GGT Doc No : 4020-001A-VD-001 2040-V5008-SCH-001 - 111392-02 - Lycopodium - Manufacturing Schedule

ID Task Name Rev.2 Duration Start Finish % Predecessors


Complete '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '23 Jan '23 Feb '23 Mar '23 Apr '23 May
08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14
1 PT Greengold - Manufacturing Schedule - Rev. A 189 days? Tue 22/05/17 Fri 23/02/03 84%

2 Project Start Date 189 days? Tue 22/05/17 Fri 23/02/03 84%

3 Receive letter of intent 0 days Tue 22/05/17 Tue 22/05/17 100% 05/17
4 Conduct kick-off meeting 0 days Fri 22/05/20 Fri 22/05/20 100% 3 05/20
5 Receive officail order 0 days Fri 22/05/27 Fri 22/05/27 100% 05/27
6 Preliminary Project Tasks 35 days Fri 22/05/20 Thu 22/07/07 100%

7 Submit General Arrangement drawing for approval 1.2 wks Fri 22/05/20 Fri 22/05/27 100% 4

8 Received feedback/approval of General Arrangement drawing2 wks Mon 22/05/30 Fri 22/06/10 100% 7

9 Receive vendor print index schedule (VPIS) for review 1 wk Fri 22/05/20 Thu 22/05/26 100% 4

10 Receive feedback on submitted VPIS 2 wks Fri 22/05/27 Thu 22/06/09 100% 9

11 Submit QC docs for review and approval 2 wks Fri 22/06/10 Thu 22/06/23 100% 10

12 Receive approval of QC docs 2 wks Fri 22/06/24 Thu 22/07/07 100% 11

13 Post GA approval tasks 34 wks? Fri 22/06/10 Thu 23/02/02 83%

14 Drawings 20 days Mon 22/06/13 Fri 22/07/08 100%

15 Generate Fabrication Drawings 4 wks Mon 22/06/13 Fri 22/07/08 100% 8

16 Procurement and Fabrication 163 days? Fri 22/06/10 Tue 23/01/24 84%

17 Gear Reducers 161 days Fri 22/06/10 Fri 23/01/20 75% ASA

18 Order unit 1 day Fri 22/06/10 Fri 22/06/10 100% 10

19 Delivery to Afromix 32 wks Mon 22/06/13 Fri 23/01/20 75% 8 29/11/2022

20 Electric Motors 131 days Fri 22/06/10 Fri 22/12/09 93%

21 Order unit 1 day Fri 22/06/10 Fri 22/06/10 100% 10

22 Delivery to Afromix 26 wks Mon 22/06/13 Fri 22/12/09 93% 8

23 Removable Couplings 111 days Mon 22/07/11 Mon 22/12/12 93%

24 Material procurement 8 wks Mon 22/07/11 Fri 22/09/02 100% 15

25 Fabrication 14 wks Mon 22/09/05 Fri 22/12/09 90% 24

26 Delivery to Afromix 1 day Mon 22/12/12 Mon 22/12/12 0% 25

27 Mounting Bases 111 days Mon 22/07/11 Mon 22/12/12 93%

28 Material procurement 8 wks Mon 22/07/11 Fri 22/09/02 100% 15

29 Fabrication 14 wks Mon 22/09/05 Fri 22/12/09 90% 28

30 Delivery to Afromix 1 day Mon 22/12/12 Mon 22/12/12 0% 29

31 Shafts 142 days Mon 22/07/11 Tue 23/01/24 73%

32 Material procurement 8 wks Mon 22/07/11 Fri 22/09/02 100% 15

33 Fabrication 14 wks Mon 22/09/05 Fri 22/12/09 90% 32

34 Pre-shutdown rubber lining 1 wk Mon 22/12/12 Fri 22/12/16 0% 33

35 December shut down period 3 wks Mon 22/12/19 Fri 23/01/06 0% 34

36 Rubber lining 2 wks Mon 23/01/09 Fri 23/01/20 0% 35

37 Post-rubber inspection 1 day Mon 23/01/23 Mon 23/01/23 0% 36

38 Delivery to Afromix 1 day Tue 23/01/24 Tue 23/01/24 0% 37

39 Impeller Blades 133 days? Mon 22/07/11 Wed 23/01/11 77%

40 Material procurement 8 wks Mon 22/07/11 Fri 22/09/02 100% 15

41 Fabrication 14 wks Mon 22/09/05 Fri 22/12/09 90% 40

42 <New Task> 1 day? Mon 22/12/12 Mon 22/12/12 0% 41

43 <New Task> 0%
44 Rubber lining 4 wks Tue 22/12/13 Mon 23/01/09 0% 42

45 Post-rubber inspection 1 day Tue 23/01/10 Tue 23/01/10 0% 44

46 Delivery to Afromix 1 day Wed 23/01/11 Wed 23/01/11 0% 45

47 Fasteners 51 days Mon 22/07/11 Mon 22/09/19 100%

48 Order required fasteners 1 day Mon 22/07/11 Mon 22/07/11 100% 15

49 Delivery to Afromix 10 wks Tue 22/07/12 Mon 22/09/19 100% 48

50 Packaging & Inspection 9 days Mon 23/01/23 Thu 23/02/02 0%

51 Fit mounting bases and removable couplings to gearboxes 1 wk Mon 23/01/23 Fri 23/01/27 0% 19,22,26,30

52 Final Inspection release 1 day Mon 23/01/30 Mon 23/01/30 0% 51,38,46,49

53 Package Drive Units 3 days Tue 23/01/31 Thu 23/02/02 0% 52 02/02


54 Package shafts and blades 3 days Tue 23/01/31 Thu 23/02/02 0% 52 02/02
55 Collection of units 1 day Fri 23/02/03 Fri 23/02/03 0%

56 Collect items from Afromix 1 day Fri 23/02/03 Fri 23/02/03 0% 53,54 02/03
57
58 Milstone Payments 181 days Fri 22/05/27 Fri 23/02/03 0%

59 10% on Order Placement 0 days Fri 22/05/27 Fri 22/05/27 100% 5 05/27
60 30% on approval of General Arrangement drawing 0 days Fri 22/06/10 Fri 22/06/10 0% 8 06/10
61 30% on receipt of Major Component 0 days Fri 22/09/02 Fri 22/09/02 0% 24,28,32,40 09/02
62 20% on advise that good are ready for collection 0 days Mon 23/01/30 Mon 23/01/30 0% 52 01/30
63 10% on approval of Retention bond 0 days Fri 23/02/03 Fri 23/02/03 0% 56 02/03

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Manual Progress
Project: Endevour Mining - PT Gre
Date: Mon 22/11/28 Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 1