '24 961SS+1 day
963 LHS-Reinforcement for slab12 days 03 Feb '24 14 Feb '24 962SS+2 days
964 LHS - Sheathing duct 3 days 14 Feb '24 16 Feb '24 963
965 LHS - PMC&PIMA Inspection 1 day 16 Feb '24 17 Feb '24 964
966 LHS - IE Inspection 1 day 17 Feb '24 18 Feb '24 965
967 LHS - Concreting 1 day 18 Feb '24 19 Feb '24 966
968 Pre Stressing 8 days 11 Mar '24 18 Mar '24 967FS+24 days
969 RE Wall 176 days 24 Oct '23 31 Mar '24
970 Excavation 21 days 24 Oct '23 14 Nov '23 935SS-60 days
971 Backfilling 45 days 07 Nov '23 20 Dec '23 935FF
972 Levelling pad PCC M15 2 days 14 Nov '23 16 Nov '23 970
973 RCC M20 Coping Beam 7 days 19 Feb '24 25 Feb '24 967

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 23
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
974 PCC for Friction Slab 3 days 25 Feb '24 28 Feb '24 973
975 RCC for Friction slab 10 days 28 Feb '24 08 Mar '24 974
Crash Barrier
976 Median Crash Barrier 14 days 19 Mar '24 31 Mar '24 968
(Below Deck)
977 Earthfill at Crash 7 days 25 Mar '24 31 Mar '24 976FF
Barrier (Entire length)
978 Bill No. 9 : Balance works of 20 days 27 Oct '23 17 Nov '23
Minor Bridg Km 67+716
979 Providing and laying stone 7 days 27 Oct '23 02 Nov '23 176SS
pitching on Embankment
slopes as per drawings and
Technical Specifications
Clauses 1400 and 2500 .
980 Providing and laying filter 4 days 27 Oct '23 31 Oct '23 176SS
media beneath the stone
pitching complete as per
drawing and Technical
Specification Clause 2504
981 Excavation for Toe Wall 2 days 02 Nov '23 04 Nov '23 979
under Stone Pitching
982 PCC M15 for Toe Wall under 1 day 04 Nov '23 05 Nov '23 981
Stone Pitching
983 PCC M15 for Approach Slab 1 day 05 Nov '23 06 Nov '23 982
984 RCC M30 for Approach Slab 7 days 06 Nov '23 15 Nov '23 983
985 HYSD for Approach Slab 7 days 06 Nov '23 15 Nov '23 983
986 Painting of Crash barrier 2 days 15 Nov '23 17 Nov '23 985
987 Bill No. 9 : Balance works of 27 days 02 Nov '23 29 Nov '23
Minor Bridge at Km 69+578
988 Providing and laying stone 7 days 02 Nov '23 08 Nov '23 979
pitching on Embankment
slopes as per drawings and
Technical Specifications
Clauses 1400 and 2500 .

989 Providing and laying filter 4 days 02 Nov '23 06 Nov '23 979
media beneath the stone
pitching complete as per
drawing and Technical
Specification Clause 2504
990 Excavation for Toe Wall 2 days 09 Nov '23 10 Nov '23 988
under Stone Pitching
991 PCC M15 for Toe Wall under 1 day 10 Nov '23 14 Nov '23 990
Stone Pitching
992 PCC M15 for Approach Slab 1 day 14 Nov '23 15 Nov '23 991

993 RCC M30 for Approach Slab 7 days 15 Nov '23 21 Nov '23 992

994 HYSD for Approach Slab 7 days 21 Nov '23 27 Nov '23 993

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 24
ID Task Task Name Duration Start Finish Predecessors 2023 2024
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
995 Painting of Crash barrier 2 days 28 Nov '23 29 Nov '23 994

Task Project Summary Manual Task Start-only Deadline

Project: Catch-up Plan Split Inactive Task Duration-only Finish-only Progress


Date: 25 Jan '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 25