OT Program on Outstanding Works REV1

ID TaskTask Name Duration Start Finish % Complete


Mode
21 January 1 May 11 August 21 November 1 March
6/2 27/3 15/5 3/7 21/8 9/10 27/11 15/1 5/3
1 9117 ZAMBEZI FACTORY 79 days Mon 17/10/22 Fri 27/1/23 10% 10%
2 Slab 8 days Mon 17/10/22 Wed 26/10/22 59%
3 Ramps 5 days Mon 17/10/22 Fri 21/10/22 100% 100%
4 Cable trench 7 days Mon 17/10/22 Tue 25/10/22 44% 44%
5 Srip top layer 100mm and compact 3 days Mon 17/10/22 Wed 19/10/22 100% 100%
6 Concrete to bottom layer 3 days Mon 17/10/22 Wed 19/10/22 90% 90%
7 Concrete to sidewalls and steel frame
7 days Mon 17/10/22 Tue 25/10/22 0% 0%
8 Mechanical and Electrical Installations 29 days Tue 25/10/22 Fri 2/12/22 18%
9 Mech & Elec First Fixtures 4 days Tue 25/10/22 Fri 28/10/22 50% 50%
10 Mech & Elec Second Fixtures 7 days Tue 25/10/22 Wed 2/11/22 0% 0%
11 Ablution facilities 14 days Mon 17/10/22 Thu 3/11/22 15%
12 Super-structure 8 days Mon 17/10/22 Wed 26/10/22 23%
13 Brickwork 7 days Mon 17/10/22 Tue 25/10/22 95% 95%
14 Plastering and skim 5 days Fri 21/10/22 Thu 27/10/22 0% 0%
15 Windows and door installation 3 days Fri 28/10/22 Tue 1/11/22 0% 0%
16 Truss installations 4 days Fri 21/10/22 Wed 26/10/22 0% 0%
17 Roof covering 5 days Thu 27/10/22 Wed 2/11/22 0% 0%
18 40mm floor screed 5 days Fri 28/10/22 Thu 3/11/22 0% 0%
19 Building Services 10 days Thu 3/11/22 Wed 16/11/22 27%
20 Plumbing 8 days Thu 3/11/22 Mon 14/11/22 25% 25%
21 Electricals 4 days Thu 3/11/22 Tue 8/11/22 30% 30%
22 Finishes 14 days Thu 3/11/22 Tue 22/11/22 0%
23 Ceilings 10 days Thu 3/11/22 Wed 16/11/22 0% 0%
24 Tiling 7 days Thu 3/11/22 Fri 11/11/22 0% 0%
25 Painting 4 days Thu 3/11/22 Tue 8/11/22 0% 0%
26 INT doors and locksets 4 days Thu 3/11/22 Tue 8/11/22 0% 0%
27 Installation and of Resin Bolt Line 16 days Sat 3/12/22 Fri 23/12/22 0% 0%
28 Commissioning of Resin Bolt Line 1 day Fri 23/12/22 Fri 23/12/22 0% 0%
29 External Works 34 days Fri 9/12/22 Thu 19/1/23 0%
30 Access Road Construction 30 days Fri 9/12/22 Fri 13/1/23 0% 0%
31 Site Paving and Driveway 20 days Fri 9/12/22 Sun 1/1/23 0% 0%
32 Workshop 14 days Fri 9/12/22 Mon 26/12/22 0% 0%
33 Canteen 26 days Fri 9/12/22 Mon 9/1/23 0% 0%
34 Sub-structure 6 days Fri 9/12/22 Fri 16/12/22 0% 0%
35 Super-structure 14 days Mon 12/12/22 Tue 27/12/22 0% 0%
36 Building Services 9 days Tue 20/12/22 Wed 28/12/22 0% 0%
37 Finishes 10 days Thu 29/12/22 Mon 9/1/23 0% 0%
38 Housekeeping 5 days Mon 2/1/23 Fri 6/1/23 0% 0%
39 Installation of Overhead Crane 11 days Wed 11/1/23 Wed 25/1/23 0% 0%
40 Project Close out (Handover) 2 days Thu 26/1/23 Fri 27/1/23 0% 0%

Critical Task Progress Baseline Summary Inactive Task


Critical Split Manual Task Baseline Split Manual Summary Inactive Milestone
Critical Progress Start-only Baseline Milestone Project Summary Inactive Summary
Task Finish-only Milestone External Tasks Deadline
Split Duration-only Summary Progress External Milestone