ID Task Task Name Duration Start Finish Predecessors

2022 2023 2024 2025 2026


Mode Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
1 PROPOSED 782 days Tue 1/11/22 Wed
DESIGN,BUILD 29/10/25
2 Start Project 0 days Tue 1/11/22 Tue 1/11/22 1/11
3 2.0 Preliminaries 730 days Tue 1/11/22 Mon
and Turnkey 18/8/25
4 Elements
Site survey & setting 28 days Wed 2/11/22Fri 9/12/22
5 2.1 Site Survey 14 days Wed 2/11/22Mon 21/11/22
6 2.2 Setting Out 14 days Wed 2/11/22Mon 21/11/22
7 2.3 Project Signboard 14 days Thu 3/11/22 Tue 22/11/22
8 2.4 Construction 7 days Tue 1/11/22 Wed
Planning 9/11/22
9 Office Equipment 14 days Tue Fri 2/12/22
and Facilities 15/11/22
10 2.5 PPE 7 days Tue 15/11/22Wed 23/11/22
11 2.6 Fire extinguisher 7 days Tue 15/11/22Wed 23/11/22
12 2.7 PC, printers & 7 days Tue Wed
table and chair 15/11/22 23/11/22
13 2.8 Consumables 7 days Tue 15/11/22Wed 23/11/22
14 2.9 Transportation 14 days Tue 15/11/22Fri 2/12/22
15 2.10 Site diary 4 days Sat 19/11/22 Wed 23/11/22
16 Environmental 14 days Tue Fri 2/12/22
Management 15/11/22
17 During Project 567 days Wed 2/11/22Thu 2/1/25
18 2.12 Material testing 567 days Wed 2/11/22Thu 2/1/25
19 2.13 Shop drawing 548 days Tue 15/11/22Thu 19/12/24
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CPM
Summary Manual Summary Rollup Progress
Date: Fri 20/1/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors
2022 2023 2024 2025 2026
Mode Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
20 2.14 Inspection, & test548 days Tue 15/11/22Thu 19/12/24
21 2.15 Contractors plan548 days Tue 15/11/22Thu 19/12/24
22 2.16 Hoarding 460 days Tue 15/11/22Mon 19/8/24
23 2.17 Progress 460 days Tue Mon
photographs 15/11/22 19/8/24
24 2.18 Temporary 455 days Wed Tue 30/7/24
Water and Power 2/11/22
25 Supply
2.19 Temporary 459 days Wed Mon 5/8/24
Access Road to 2/11/22
Construction Access
26 2.20 Temporary div 455 days Wed 2/11/22Tue 30/7/24
27 2.21 Contractors teams 459 days Wed 2/11/22Mon 5/8/24
28 2.22 Contractors officer
459 days Wed 2/11/22Mon 5/8/24
29 2.23 Communcation 459 days Thu Tue 13/8/24
System 10/11/22
30 2.24 Safety,health, 459 days Wed Mon 5/8/24
welfare 2/11/22
31 2.25 Sanitation 459 days Wed 2/11/22Mon 5/8/24
32 2.26 M&E Coordinater455 days Wed 2/11/22Tue 30/7/24
33 2.27 Quality Assurance455 days Wed 2/11/22Tue 30/7/24
34 Final project 20 days Wed 4/1/23 Tue 31/1/23
35 2.28 As-built drawing 14 days Wed 4/1/23 Mon 23/1/23
36 2.29 Cleaning, clearing7 days Sat 21/1/23 Mon 30/1/23
37 3.0 EARTHWORK 52 days Thu 24/11/22Fri 3/2/23
38 3.1 Site clearing 10 days Fri 30/12/22 Thu 12/1/23
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CPM
Summary Manual Summary Rollup Progress
Date: Fri 20/1/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors
2022 2023 2024 2025 2026
Mode Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
39 3.2 Excavation 15 days Fri 30/12/22 Thu 19/1/23
40 3.3 Filling 15 days Thu 2/2/23 Wed 22/2/23
41 3.4 Levelling 24 days Sun 1/1/23 Wed 1/2/23
42 Temporary Works 52 days Thu 24/11/22Fri 3/2/23
43 3.5 Silt Trap 14 days Wed 28/12/22Mon 16/1/23
44 3.6 Wash Trough 14 days Thu 8/12/22 Tue 27/12/22
45 3.7 Temporary earth 14 days Sun 8/1/23 Wed
drain 25/1/23
46 3.8 Earth sump 14 days Sun 8/1/23 Wed 25/1/23
47 3.9 FDT 14 days Sun 8/1/23 Wed 25/1/23
48 3.10 Silt fence 14 days Sun 8/1/23 Wed 25/1/23
49 3.11 Check dam 14 days Thu 28/12/23Tue 16/1/24
50 3.12 Temporary precast
14 days Sun 15/1/23 Wed 1/2/23
51 3.13 Precast concrete14 days Thu 26/1/23 Tue 14/2/23
52 3.14 RC sump 7 days Sun 15/1/23 Mon 23/1/23
53 3.15 MS Grating 7 days Thu 26/1/23 Fri 3/2/23
54 4.0 BUILDING WORKS782 days Tue 1/11/22 Wed 29/10/25
55 STUDENT AFFAIRS 782 days Tue 1/11/22 Wed
BUILDING 29/10/25
56 4.1 Foundation 50 days Fri 6/1/23 Thu 16/3/23
57 4.2 Ground beam 50 days Fri 17/3/23 Thu 25/5/23
58 4.3 Anti termite 50 days Fri 26/5/23 Thu 3/8/23
treatment

