标识号 任务模 Task Name Duration Round 开始时间 完成时间 2023

式 2022/7 2022/8 2022/9 2022/10 2022/11 2022/12


1 Pier Construction 571days 2022/8/12 2024/2/23
2 P421 32days 2022/8/12 2022/9/12
3 pier cap work 32days 2022/8/12 2022/9/12
4 P422 32days 2022/8/13 2022/9/13
5 pier cap work 32days 2022/8/13 2022/9/13
6 P423 32days 2022/8/22 2022/9/23
7 pier cap work 32days 2022/8/22 2022/9/23
8 P424 32days 2022/8/23 2022/9/24
9 pier cap work 32days 2022/8/23 2022/9/24
10 P425 32days 2022/9/13 2022/10/14
11 pier cap work 32days 2022/9/13 2022/10/14
12 P426 32days 2022/9/14 2022/10/15
13 pier cap work 32days 2022/9/14 2022/10/15
14 P427 32days 2022/9/24 2022/10/25
15 pier cap work 32days 2022/9/24 2022/10/25
16 P428 32days 2022/9/25 2022/10/26
17 pier cap work 32days 2022/9/25 2022/10/26
18 P441 32days 2022/10/15 2022/11/16
19 pier cap work 32days 2022/10/15 2022/11/16
20 P442 32days 2022/10/16 2022/11/17
21 pier cap work 32days 2022/10/16 2022/11/17
22 P443 32days 2022/10/26 2022/11/27

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 1
标识号 任务模 Task Name Duration Round 开始时间 完成时间 2023
式 2022/7 2022/8 2022/9 2022/10 2022/11 2022/12
23 pier cap work 32days 2022/10/26 2022/11/27
24 P444 32days 2022/10/27 2022/11/27
25 pier cap work 32days 2022/10/27 2022/11/27
26 P445 32days 2022/11/17 2022/12/18
27 pier cap work 32days 2022/11/17 2022/12/18
28 P446 32days 2022/11/18 2022/12/19
29 pier cap work 32days 2022/11/18 2022/12/19
30 P447 32days 2022/11/28 2022/12/29
31 pier cap work 32days 2022/11/28 2022/12/29
32 P448 32days 2022/11/29 2022/12/30
33 pier cap work 32days 2022/11/29 2022/12/30
34 P429 32days 2022/12/19 2023/1/20
35 pier cap work 32days 2022/12/19 2023/1/20
36 P430 32days 2022/12/20 2023/1/21
37 pier cap work 32days 2022/12/20 2023/1/21
38 P431 32days 2022/12/30 2023/1/30
39 pier cap work 32days 2022/12/30 2023/1/30
40 P432 32days 2022/12/31 2023/1/31
41 pier cap work 32days 2022/12/31 2023/1/31
42 P433 32days 2023/1/21 2023/2/21
43 pier cap work 32days 2023/1/21 2023/2/21
44 P434 32days 2023/1/22 2023/2/22

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 2
标识号 任务模 Task Name Duration Round 开始时间 完成时间 2023
式 2022/7 2022/8 2022/9 2022/10 2022/11 2022/12
45 pier cap work 32days 2023/1/22 2023/2/22
46 P435 32days 2023/1/31 2023/3/4
47 pier cap work 32days 2023/1/31 2023/3/4
48 P436 32days 2023/2/1 2023/3/5
49 pier cap work 32days 2023/2/1 2023/3/5
50 P437 32days 2023/2/22 2023/3/25
51 pier cap work 32days 2023/2/22 2023/3/25
52 P438 32days 2023/2/23 2023/3/26
53 pier cap work 32days 2023/2/23 2023/3/26
54 P439 32days 2023/3/5 2023/4/5
55 pier cap work 32days 2023/3/5 2023/4/5
56 P440 32days 2023/3/6 2023/4/6
57 pier cap work 32days 2023/3/6 2023/4/6
58 P449 32days 2023/3/26 2023/4/27
59 pier cap work 32days 2023/3/26 2023/4/27
60 P450 32days 2023/3/27 2023/4/28
61 pier cap work 32days 2023/3/27 2023/4/28
62 P451 32days 2023/4/6 2023/5/8
63 pier cap work 32days 2023/4/6 2023/5/8
64 P452 32days 2023/4/7 2023/5/9
65 pier cap work 32days 2023/4/7 2023/5/9
66 P453 32days 2023/4/28 2023/5/29

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 3
标识号 任务模 Task Name Duration Round 开始时间 完成时间 2023
式 2022/7 2022/8 2022/9 2022/10 2022/11 2022/12
67 pier cap work 32days 2023/4/28 2023/5/29
68 P454 32days 2023/4/29 2023/5/30
69 pier cap work 32days 2023/4/29 2023/5/30
70 P455 32days 2023/5/9 2023/6/9
71 pier cap work 32days 2023/5/9 2023/6/9
72 P456 32days 2023/5/10 2023/6/10
73 pier cap work 32days 2023/5/10 2023/6/10
74 P457 32days 2023/5/30 2023/7/1
75 pier cap work 32days 2023/5/30 2023/7/1
76 P458 32days 2023/5/31 2023/7/2
77 pier cap work 32days 2023/5/31 2023/7/2
78 P459 32days 2023/6/10 2023/7/11
79 pier cap work 32days 2023/6/10 2023/7/11
80 P460 32days 2023/6/11 2023/7/12
81 pier cap work 32days 2023/6/11 2023/7/12
82 P461 32days 2023/7/2 2023/8/2
83 pier cap work 32days 2023/7/2 2023/8/2
84 P462 32days 2023/7/3 2023/8/3
85 pier cap work 32days 2023/7/3 2023/8/3
86 P463 32days 2023/7/13 2023/8/13
87 pier cap work 32days 2023/7/13 2023/8/13
88 P464 32days 2023/7/14 2023/8/14

