S.M. NIRMAN
Infrastructure & Development Pvt. Ltd.
Address : 20/3 S.N. Roy Road Kolkata 38
Out Side plaster 9 Jan 2024 8 Apr 2024 25 Jan 2024 24 Apr 2024 4 Feb 2024 2 May 2024
Inside Plaster 10 Mar 2024 25 Mar 2024 26 Mar 2024 10 Apr 2024 5 Apr 2024 20 Apr 2024
Above roof Brick Work 13 Jan 2024 23 Jan 2024 29 Jan 2024 13 Feb 2024 8 Feb 2024 23 Feb 2024
Casting 1 Nov 2023 23 Nov 2023 24 Nov 2023 14 Dec 2023 3 Dec 2023 23 Dec 2023
Inside Plaster 23 Feb 2024 9 Mar 2024 10 Mar 2024 25 Mar 2024 20 Mar 2024 4 Apr 2024
11th Floor Level
Elevation
Brick Work 31 Dec 2023 12 Jan 2024 16 Jan 2024 28 Jan 2024 26 Jan 2024 7 Feb 2024
Casting 6 Oct 2023 31 Oct 2023 22 Oct 2023 23 Nov 2023 8 Nov 2023 2 Dec 2023
Inside Plaster 31 Jan 2024 22 Feb 2024 16 Feb 2024 9 Mar 2024 26 Feb 2024 19 Mar 2024
10 th floor Level Brick Work 8 Dec 2023 30 Dec 2023 24 Dec 2023 15 Jan 2024 3 Jan 2024 25 Jan 2024
Casting 11 Sep 2023 5 Oct 2023 29 Sep 2023 21 Oct 2023 8 Oct 2023 7 Nov 2023
Inside Plaster 8 Jan 2024 30 Jan 2024 24 Jan 2024 15 Feb 2024 3 Feb 2024 25 Feb 2024
9th floor Level Brick Work 15 Nov 2023 7 Dec 2023 1 Dec 2023 23 Dec 2023 11 Dec 2023 2 Jan 2024
Casting 19 Aug 2023 10 Sep 2023 4 Sep 2023 28 Sep 2023 13 Sep 2023 7 Oct 2023
Inside Plaster 16 Dec 2023 7 Jan 2024 1 Jan 2024 23 Jan 2024 11 Jan 2024 2 Feb 2024
8th floor Level Brick Work 23 Oct 2023 14 Nov 2023 8 Nov 2023 30 Nov 2023 18 Nov 2023 10 Dec 2023
Casting 26 Jul 2023 18 Aug 2023 11 Aug 2023 3 Sep 2023 21 Aug 2023 12 Sep 2023
Inside Plaster 23 Nov 2023 15 Dec 2023 9 Dec 2023 31 Dec 2023 19 Dec 2023 10 Jan 2024
7th Floor Level Brick Work 30 Sep 2023 22 Oct 2023 16 Oct 2023 7 Nov 2023 26 Oct 2023 17 Nov 2023
Casting 23 Jun 2023 25 Jul 2023 19 Jul 2023 10 Aug 2023 28 Jul 2023 20 Aug 2023
Inside Plaster 31 Oct 2023 22 Nov 2023 16 Nov 2023 8 Dec 2023 26 Nov 2023 18 Dec 2023
6th Floor Level Brick Work 7 Sep 2023 29 Sep 2023 23 Sep 2023 15 Oct 2023 3 Oct 2023 25 Oct 2023
Casting 31 May 2023 22 Jun 2023 16 Jun 2023 18 Jul 2023 25 Jun 2023 27 Jul 2023
Inside Plaster 8 Oct 2023 30 Oct 2023 24 Oct 2023 15 Nov 2023 3 Nov 2023 25 Nov 2023
5th Floor Level Brick Work 15 Aug 2023 6 Sep 2023 31 Aug 2023 22 Sep 2023 10 Sep 2023 2 Oct 2023
Casting 8 May 2023 30 May 2023 24 May 2023 15 Jun 2023 2 Jun 2023 24 Jun 2023
Inside Plaster 15 Sep 2023 7 Oct 2023 1 Oct 2023 23 Oct 2023 11 Oct 2023 2 Nov 2023
4th Floor Level Brick Work 23 Jul 2023 14 Aug 2023 8 Aug 2023 30 Aug 2023 18 Aug 2023 9 Sep 2023
Casting 14 Apr 2023 7 May 2023 30 Apr 2023 23 May 2023 10 May 2023 1 Jun 2023
Inside Plaster 23 Aug 2023 14 Sep 2023 8 Sep 2023 30 Sep 2023 18 Sep 2023 10 Oct 2023
3rd Floor Level Brick Work 30 Jun 2023 22 Jul 2023 16 Jul 2023 7 Aug 2023 26 Jul 2023 17 Aug 2023
Casting 22 Mar 2023 13 Apr 2023 2 Apr 2023 29 Apr 2023 11 Apr 2023 9 May 2023
Inside Plaster 31 Jul 2023 22 Aug 2023 16 Aug 2023 7 Sep 2023 26 Aug 2023 17 Sep 2023
2nd Floor Level Brick Work 7 Jun 2023 29 Jun 2023 23 Jun 2023 15 Jul 2023 3 Jul 2023 25 Jul 2023
Casting 24 Feb 2023 21 Mar 2023 7 Mar 2023 1 Apr 2023 19 Mar 2023 10 Apr 2023
Inside Plaster 8 Jul 2023 30 Jul 2023 24 Jul 2023 15 Aug 2023 3 Aug 2023 25 Aug 2023
1st Floor Level Brick Work 15 May 2023 6 Jun 2023 31 May 2023 22 Jun 2023 10 Jun 2023 2 Jul 2023
Casting 1 Feb 2023 23 Feb 2023 12 Feb 2023 6 Mar 2023 21 Feb 2023 18 Mar 2023
Inside Plaster 7 Jun 2023 7 Jul 2023 23 Jun 2023 23 Jul 2023 3 Jul 2023 2 Aug 2023
Gr. Floor Level Brick Work 14 Apr 2023 14 May 2023 30 Apr 2023 30 May 2023 10 May 2023 9 Jun 2023
Casting 31 Dec 2022 31 Jan 2023 11 Jan 2023 11 Feb 2023 20 Jan 2023 20 Feb 2023
Deck Slab Level Casting 10 Nov 2022 30 Dec 2022 21 Nov 2022 10 Jan 2023 30 Nov 2022 19 Jan 2023
Basement Raft Casting 10 Oct 2022 9 Nov 2022 21 Oct 2022 20 Nov 2022 30 Oct 2022 29 Nov 2022
Note : The GFC drawings are required 30 days before starting of activity for planning, B.B.S. and arrangement.
Note : Plaster work starting date assumed completion of electrical work.
Hindrance register record to be mantained according as per actual on site.