ID Task Name Duration Start Finish % Complete '22 Sep '22 Oct '22 Nov '22 Dec '22

07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04
1 FLEXIBLE JOINT ‐ NK KSO BBB 46 days? 21/09/22 23/11/22 46%
2 Pre‐Production 14 days 26/08/22 14/09/22 100%
3 Approval Calculation EJMA 1 day 14/09/22 14/09/22 100% 14/09
4 Approval General Arrangement Draw 1 day 14/09/22 14/09/22 100% 14/09
5 Material Section 4 days 21/09/22 26/09/22 100%
6 Inventory Material 4 days 21/09/22 26/09/22 100%
7 Production Process 15 days 27/09/22 17/10/22 100%
8 Bellow Roll Forming 4 days 27/09/22 30/09/22 100%
9 Weaving Wire Braiding 5 days 03/10/22 07/10/22 100%
10 Cutting Tubes to Production Length 3 days 10/10/22 12/10/22 100%
11 Assembly Welding & Crimping 3 days 13/10/22 17/10/22 100%
12 Inspection and Test 2 days 18/10/22 19/10/22 28% 19/10
13 Visual Inspection 1 day 18/10/22 18/10/22 70%
14 Dimension Inspection 1 day 18/10/22 18/10/22 15%
15 Hydropressure Test 1 day 19/10/22 19/10/22 0%
16 Final Production 3 days 20/10/22 24/10/22 0% 24/10
17 Final Inspection 1 day 20/10/22 20/10/22 0%
18 Packing Process 1 day 21/10/22 21/10/22 0%
19 Documentation Check 1 day 24/10/22 24/10/22 0%
20 QC Check 1 day 24/10/22 24/10/22 0%
21 Delivery Shiping 17 days 25/10/22 16/11/22 0%
22 Estimated Delivery fom Manufacture 2 days 26/10/22 27/10/22 0%
23 Estimated Departure Shipping 14 days 27/10/22 15/11/22 0%
24 ETA to Jakarta 1 day 16/11/22 16/11/22 0% 16/11
25 FAT 2 days 22/11/22 23/11/22 0% 23/11
26 Dimension Check 1 day 22/11/22 22/11/22 0%
27 Visual Check 1 day 22/11/22 22/11/22 0%
28 Hydropressure Test 1 day 23/11/22 23/11/22 0%

Task Inactive Milestone Start-only Baseline Milestone

Split Inactive Summary Finish-only Baseline Summary


Project:
Milestone Manual Task External Tasks Progress
NK - FLEXIBLE JOINT PROJECT
Date: 10/10/22 Summary Duration-only External Milestone Manual Progress

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Baseline