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 4
标识号 任务模 Task Name Duration Round 开始时间 完成时间 2023
式 2022/7 2022/8 2022/9 2022/10 2022/11 2022/12
89 pier cap work 32days 2023/7/14 2023/8/14
90 P465 32days 2023/8/3 2023/9/3
91 pier cap work 32days 2023/8/3 2023/9/3
92 P466 32days 2023/8/4 2023/9/4
93 pier cap work 32days 2023/8/4 2023/9/4
94 P467 32days 2023/8/14 2023/9/14
95 pier cap work 32days 2023/8/14 2023/9/14
96 P468 32days 2023/8/15 2023/9/15
97 pier cap work 32days 2023/8/15 2023/9/15
98 P469 32days 2023/9/5 2023/10/6
99 pier cap work 32days 2023/9/5 2023/10/6
100 P470 32days 2023/9/6 2023/10/7
101 pier cap work 32days 2023/9/6 2023/10/7
102 P471 32days 2023/9/15 2023/10/17
103 pier cap work 32days 2023/9/15 2023/10/17
104 P472 32days 2023/9/16 2023/10/18
105 pier cap work 32days 2023/9/16 2023/10/18
106 P473 32days 2023/10/7 2023/11/7
107 pier cap work 32days 2023/10/7 2023/11/7
108 P474 32days 2023/10/8 2023/11/8
109 pier cap work 32days 2023/10/8 2023/11/8
110 P475 32days 2023/10/18 2023/11/18

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 5
标识号 任务模 Task Name Duration Round 开始时间 完成时间 2023
式 2022/7 2022/8 2022/9 2022/10 2022/11 2022/12
111 pier cap work 32days 2023/10/18 2023/11/18
112 P476 32days 2023/10/19 2023/11/19
113 pier cap work 32days 2023/10/19 2023/11/19
114 P477 32days 2023/11/8 2023/12/10
115 pier cap work 32days 2023/11/8 2023/12/10
116 P478 32days 2023/11/9 2023/12/11
117 pier cap work 32days 2023/11/9 2023/12/11
118 P479 32days 2023/11/19 2023/12/21
119 pier cap work 32days 2023/11/19 2023/12/21
120 P480 32days 2023/11/20 2023/12/22
121 pier cap work 32days 2023/11/20 2023/12/22
122 P481 32days 2023/12/11 2024/1/11
123 pier cap work 32days 2023/12/11 2024/1/11
124 P482 32days 2023/12/12 2024/1/12
125 pier cap work 32days 2023/12/12 2024/1/12
126 P483 32days 2023/12/22 2024/1/22
127 pier cap work 32days 2023/12/22 2024/1/22
128 P484 32days 2023/12/23 2024/1/23
129 pier cap work 32days 2023/12/23 2024/1/23
130 P485 32days 2024/1/12 2024/2/13
131 pier cap work 32days 2024/1/12 2024/2/13
132 P486 32days 2024/1/13 2024/2/14

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 6
标识号 任务模 Task Name Duration Round 开始时间 完成时间 2023
式 2022/7 2022/8 2022/9 2022/10 2022/11 2022/12
133 pier cap work 32days 2024/1/13 2024/2/14
134 P486 32days 2024/1/23 2024/2/23
135 pier cap work 32days 2024/1/23 2024/2/23

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 7
2023 2024
2023/1 2023/2 2023/3 2023/4 2023/5 2023/6 2023/7 2023/8 2023/9 2023/10 2023/11 2023/12 2024/1 2024/2 2024/3

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 8
2023 2024
2023/1 2023/2 2023/3 2023/4 2023/5 2023/6 2023/7 2023/8 2023/9 2023/10 2023/11 2023/12 2024/1 2024/2 2024/3

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 9
2023 2024
2023/1 2023/2 2023/3 2023/4 2023/5 2023/6 2023/7 2023/8 2023/9 2023/10 2023/11 2023/12 2024/1 2024/2 2024/3

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 10
2023 2024
2023/1 2023/2 2023/3 2023/4 2023/5 2023/6 2023/7 2023/8 2023/9 2023/10 2023/11 2023/12 2024/1 2024/2 2024/3

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 11
2023 2024
2023/1 2023/2 2023/3 2023/4 2023/5 2023/6 2023/7 2023/8 2023/9 2023/10 2023/11 2023/12 2024/1 2024/2 2024/3

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 12
2023 2024
2023/1 2023/2 2023/3 2023/4 2023/5 2023/6 2023/7 2023/8 2023/9 2023/10 2023/11 2023/12 2024/1 2024/2 2024/3

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 13
2023 2024
2023/1 2023/2 2023/3 2023/4 2023/5 2023/6 2023/7 2023/8 2023/9 2023/10 2023/11 2023/12 2024/1 2024/2 2024/3

Task Inactive Milestone Finish-only

Color1 Inactive Summary External Tasks

Split Manual Task External Milestone


Project: June.18.22 (2) 13+500-
Milestone Duration-only Deadline
Date: 2022/6/20
Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Page 14

You might also like