2 Project Start Date 189 days? Tue 22/05/17 Fri 23/02/03 84%
3 Receive letter of intent 0 days Tue 22/05/17 Tue 22/05/17 100% 05/17
4 Conduct kick-off meeting 0 days Fri 22/05/20 Fri 22/05/20 100% 3 05/20
5 Receive officail order 0 days Fri 22/05/27 Fri 22/05/27 100% 05/27
6 Preliminary Project Tasks 35 days Fri 22/05/20 Thu 22/07/07 100%
7 Submit General Arrangement drawing for approval 1.2 wks Fri 22/05/20 Fri 22/05/27 100% 4
8 Received feedback/approval of General Arrangement drawing2 wks Mon 22/05/30 Fri 22/06/10 100% 7
9 Receive vendor print index schedule (VPIS) for review 1 wk Fri 22/05/20 Thu 22/05/26 100% 4
10 Receive feedback on submitted VPIS 2 wks Fri 22/05/27 Thu 22/06/09 100% 9
11 Submit QC docs for review and approval 2 wks Fri 22/06/10 Thu 22/06/23 100% 10
16 Procurement and Fabrication 163 days? Fri 22/06/10 Tue 23/01/24 84%
17 Gear Reducers 161 days Fri 22/06/10 Fri 23/01/20 75% ASA
43 <New Task> 0%
44 Rubber lining 4 wks Tue 22/12/13 Mon 23/01/09 0% 42
51 Fit mounting bases and removable couplings to gearboxes 1 wk Mon 23/01/23 Fri 23/01/27 0% 19,22,26,30
56 Collect items from Afromix 1 day Fri 23/02/03 Fri 23/02/03 0% 53,54 02/03
57
58 Milstone Payments 181 days Fri 22/05/27 Fri 23/02/03 0%
59 10% on Order Placement 0 days Fri 22/05/27 Fri 22/05/27 100% 5 05/27
60 30% on approval of General Arrangement drawing 0 days Fri 22/06/10 Fri 22/06/10 0% 8 06/10
61 30% on receipt of Major Component 0 days Fri 22/09/02 Fri 22/09/02 0% 24,28,32,40 09/02
62 20% on advise that good are ready for collection 0 days Mon 23/01/30 Mon 23/01/30 0% 52 01/30
63 10% on approval of Retention bond 0 days Fri 23/02/03 Fri 23/02/03 0% 56 02/03
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Manual Progress
Project: Endevour Mining - PT Gre
Date: Mon 22/11/28 Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress