ID Task Task Name Duration Start Finish Jun '23 Jul '23 Aug '23 Sep '23 Oct

Finish Jun '23 Jul '23 Aug '23 Sep '23 Oct '23 Nov '23
Mode 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12
1 ENDOSULFAN REHABILITATION VILLAGE 124 days 01-07-2023 01-11-2023
2 Ground Floor 120 days 01-07-2023 28-10-2023
3 Left side-Clinical psychology 117 days 01-07-2023 25-10-2023
4 PHE 81 days 01-07-2023 19-09-2023
5 Burried Soil and waste with IC30 days 01-07-2023 30-07-2023
6 leak test 3 days 31-07-2023 02-08-2023
7 concealed water line 7 days 03-08-2023 09-08-2023
8 burried water line 2 days 10-08-2023 11-08-2023
9 pressure test 3 days 10-08-2023 12-08-2023
10 sanitary 5 days 15-09-2023 19-09-2023
11 FPS/FAS 25 days 01-10-2023 25-10-2023
12 Hydrant/Brigade piping 6 days 01-10-2023 06-10-2023
13 Pressure test 2 days 07-10-2023 08-10-2023
14 Valve installation 2 days 19-10-2023 20-10-2023
15 FA cable 3 days 05-10-2023 07-10-2023
16 FA fixtures 2 days 22-10-2023 23-10-2023
17 Extinguisher 2 days 22-10-2023 23-10-2023
18 Sinages 2 days 24-10-2023 25-10-2023
19 Right side -Consulting 77 days 13-08-2023 28-10-2023
20 PHE 54 days 13-08-2023 05-10-2023
21 burried soil and waste with IC28 days 13-08-2023 09-09-2023
22 leak test 3 days 10-09-2023 12-09-2023
23 Concealed water line 7 days 13-09-2023 19-09-2023
24 Burried water line 2 days 20-09-2023 21-09-2023
25 Pressure test 3 days 22-09-2023 24-09-2023
26 Sanitary 5 days 01-10-2023 05-10-2023
27 FPS/FAS 21 days 08-10-2023 28-10-2023
28 Hydrant/Brigade piping 8 days 09-10-2023 16-10-2023
29 Pressure test 2 days 17-10-2023 18-10-2023
30 Valve installation 2 days 21-10-2023 22-10-2023
31 FA cable 2 days 08-10-2023 09-10-2023
32 FA fixtures 2 days 24-10-2023 25-10-2023
33 Extinguisher 2 days 25-10-2023 26-10-2023
34 Sinages 2 days 27-10-2023 28-10-2023
35 Terrace Floor 31 days 25-09-2023 25-10-2023
36 Exposed water line left side 4 days 25-09-2023 28-09-2023
37 Exposed water line right side 3 days 29-09-2023 01-10-2023
38 Sprinkler piping 15 days 02-10-2023 16-10-2023
39 Terrace pump 4 days 22-10-2023 25-10-2023
40 FA Commissioning 4 days 29-10-2023 01-11-2023
41 Hydrant commissioning 4 days 29-10-2023 01-11-2023

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Progress
Date: 31-05-2023
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only