标识号 Project project 前置任务 开始时间 完成时间 2023年9月 2023年10月 2023年11月 2023年12月 2024年1月 2024年2月

duration 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11
1 Diaphragm Wall Work Schedule 152 d 2023/9/11 2024/2/9
2 Mobilization to site 3d 2023/9/11 2023/9/13
3 provisional facility establishment 8d 2 2023/9/15 2023/9/22
4 Conducting Wall / Guide Wall 83.5 d 2023/9/23 2023/12/15
5 Stage 1 (40m long, west side type 1-4a & east side type23 3-4)
d 2023/9/23 2023/10/15
6 setting out and inspection 3d 3 2023/9/23 2023/9/25
7 Concrete ground cutting, excavation and clearing 5d 6 2023/9/26 2023/9/30
8 steel bar installation 4d 7 2023/10/1 2023/10/4
9 formwork installation 4d 8 2023/10/5 2023/10/8
10 concreting 3d 9 2023/10/9 2023/10/11
11 removal of formwork 2d 10 2023/10/12 2023/10/13
12 enhancement of complete work 2d 11 2023/10/14 2023/10/15
13 Stage 2 (10m long, east side type 1-2) 8d 2023/12/7 2023/12/15
14 setting out and inspection 1d 55 2023/12/7 2023/12/8
15 Concrete ground cutting, excavation and clearing 1d 14 2023/12/8 2023/12/9
16 steel bar installation 2d 15 2023/12/9 2023/12/11
17 formwork installation 1d 16 2023/12/11 2023/12/12
18 concreting 1d 17 2023/12/12 2023/12/13
19 removal of formwork 1d 18 2023/12/13 2023/12/14
20 enhancement of complete work 1d 19 2023/12/14 2023/12/15
21 Permanent Wall (Closer to running tunnel) 130 d 2023/9/15 2024/1/22
22 West flange 88.5 d 2023/9/15 2023/12/12
23 Wall type 1 49.5 d 2023/9/15 2023/11/3
24 excavation-borehole drill 6d 12FS+7 d 2023/10/23 2023/10/28
25 test of slot verticality and approval after report 3d 24 2023/10/29 2023/10/31
26 reinforcement preparation(CWE) 6d 2 2023/9/15 2023/9/20
27 installation of reinforcement 1d 26,25 2023/11/1 2023/11/1
28 concreting 1d 27 2023/11/2 2023/11/2
29 finishing and relocation of drill rig 0.5 d 28 2023/11/3 2023/11/3
30 Wall type 3a 53 d 2023/9/21 2023/11/12
31 excavation-borehole drill 4d 29 2023/11/3 2023/11/7
32 test of slot verticality and approval after report 3d 31 2023/11/7 2023/11/10
33 reinforcement preparation(CWE) 4d 26 2023/9/21 2023/9/24
34 installation of reinforcement 1d 33,32 2023/11/10 2023/11/11
35 concreting 1d 34 2023/11/11 2023/11/12
36 finishing and relocation of drill rig 0.5 d 35 2023/11/12 2023/11/12
37 Wall type 2 58.5 d 2023/9/25 2023/11/22
38 excavation-borehole drill 4d 36 2023/11/13 2023/11/16
39 test of slot verticality and approval after report 3d 38 2023/11/17 2023/11/19
40 reinforcement preparation(CWE) 3d 33 2023/9/25 2023/9/27
41 installation of reinforcement 1d 40,39 2023/11/20 2023/11/20
42 concreting 1d 41 2023/11/21 2023/11/21
43 finishing and relocation of drill rig 0.5 d 42 2023/11/22 2023/11/22
44 Wall type 4a 65 d 2023/9/28 2023/12/1
45 excavation-borehole drill 4d 43 2023/11/22 2023/11/26
46 test of slot verticality and approval after report 3d 45 2023/11/26 2023/11/29
47 reinforcement preparation(CWE) 4d 40 2023/9/28 2023/10/1
48 installation of reinforcement 1d 47,46 2023/11/29 2023/11/30
49 concreting 1d 48 2023/11/30 2023/12/1
50 finishing and relocation of drill rig 0.5 d 49 2023/12/1 2023/12/1
51 CAP BEAM(no. 2 &3) 66.5 d 2023/10/2 2023/12/7
52 reinforcement preparation(CWE) 4d 47 2023/10/2 2023/10/5
53 installatin fo reinforcement 4d 52,50 2023/12/2 2023/12/5
标识号 Project project 前置任务 开始时间 完成时间 2023年9月 2023年10月 2023年11月 2023年12月 2024年1月 2024年2月
duration 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11