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CPM
Summary Manual Summary Rollup Progress
Date: Fri 20/1/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Predecessors
2022 2023 2024 2025 2026
Mode Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
59 4.4 Ground floor 50 days Sun 2/7/23 Thu 7/9/23
column
60 4.5 First floor beam 50 days Sun 10/9/23 Thu 16/11/23
61 4.6 First floor slab 50 days Sun 19/11/23Thu 25/1/24
62 4.7 Roof beam 50 days Sun 28/1/24 Thu 4/4/24
63 4.8 Roof frame 50 days Mon 8/4/24 Fri 14/6/24
64 4.9 Roof tiles 50 days Mon 17/6/24Fri 23/8/24
65 4.10 Brickwork 50 days Mon 26/8/24Fri 1/11/24
66 4.11 Staircase 50 days Mon 26/8/24Fri 1/11/24
67 4.12 Window 40 days Mon 4/11/24Fri 27/12/24
68 4.13 Plastering 50 days Mon 4/11/24Fri 10/1/25
69 4.14 Skim coat 40 days Mon 4/11/24Fri 27/12/24
70 4.15 Door leaves 30 days Mon 4/11/24Fri 13/12/24
71 4.16 External ceiling 50 days Tue Mon
finishes 17/12/24 24/2/25
72 4.17 Internal ceiling 50 days Wed Tue 25/2/25
finishes 18/12/24
73 4.18 Painting 50 days Sun 23/2/25 Thu 1/5/25
74 5.0 EXTERNAL WORK 239 days Tue 29/11/22Fri 27/10/23
75 5.1 Water Supply 73 days Fri 29/11/24 Tue 11/3/25
76 5.2 Drainage 171 days Sat 30/11/24 Fri 25/7/25
77 5.3 Brick fence 64 days Sat 4/1/25 Wed 2/4/25
78 5.4 Sewer 64 days Fri 29/11/24 Wed 26/2/25
79 5.5 Pavement road 233 days Sat 30/11/24 Tue 21/10/25

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CPM
Summary Manual Summary Rollup Progress
Date: Fri 20/1/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Task Name Duration Start Finish Predecessors
2022 2023 2024 2025 2026
Mode Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
80 5.6 Grass planting work
56 days Tue 25/2/25 Tue 13/5/25
81 5.7 Rainwater 21 days Tue 25/2/25 Tue 25/3/25
Harvestor
82 6.0 MECHANICAL 88 days Sun Tue 11/2/25
WORK 13/10/24
83 6.1 Ventilation 20 days Sun 13/10/24Thu 7/11/24
84 6.2 Plumbing 30 days Sat 14/12/24 Thu 23/1/25
85 6.3 Energy-efficiency 20 days Sun 13/10/24Thu 7/11/24
86 6.4 Others 18 days Sun 19/1/25 Tue 11/2/25
87 7.0 ELECTRICAL 89 days Thu 13/2/25 Tue 17/6/25
WORKS
88 7.1 Power Substation 20 days Thu 13/2/25 Wed 12/3/25
89 7.2 Internal lighting 20 days Sat 19/4/25 Thu 15/5/25
90 7.3 Sound system 20 days Thu 2/5/24 Wed 29/5/24
91 7.4 Video surveillance20 days Thu 13/2/25 Wed 12/3/25
92 7.5 Others 9 days Thu 5/6/25 Tue 17/6/25
93 8.0 LANDSCAPPING 60 days Sat 14/6/25 Thu 4/9/25
WORKS
94 8.1 Outdoor furniture15 days Sat 14/6/25 Thu 3/7/25
95 8.2 Paving 15 days Sun 13/7/25 Thu 31/7/25
96 8.3 Driveways 15 days Sun 3/8/25 Thu 21/8/25
97 8.4 Vegetations 15 days Fri 15/8/25 Thu 4/9/25
98 9.0 PRIME COST SUM254 days Sat 9/11/24 Wed 29/10/25

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CPM
Summary Manual Summary Rollup Progress
Date: Fri 20/1/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task Task Name Duration Start Finish Predecessors
2022 2023 2024 2025 2026
Mode Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
99 9.1 Air-conditioner 160 days Sun Thu 31/7/25
System 22/12/24
100 9.2 Fire Prevention 160 days Sun Thu 31/7/25
System 22/12/24
101 9.3 Building Automatic160 days Sun 22/12/24Thu 31/7/25
102 9.4 LV Electrical & 170 days Sun Thu 7/8/25
Standby Generator 15/12/24
103 9.5 HT Electrical System
170 days Sun 15/12/24Thu 7/8/25
104 9.6 ELV System 170 days Sun 15/12/24Thu 7/8/25
105 9.7 ICT System 170 days Sat 9/11/24 Thu 3/7/25
106 9.8 Testing & 30 days Fri 19/9/25 Thu
Comissioning 30/10/25
107 END PROJECT 0 days Wed 29/10/25Wed 29/10/25 29/10

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CPM
Summary Manual Summary Rollup Progress
Date: Fri 20/1/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6