Project1

ID Task Task Name Duration Start


Qtr 2, 2020 Finish Qtr 3, 2020 Qtr 4, 2020
Mode Jun Jul Aug Sep Oct
1 Tissue Project 307.06 days Wed 01-07-20Thu 02-09-21
2 Civil work 120 days Wed 01-07-20Wed 16-12-20
3 piling 1 wk Wed 01-07-20Thu 09-07-20 75%
4 excavation 4 wks Wed 23-09-20Tue 27-10-20 10
5 floor 1 wk Tue 27-10-20 Wed 04-11-20
6 rcc 1 wk Fri 20-11-20 Mon 30-11-20
7 colomn 1 wk Tue 08-12-20 Wed 16-12-20
8 Mechanical 168 days Fri 20-11-20 Wed 14-07-21
9 as 2 wks Fri 20-11-20 Tue 08-12-20
10 as 5 wks Tue 08-12-20 Tue 19-01-21
11 as 3 wks Tue 02-03-21 Fri 26-03-21
12 ss 12 wks Tue 02-03-21 Thu 10-06-21
13 ssd 1 wk Thu 10-06-21Fri 18-06-21
14 rr 1 wk Fri 18-06-21 Mon 28-06-21
15 tt 2 wks Mon 28-06-21Wed 14-07-21
16 Elec 145 days Wed 23-09-20Wed 14-04-21
17 rr 1 wk Wed 23-09-20Thu 01-10-20 0%
18 tyu 2 wks Tue 02-03-21 Thu 18-03-21
19 uuy 3 wks Thu 18-03-21Tue 13-04-21
20 Complete 1 day Tue 13-04-21 Wed 14-04-21

Critical Finish-only Manual Summary

Critical Split Duration-only Project Summary

Critical Progress Baseline External Tasks

Task Baseline Split External Milestone

Split Baseline Milestone Inactive Task

Task Progress Milestone Inactive Milestone

Manual Task Summary Progress Inactive Summary

Start-only Summary Deadline

Page 1
Project1

Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021


Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

81%

100%
50%
25%
100%
20%
75%
75%
0%
0%
0%
0%
0%
0%

0%
0%
0%

Critical Finish-only Manual Summary

Critical Split Duration-only Project Summary

Critical Progress Baseline External Tasks

Task Baseline Split External Milestone

Split Baseline Milestone Inactive Task

Task Progress Milestone Inactive Milestone

Manual Task Summary Progress Inactive Summary

Start-only Summary Deadline