Balance Activities Schedule Basement

S.No. Description Days Start Finish Remarks


Tower B (Basement)
A Retainers (Pour 3 & 4 Lift )
Reinforcement 2 05-04-2023 07-04-2023 Completed
Shuttering 3 25-04-2023 28-04-2023 Completed
Casting 2 29-04-2023 30-04-2023 Completed

Ramp (Pour 3 & 4)


Shuttering 4 20-06-2023 24-06-2023
Reinforcement 3 25-06-2023 28-06-2023
Casting 1 29-06-2023 29-06-2023

Staircase - 3 (Pour -4)


Shuttering 3 01-05-2023 04-05-2023 Completed
Reinforcement 3 05-05-2023 08-05-2023 Completed
Casting 3 09-05-2023 12-05-2023 Completed

Backfilling (Pour 3 & 4) 30 19-05-2023 18-06-2023 WIP


Compaction & Leveling 8 10-06-2023 18-06-2023
PCC 10 19-06-2023 29-06-2023
Grade Slab
Reinforcement 15 30-06-2023 15-07-2023
RCC 15 01-07-2023 16-07-2023
Blockwork 7 17-07-2023 24-07-2023
Plaster 6 21-07-2023 27-07-2023

B Retainer (Pour 1 & 2 Lift )


Reinforcement 2 01-05-2023 03-05-2023 Completed
Shuttering 5 04-05-2023 09-05-2023 Completed
Casting 2 10-05-2023 12-05-2023 Completed
Ramp (Pour 1 & 2)
Shuttering 3 10-06-2023 13-06-2023
Reinforcement 2 14-06-2023 16-06-2023
Casting 1 17-06-2023 17-06-2023

Staircase - 4 (Pour -2)


Shuttering 3 19-06-2023 22-06-2023
Reinforcement 3 23-06-2023 26-06-2023
Casting 3 27-06-2023 30-06-2023

Backfilling (Pour 1 & 2) 20 19-06-2023 09-07-2023 WIP


Compaction & Leveling 10 01-07-2023 11-07-2023
PCC 10 09-07-2023 19-07-2023
Grade Slab
Reinforcement 15 20-07-2023 04-08-2023
RCC 15 21-07-2023 05-08-2023
Blockwork 7 06-08-2023 13-08-2023
Plaster 6 10-08-2023 16-08-2023

C DRAIN
Layout 7 12-07-2023 19-07-2023
Base Preparation 7 20-07-2023 27-07-2023
PCC 20 19-06-2023 09-07-2023
Reinforcement 20 16-07-2023 05-08-2023
Shuttering 20 19-07-2023 08-08-2023
Casting 20 20-07-2023 09-08-2023