WORKING SCHEUDLE 01 Sep 2022 to 01 Sep 2023

Project: SITARA COMPLEX BLOCK # 05

Contractor :-M/S Taha Associates Project Start Date:-01 Sep 2022 Project End Date:-01 Sep 2023 Lagend Proposed
Item Description Start Date End Date Total 20-Oct 20-Nov 20-Dec Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Status
No. Days
W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

1 STRUCTURE WORK

A BASEMENT

1.0 Excavation 1-Sep-2022 1-Oct-2022 30

2.0 P.c.c 1-Oct-2022 11-Oct-2022 10

3.0 Steel Fixing of (Footing & walls ) 11-Oct-2022 22-Oct-2022 5

4.0 Footing Concrete 22-Oct-2022 16-Nov-2022 25

5.0 Concrete (Columns & Walls ) 17-Nov-2022 16-Dec-2022 29

6.0 Roof Slab ,Beam Concrete 18-Dec-2022 1-Feb-2023 45

GROUND FLOOR:-
2

1.0 Columns Concrete 1-Feb-2023 16-Feb-2023 15

2.0 Roof Slab ,Beam Concrete 16-Feb-2023 17-Mar-2023 29

1st FLOOR :-
3

1.0 Columns Concrete 18-Mar-2023 6-Apr-2023 19

2.0 Roof Slab ,Beam Concrete 6-Apr-2023 16-May-2023 40

FINISHING WORK
4

1.0 Roof Slab Water Proofing 18-May-2023 16-Jun-2023 29

BASEMENT :-
A

1.0 Brick Walls & Plaster 1-Jun-2023 20-Jun-2023 19

2.0 Flooring P.c.c 20-Jun-2023 30-Jun-2023 10 .

3.0 Tile Work 1-Jul-2023 15-Jul-2023 14

4.0 False Celling Work 15-Jul-2023 25-Jul-2023 10

5.0 Paint Work 15-Jul-2023 30-Jul-2023 15

GROUND FLOOR :-
B

1.0 Brick Walls & Plaster 1-Jul-2023 15-Jul-2023 14

2.0 Flooring P.c.c 20-Jul-2023 30-Jul-2023 10

3.0 Tile Work 20-Jul-2023 30-Jul-2023 16

4.0 False Celling Work 30-Jul-2023 9-Aug-2023 10

5.0 Paint Work 9-Aug-2023 24-Aug-2023 15

6.0 Aluminium Work 26-Aug-2023 1-Sep-2023 14

1st FLOOR :-
C

1.0 Brick Walls & Plaster 1-Jul-2023 15-Jul-2023 14

2.0 Flooring P.c.c 20-Jul-2023 30-Jul-2023 10

3.0 Tile Work 20-Jul-2023 30-Jul-2023 16

4.0 False Celling Work 30-Jul-2023 9-Aug-2023 10

5.0 Paint Work 9-Aug-2023 24-Aug-2023 15

6.0 Aluminium Work 26-Aug-2023 1-Sep-2023 14