ID Task Name Duration Start Finish Predecessors Sep '23 Oct '23 Nov '23 Dec '23

13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17
1 PROPOSED 96.63 9/1/2023 12/12/2023
DEMOLITIONS,ALTERATIONS AT AIR days?
2
3 PRELIMINARIES,MOBILISATION 7.63 days? 9/1/2023 9/8/2023
4 GENERAL CONDITIONS AND
PRELIMINARIES
5 Site Possession 0 days 9/1/2023 9/1/2023 9/1
6 Commencement of Work 0 days 9/1/2023 9/1/2023 9/1
7 PRE CONSTRUCTION SITE WORKS 5 days 9/2/2023 9/7/2023
8 Equipment Mobilisation 2 days 9/2/2023 9/4/2023 6FS+1 day
9 Setting Out 2 days 9/5/2023 9/7/2023 8
10 STATUTORY PERMITS & APPROVALS4 days 9/5/2023 9/8/2023
11 KAA Approved drawings 2 days 9/5/2023 9/6/2023
12 NEMA 2 days 9/7/2023 9/8/2023 11
13 CIVIL WORKS 21 days 9/9/2023 10/1/2023
14 De‐commissioning/Demolition of 7 days 9/9/2023 9/16/2023 12
kitchen
15 Removal of existing building Roofs 2 days 9/16/2023 9/18/2023 14,12
16 Demolition of gates/Grills 1 day 9/18/2023 9/19/2023 15
17 Demolition of facia boards, Doors, 4 days 9/19/2023 9/23/2023 16
Partitions etc
18 Demolition of existing floors 5 days 9/21/2023 9/27/2023 17FS‐2 days
19 4 days 9/27/2023 10/1/2023 18
20 SITE PREPARTION WORKS 13 days 9/5/2023 9/18/2023
21 Removal of shrubs,top soil 3 days 9/5/2023 9/7/2023 11SS
22 General Excavation 10 days 9/8/2023 9/18/2023 21
works/Washroom excavation works
23 ABLUTION UNITS (MALE & FEMALE) 80 days 9/18/2023 12/12/2023
24 Sub structure concrete 7 days 9/18/2023 9/26/2023 22
works/backfilling works
25 Superstructure concrete works 10 days 9/26/2023 10/6/2023 24
26 Block walling 7 days 10/6/2023 10/13/2023 25
27 Electrical/Plumbing first fix 2 days 10/10/2023 10/12/2023 26FS‐3 days
28 Internal/External Plaster works 8 days 10/13/2023 10/22/2023 26
29 Vanity structures 4 days 10/22/2023 10/26/2023 28
30 Internal ceiling works 7 days 10/26/2023 11/2/2023 29
31 Roofing works 10 days 11/3/2023 11/13/2023 30
32 Doors/Windows 8 days 11/13/2023 11/22/2023 31
33 Wall and floor finishes 16 days 11/22/2023 12/8/2023 32
34 Electrical/Plumbing final fixes 3 days 12/8/2023 12/12/2023 33
35 GENERATOR RELOCATION WORKS 10 days 9/26/2023 10/6/2023
36 Blockwalling/Louver walling 7 days 9/26/2023 10/3/2023 24
37 Construction of Plinth 2 days 10/3/2023 10/5/2023 36
38 Generator shifting and commissionin1 day 10/5/2023 10/6/2023 37
39 ROOFING REPAIRS AND RAINWATER 15 days 10/1/2023 10/17/2023
DISPOSAL
40 Small 4 buildings roof timber works 7 days 10/1/2023 10/8/2023
41 Roof covering works 4 days 10/8/2023 10/12/2023 40
42 Rain water Disposal 4 days 10/12/2023 10/17/2023 41
43 EXTERNAL FAÇADE FINISHES 29 days 10/1/2023 10/31/2023
44 Walling Works 10 days 10/1/2023 10/11/2023
45 ICT/CCTV/Security first fix 2 days 10/10/2023 10/12/2023 44FF+1 day
46 Plaster works 8 days 10/11/2023 10/20/2023 44
47 Painting works 7 days 10/20/2023 10/27/2023 46
48 ICT/CCTV/Security Final fix 4 days 10/27/2023 10/31/2023 47
49 WINDOWS & DOORFINISHES 36 days 10/27/2023 12/4/2023
50 Louver windows 21 days 10/27/2023 11/18/2023 47
51 Doors 15 days 11/18/2023 12/4/2023 50
52 DRAINAGE WORKS/SURFACES AND 73 days 9/26/2023 12/12/2023
PAVING WORKS
53 Drainage works inside the plot 14 days 9/26/2023 10/10/2023 24
54 Drainage works outside/Road crossin14 days 10/1/2023 10/16/2023 53SS+5 days
55 Surface treatment 3 days 10/16/2023 10/19/2023 54,53
56 Foundation works for the canopy 10 days 10/19/2023 10/29/2023 55
57 Graded crushed stone filling 7 days 10/30/2023 11/6/2023 55,56
58 Canopy works 10 days 11/3/2023 11/13/2023 57FS‐3 days
59 Pavings 7 days 11/10/2023 11/17/2023 58FS‐3 days
60 Open Drain Covers 2 days 11/17/2023 11/20/2023 59
61 Buggage Claim Bench 7 days 11/20/2023 11/27/2023 60
62 Demolition of Canopy and Timber 4 days 11/27/2023 12/1/2023 61
Benching
63 Gates/Grills 10 days 12/1/2023 12/12/2023 62
64 NEW KITCHEN & GENERATOR AREAS 35.5 days 10/2/2023 11/8/2023
65 Walling 4 days 10/2/2023 10/5/2023
66 Plaster 4 days 10/6/2023 10/10/2023 65
67 Painting 4 days 10/12/2023 10/16/2023 66
68 Floor finishes 5 days 10/18/2023 10/23/2023 67
69 Concrete Platform 2 days 10/25/2023 10/26/2023 68
70 Grill doors 5 days 10/27/2023 11/1/2023 69
71 Kitchen worktops 5 days 11/3/2023 11/8/2023 70
72 SNAGGING WORKS 7 days 12/4/2023 12/11/2023
73 General snagging works 7 days 12/4/2023 12/11/2023
74 MEPD Commissioning works 5 days 12/4/2023 12/8/2023 73SS
75 PROJECT HANDOVER/CLOSED OUT 0 days 12/12/2023 12/12/2023 73 12/12
76

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish‐only Critical Split
Project: msproj11
Date: 9/17/2023 Split Project Summary Inactive Task Manual Task Manual Summary Deadline Progress
Milestone External Tasks Inactive Milestone Duration‐only Start‐only Critical Manual Progress

Page 1