The document outlines the proposed slab milestone dates for the Titanium Tech Park Project in Whitefield. It details 16 milestones for the completion of roof slabs from the basement 3 level through to the 12th floor. Each milestone lists the planned start and finish dates for its 4 pour sections, along with the duration in days to complete that stage of work. The contractor is Kalyani Developer and project management consultant is Sycone CPMC.
The document outlines the proposed slab milestone dates for the Titanium Tech Park Project in Whitefield. It details 16 milestones for the completion of roof slabs from the basement 3 level through to the 12th floor. Each milestone lists the planned start and finish dates for its 4 pour sections, along with the duration in days to complete that stage of work. The contractor is Kalyani Developer and project management consultant is Sycone CPMC.
The document outlines the proposed slab milestone dates for the Titanium Tech Park Project in Whitefield. It details 16 milestones for the completion of roof slabs from the basement 3 level through to the 12th floor. Each milestone lists the planned start and finish dates for its 4 pour sections, along with the duration in days to complete that stage of work. The contractor is Kalyani Developer and project management consultant is Sycone CPMC.
CONTRACTOR: KALYANI DEVELOPER PMC: SYCONE CPMC PROPOSED SLAB MILESTONE DATES Sr.No Activity Start Finish Duration 1 BASEMENT-3 ROOF SLAB 20 September 2022 23 November 2022 65 a Pour-1 27 September 2022 17 October 2022 21 b Pour-2 05 October 2022 24 October 2022 20 c Pour-3 28 October 2022 17 November 2022 21 d Pour-4 30 October 2022 19 November 2022 21 e Pour-5 25 October 2022 15 November 2022 22 f Pour-6 03 November 2022 23 November 2022 21 2 BASEMENT-2 ROOF SLAB 20 October 2022 13 December 2022 55 a Pour-1 20 October 2022 22 November 2022 34 b Pour-2 24 October 2022 24 November 2022 32 c Pour-3 17 November 2022 07 December 2022 21 d Pour-4 19 November 2022 09 December 2022 21 e Pour-5 15 November 2022 05 December 2022 21 f Pour-6 23 November 2022 13 December 2022 21 3 BASEMENT-1 ROOF SLAB 23 November 2022 03 January 2023 42 a Pour-1 23 November 2022 13 December 2022 21 b Pour-2 25 November 2022 15 December 2022 21 c Pour-3 08 December 2022 28 December 2022 21 d Pour-4 10 December 2022 30 December 2022 21 e Pour-5 06 December 2022 26 December 2022 21 f Pour-6 14 December 2022 03 January 2023 21 4 GROUND FLOOR ROOF SLAB 14 December 2022 24 January 2023 42 a Pour-1 14 December 2022 03 January 2023 21 b Pour-2 16 December 2022 05 January 2023 21 c Pour-3 29 December 2022 18 January 2023 21 d Pour-4 31 December 2022 20 January 2023 21 e Pour-5 27 December 2022 16 January 2023 21 f Pour-6 04 January 2023 24 January 2023 21 5 1ST FLOOR ROOF SLAB 08 January 2023 15 February 2023 39 a Pour-1 08 January 2023 02 February 2023 26 b Pour-2 10 January 2023 04 February 2023 26 c Pour-3 23 January 2023 13 February 2023 22 d Pour-4 25 January 2023 15 February 2023 22 6 2ND FLOOR ROOF SLAB 03 February 2023 08 March 2023 34 a Pour-1 03 