SCHEDULE 6A.

mpp
ID Task Task Name Duration Start Finish Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021
Mode Jun Jul Aug Sep Oct Nov Dec Jan
0 SCHEDULE 6A 426 days Wed 01/07/20Wed 16/02/22
1 PEMBERSIHAN TEMPAT KERJA 426 days Wed 01/07/20 Wed 16/02/22
8 PEKERJAAB PERSIAPAN 60 days Fri 31/07/20 Thu 22/10/20 29%
9 Pembersihan Tempat Kerja 60 days Fri 31/07/20 Thu 22/10/20 50%
10 Pemotongan Pohon, dia. 30 cm - 50 cm 15 days Fri 31/07/20 Thu 20/08/20 0%
11 Pemotongan Pohon, dia. >50 cm - 75 cm 15 days Fri 31/07/20 Thu 20/08/20 0%
12 Pemotongan Pohon, dia. >75 cm 15 days Fri 31/07/20 Thu 20/08/20 0%
13 PEMBONGKARAN 15 days Fri 31/07/20 Thu 20/08/20 0%
14 Pembongkaran Pasangan Batu atau Struktur Beton 15 days Fri 31/07/20 Thu 20/08/20 0%
15 Pembongkaran Kerb 15 days Fri 31/07/20 Thu 20/08/20 0%
16 Pembongkaran Perkerasan Jalan Aspal atau Beton 15 days Fri 31/07/20 Thu 20/08/20 0%
17 Pembongkaran Rambu Lalu Lintas 15 days Fri 31/07/20 Thu 20/08/20 0%
18 Pembongkaran Rumah 15 days Fri 31/07/20 Thu 20/08/20 0%
19 PENGADAAN 133 days Wed 22/07/20 Fri 22/01/21 67%
32 PEKERJAAN UNDERPASS BRIDGE 54+525 97 days Wed 22/07/20 Thu 03/12/20 0%
33 UNDERPASS 1 92 days Wed 22/07/20 Thu 26/11/20 0%
34 JEMBATAN SUNGAI CIPELANG A 120 days Wed 22/07/20 Tue 05/01/21 10%
35 UNDERPASS 2 92 days Wed 22/07/20 Thu 26/11/20 0%
36 PEKERJAAN UNDERPASS BRIDGE 120 days Wed 22/07/20 Tue 05/01/21 0%
37 JEMBATAN SUNGAI CIPELANG B 120 days Wed 22/07/20 Tue 05/01/21 0%
38 PEKERJAAN PERKERASAN DAN UTILITAS MAIN ROAD 355 days Sun 20/09/20 Fri 28/01/22

57 AKSES UJUNG JAYA 333 days Wed 22/07/20 Fri 29/10/21


80 PLAXA TOL DAN FASILITAS KANTOR 120 days Fri 22/01/21 Thu 08/07/21
83 DEMOBILISASI 14 days Tue 11/01/22 Fri 28/01/22
84 PHO 0 days Fri 28/01/22 Fri 28/01/22

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 1
SCHEDULE 6A.mpp

Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
8%
3%

67%

10%

0%
0%
0%

23%
0%
0%
28/01

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 2
SCHEDULE 6A.mpp

Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 3