54 concreting 1d 53 2023/12/6 2023/12/6
55 finishing 0.5 d 54 2023/12/7 2023/12/7
56 Removal of lateral part of conducting wall 5d 55 2023/12/7 2023/12/12
57 East flange (Further to running tunnel) 104 d 2023/10/6 2024/1/17
58 Wall type W1 80 d 2023/10/6 2023/12/24
59 excavation-borehole drill 4d 20,71 2023/12/15 2023/12/19
60 test of slot verticality and approval after report 3d 59 2023/12/19 2023/12/22
61 reinforcement preparation(CWE) 4d 52 2023/10/6 2023/10/9
62 installation of reinforcement 1d 60,61 2023/12/22 2023/12/23
63 concreting 1d 62 2023/12/23 2023/12/24
64 finishing and relocation of drill rig 0.5 d 63 2023/12/24 2023/12/24
65 Wall type W3 62.5 d 2023/10/10 2023/12/11
66 excavation-borehole drill 4d 50 2023/12/2 2023/12/5
67 test of slot verticality and approval after report 3d 66 2023/12/6 2023/12/8
68 reinforcement preparation(CWE) 3d 61 2023/10/10 2023/10/12
69 installation of reinforcement 1d 67,68 2023/12/9 2023/12/9
70 concreting 1d 69 2023/12/10 2023/12/10
71 finishing and relocation of drill rig 0.5 d 70 2023/12/11 2023/12/11
72 Wall type W2 82.5 d 2023/10/13 2024/1/3
73 excavation-borehole drill 4d 64 2023/12/25 2023/12/28
74 test of slot verticality and approval after report 3d 73 2023/12/29 2023/12/31
75 reinforcement preparation(CWE) 3d 68 2023/10/13 2023/10/15
76 installation of reinforcement 1d 74,75 2024/1/1 2024/1/1
77 concreting 1d 76 2024/1/2 2024/1/2
78 finishing and relocation of drill rig 0.5 d 77 2024/1/3 2024/1/3
79 Wall type W4 89 d 2023/10/16 2024/1/12
80 excavation-borehole drill 4d 78 2024/1/3 2024/1/7
81 test of slot verticality and approval after report 3d 80 2024/1/7 2024/1/10
82 reinforcement preparation(CWE) 3d 75 2023/10/16 2023/10/18
83 installation of reinforcement 1d 81,82 2024/1/10 2024/1/11
84 concreting 1d 83 2024/1/11 2024/1/12
85 finishing and relocation of drill rig 0.5 d 84 2024/1/12 2024/1/12
86 CAP BEAM(No. 2& 1) 91 d 2023/10/19 2024/1/17
87 reinforcement preparation(CWE) 2d 82 2023/10/19 2023/10/20
88 installatin fo reinforcement 3d 87,85 2024/1/13 2024/1/15
89 concreting 1d 88 2024/1/16 2024/1/16
90 finishing 1d 89 2024/1/17 2024/1/17
91 Removal of lateral part of conducting wall 5d 90 2024/1/18 2024/1/22
92 Construction of Provisional Diaphram Wall 109 d 2023/10/21 2024/2/6
93 Wall type1B 98.5 d 2023/10/21 2024/1/27
94 excavation-borehole drill 4d 90 2024/1/18 2024/1/21
95 test of slot verticality and approval after report 3d 94 2024/1/22 2024/1/24
96 reinforcement preparation(CWE) 3d 87 2023/10/21 2023/10/23
97 installation of reinforcement 1d 95,96 2024/1/25 2024/1/25
98 concreting 1d 97 2024/1/26 2024/1/26
99 finishing and relocation of drill rig 0.5 d 98 2024/1/27 2024/1/27
100 Wall type1A 105 d 2023/10/24 2024/2/5
101 excavation-borehole drill 4d 99 2024/1/27 2024/1/31
102 test of slot verticality and approval after report 3d 101 2024/1/31 2024/2/3
103 reinforcement preparation(CWE) 3d 96 2023/10/24 2023/10/26
104 installation of reinforcement 1d 102,103 2024/2/3 2024/2/4
105 concreting 1d 104 2024/2/4 2024/2/5
106 finishing and relocation of drill rig 0.5 d 105 2024/2/5 2024/2/5
标识号 Project project 前置任务 开始时间 完成时间 2023年9月 2023年10月 2023年11月 2023年12月 2024年1月 2024年2月
duration 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11
107 Removal of conducting wall 1d 106 2024/2/6 2024/2/6
108 Demobilization 3d 107 2024/2/7 2024/2/9