February 2023 23 February 2023 21 b Pour-2 05 February 2023 25 February 2023 21 c Pour-3 14 February 2023 06 March 2023 21 d Pour-4 16 February 2023 08 March 2023 21 7 3RD FLOOR ROOF SLAB 24 February 2023 29 March 2023 34 a Pour-1 24 February 2023 16 March 2023 21 b Pour-2 26 February 2023 18 March 2023 21 c Pour-3 07 March 2023 27 March 2023 21 d Pour-4 09 March 2023 29 March 2023 21 8 4TH FLOOR ROOF SLAB 17 March 2023 19 April 2023 34 a Pour-1 17 March 2023 06 April 2023 21 b Pour-2 19 March 2023 08 April 2023 21 c Pour-3 28 March 2023 17 April 2023 21 d Pour-4 30 March 2023 19 April 2023 21 9 5th FLOOR ROOF SLAB 07 April 2023 10 May 2023 34 a Pour-1 07 April 2023 27 April 2023 21 b Pour-2 09 April 2023 29 April 2023 21 c Pour-3 18 April 2023 08 May 2023 21 d Pour-4 20 April 2023 10 May 2023 21 10 6th FLOOR ROOF SLAB 28 April 2023 31 May 2023 34 a Pour-1 28 April 2023 18 May 2023 21 b Pour-2 30 April 2023 20 May 2023 21 c Pour-3 09 May 2023 29 May 2023 21 d Pour-4 11 May 2023 31 May 2023 21 11 7th FLOOR ROOF SLAB 19 May 2023 21 June 2023 34 a Pour-1 19 May 2023 08 June 2023 21 b Pour-2 21 May 2023 10 June 2023 21 c Pour-3 30 May 2023 19 June 2023 21 d Pour-4 01 June 2023 21 June 2023 21 12 8th FLOOR ROOF SLAB 09 June 2023 12 July 2023 34 a Pour-1 09 June 2023 29 June 2023 21 b Pour-2 11 June 2023 01 July 2023 21 c Pour-3 20 June 2023 10 July 2023 21 d Pour-4 22 June 2023 12 July 2023 21 13 9th FLOOR ROOF SLAB 30 June 2023 02 August 2023 34 a Pour-1 30 June 2023 20 July 2023 21 b Pour-2 02 July 2023 22 July 2023 21 c Pour-3 11 July 2023 31 July 2023 21 d Pour-4 13 July 2023 02 August 2023 21 14 10th FLOOR ROOF SLAB 21 July 2023 23 August 2023 34 a Pour-1 21 July 2023 10 August 2023 21 b Pour-2 23 July 2023 12 August 2023 21 c Pour-3 01 August 2023 21 August 2023 21 d Pour-4 03 August 2023 23 August 2023 21 15 11th FLOOR ROOF SLAB 11 August 2023 13 September 2023 34 a Pour-1 11 August 2023 31 August 2023 21 b Pour-2 13 August 2023 02 September 2023 21 c Pour-3 22 August 2023 11 September 2023 21 d Pour-4 24 August 2023 13 September 2023 21 16 12th FLOOR ROOF SLAB 01 September 2023 04 October 2023 34 a Pour-1 01 September 2023 21 September 2023 21 b Pour-2 03 September 2023 23 September 2023 21 c Pour-3 12 September 2023 02 October 2023 21 d Pour-4 14 September 2023 04 October 2023 21 17 13th FLOOR ROOF SLAB 22 September 2023 25 October 2023 34 a Pour-1 22 September 2023 12 October 2023 21 b Pour-2 24 September 2023 14 October 2023 21 c Pour-3 03 October 2023 23 October 2023 21 d Pour-4 05 October 2023 25 October 2023 21 18 14th FLOOR ROOF SLAB 13 October 2023 15 November 2023 34 a Pour-5 13 October 2023 02 November 2023 21 b Pour-6 15 October 2023 04 November 2023 21 c Pour-7 24 October 2023 13 November 2023 21 d Pour-8 26 October 2023 15 November 2023 21 19 15th FLOOR ROOF SLAB 03 November 2023 06 December 2023 34 a Pour-9 03 November 2023 23 November 2023 21 b Pour-10 05 November 2023 25 November 2023 21 c Pour-11 14 November 2023 04 December 2023 21 d Pour-12 16 November 2023 06 December 2023 21 NOTE:- DATES ARE EXCLUDING POURSTIP CASTING DATE