ID Task Task Name Duration Start Finish % Complete

Mode Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
1 Ansamblu rezidential NOVUM VIILOR-bloc A 145 days Mon 11/10/21 Mon 28/03/22 87%
2 anunt incepere lucrari Primarie Sector 5 3 days Mon 18/10/21 Wed 20/10/21 100%
3 anunt incepere lucrari ISC 3 days Wed 20/10/21 Fri 22/10/21 100%
4 proces verbal trasare limita proprietate 1 day Mon 08/11/21 Mon 08/11/21 100%
5 Organizarea de santier 94 days Mon 11/10/21 Thu 27/01/22 100%
57 Infrastructura 100 days Mon 08/11/21 Thu 03/03/22 100%
58 sapatura plot -4.25- 4.95 faza 1 21 days Mon 08/11/21 Wed 01/12/21 100%
70 sapatura plot -5.25 faza 1 31 days Fri 03/12/21 Fri 07/01/22 100%
83 armare radier zona bloc A zona -4.25- 4.95 24 days Mon 22/11/21 Sat 18/12/21 100%
93 instalatii radier zona bloc A 26 days Wed 24/11/21 Thu 23/12/21 100%
103 cofrare radier zona bloc A ( inclusiv base) 5 days Thu 16/12/21 Tue 21/12/21 100%
106 radier zona bloc A si parcare subterana 50 days Mon 22/11/21 Tue 18/01/22 100%
134 Verticale subsol parcare subterana 53 days Tue 21/12/21 Sat 19/02/22 100%
154 Placa peste subsol corp A si parcare subterana
16 days Mon 14/02/22 Thu 03/03/22 100%
164 Lucrari de incinta 39 days Mon 31/01/22 Wed 16/03/22 92%
178 Hidroizolatie pereti subsol 27 days Mon 14/02/22 Wed 16/03/22 67%
187 Bransament apa-canal faza 1 (interior proprietate)
20 days Mon 21/02/22 Tue 15/03/22 4%
197 Verticale parter bloc A 10 days Wed 02/03/22 Sat 12/03/22 13%
202 Umplutura pamant bloc A si parcare subterana19 days Mon 07/03/22 Mon 28/03/22 0%