ID Task Name Duration Start Finish Predecessors

October 2022 November 2022 December 2022


13 18 23 28 2 7 12 17 22 27 2 7
1 1. define specification 20 days Thu 10/20/22Wed 11/16/22
2 1.1 identify customer 2 days Thu 10/20/22Fri 10/21/22
3 1.2 interview 10 customer 10 days Mon 10/24/22Fri 11/4/22 2
4 1.3 interpret product 3 days Mon 11/7/22Wed 11/9/223
5 1.4 benchmaert product 4 days Thu 11/10/22Tue 11/15/224
6 1.5 define target pds 1 day Wed 11/16/22Wed 11/16/225
7 1.6 target pds released 1 day Thu 11/17/22Thu 11/17/226
8 2. generate concept 2 days Thu 10/20/22Fri 10/21/22
9 2.1 review comp product 2 days Thu 11/17/22Fri 11/18/22 6
10 2.2 search patents 3 days Fri 11/18/22 Tue 11/22/22
11 2.3 braintorm concept 3 days Mon 10/24/22Wed 10/26/22
12 3. select top 2 concept 2 days Mon 11/21/22Tue 11/22/229
13 4 mq presented 2 days Wed 11/23/22Thu 11/24/2210
14 5. profile motor power 24 days Thu 10/27/22Tue 11/29/22
15 5.1 design test stand 5 days Thu 10/27/22Wed 11/2/2211
16 5.2 build test stand 5 days Wed 11/23/22Tue 11/29/2212

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Wed 10/19/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1

You might also like