COMPLETION WORK PROGRAMME

MULTI-AGENCY OFFICE COMPLEX


ALAUSA IKEJA
ID Task Name Duration Start Finish Predecessors % Half 2, 2021 Half 1, 2022
Complete M J J A S O N D J F M A M
1 MULTI-AGENCY BUILDING IKEJA 210 days? Tue 01 Jun '21 Fri 01 Apr '22 0% 01/06 01/04

2 Design Production & Approval 25 days? Tue 01 Jun '21 Mon 05 Jul '21 0%

3 Architectural Working Design 5 wks Tue 01 Jun '21 Mon 05 Jul '21 0%

4 MEP Working Design 5 wks Tue 01 Jun '21 Mon 05 Jul '21 0%

5 HVAC Working Design 5 wks Tue 01 Jun '21 Mon 05 Jul '21 0%

6 Mobilization 6 days Mon 05 Jul '21 Mon 12 Jul '21 0% 05/07 12/07

7 Kick off meeting 0 days Mon 05 Jul '21 Mon 05 Jul '21 0% 05/07

8 Safety Induction 1 day Mon 05 Jul '21 Mon 05 Jul '21 7 0% 05/07 05/07

9 Mobilization (office, store) 1 wk Tue 06 Jul '21 Mon 12 Jul '21 8 0% 06/07 12/07

10 DEMOLITION & ALTERATION 50 days Tue 13 Jul '21 Mon 20 Sep '21 0% 13/07 20/09

11 Ground Floor - Pent Floor 50 days Tue 13 Jul '21 Mon 20 Sep '21 0% 13/07 20/09

12 Remove all walls marked for alteration/demolition, 6 wks Tue 13 Jul '21 Mon 23 Aug '21 9,3SS 0% 13/07 23/08
including all cracked areas

13 Remove all existing windows and door frames 4 wks Tue 13 Jul '21 Mon 09 Aug '21 12SS 0%
marked for alteration

14 Remove existing floor tiles 6 wks Tue 13 Jul '21 Mon 23 Aug '21 13SS 0% 13/07 23/08

15 Set out revised plan 6 wks Tue 13 Jul '21 Mon 23 Aug '21 13SS 0% 13/07 23/08

16 Coring of floor slab for service ducts 10 wks Tue 13 Jul '21 Mon 20 Sep '21 13SS 0% 13/07 20/09

17 Remove existing curtin wall on Pent Floor 4 wks Tue 24 Aug '21 Mon 20 Sep '21 15 0% 24/08 20/09

18 NEW WORKS 180 days? Tue 13 Jul '21 Fri 01 Apr '22 0% 13/07 01/04

19 WET FINISHES 165 days Tue 13 Jul '21 Fri 11 Mar '22 0% 13/07 11/03

20 Ground Floor - First Floor 105 days Tue 05 Oct '21 Fri 11 Mar '22 0% 05/10 11/03

21 Blockwall and lintels 6 wks Tue 05 Oct '21 Mon 15 Nov '21 29 0%
22 Door/window subframes 4 wks Tue 19 Oct '21 Mon 15 Nov '21 21SS+2 wks 0% 19/10 15/11

23 All 1st/2nd Fix MEP & VRF AC Pipeworks 4 wks Tue 16 Nov '21 Mon 13 Dec '21 21 0%
24 Internal plastering 4 wks Tue 16 Nov '21 Mon 13 Dec '21 23SS 0% 16/11 13/12

25 Wall tiling works 4 wks Tue 30 Nov '21 Fri 07 Jan '22 24SS+2 wks 0% 30/11 07/01

26 Floor tiling works 4 wks Tue 07 Dec '21 Fri 14 Jan '22 25SS+1 wk 0% 07/12 14/01

27 Floor surface treatment/felting - Parking and 20 wks Tue 12 Oct '21 Fri 11 Mar '22 21SS+1 wk 0% 12/10 11/03
terrace areas

28 Second Floor - Pent Floor 110 days Tue 13 Jul '21 Mon 13 Dec '21 0% 13/07 13/12

29 Blockwall and lintels 12 wks Tue 13 Jul '21 Mon 04 Oct '21 12SS 0% 13/07 04/10

30 Door/window subframes 10 wks Tue 03 Aug '21 Mon 11 Oct '21 29SS+3 wks 0%
31 All 1st/2nd Fix MEP & VRF AC Pipeworks 12 wks Tue 03 Aug '21 Mon 25 Oct '21 29SS+3 wks,4,50% 03/08 25/10

Task External Tasks Duration-only External Tasks Deadline


Split External Milestone Manual Summary Rollup External Milestone
Project: COMPLETION PROGRAMME
Date: Wed 11 Aug '21 Milestone Inactive Milestone Manual Summary Critical
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Progress

Page 1
COMPLETION WORK PROGRAMME
MULTI-AGENCY OFFICE COMPLEX
ALAUSA IKEJA
ID Task Name Duration Start Finish Predecessors % Half 2, 2021 Half 1, 2022
Complete M J J A S O N D J F M A M
32 Internal plastering/Screeding 12 wks Tue 17 Aug '21 Mon 08 Nov '21 31SS+2 wks 0% 17/08 08/11

33 Wall tiling works 12 wks Tue 07 Sep '21 Mon 29 Nov '21 32SS+3 wks 0% 07/09 29/11

34 Floor tiling works/Toilet floor felting 12 wks Tue 21 Sep '21 Mon 13 Dec '21 33SS+2 wks 0% 21/09 13/12

35 External Plastering/Screeding 8 wks Tue 05 Oct '21 Mon 29 Nov '21 29 0% 05/10 29/11

36 DRY FINISHES 100 days Tue 28 Sep '21 Fri 25 Feb '22 0% 28/09 25/02

37 Ground Floor - First Floor 40 days Tue 14 Dec '21 Fri 18 Feb '22 0% 14/12 18/02

38 Aluminium windows 2 wks Tue 14 Dec '21 Fri 07 Jan '22 24 0%


39 Suspended Modular ceiling grids 2 wks Tue 14 Dec '21 Fri 07 Jan '22 38SS 0%
40 Glass/Steel works 4 wks Tue 21 Dec '21 Fri 28 Jan '22 39SS+1 wk 0%
41 Install Doors 4 wks Tue 21 Dec '21 Fri 28 Jan '22 40SS 0%
42 1st coats internal painting 4 wks Mon 10 Jan '22 Fri 04 Feb '22 41SS+1 wk 0%
43 MEP fittings and accessories/AC units 4 wks Mon 10 Jan '22 Fri 04 Feb '22 42SS 0%
44 Suspended Modular ceiling tiles 4 wks Mon 24 Jan '22 Fri 18 Feb '22 43SS+2 wks 0%
45 Final coats internal painting 4 wks Mon 24 Jan '22 Fri 18 Feb '22 44SS 0%
46 Second Floor - Pent Floor 100 days Tue 28 Sep '21 Fri 25 Feb '22 0% 28/09 25/02

47 Aluminium windows 6 wks Tue 28 Sep '21 Mon 08 Nov '21 34SS+1 wk 0% 28/09 08/11

48 Suspended Modular ceiling grids 8 wks Tue 26 Oct '21 Mon 20 Dec '21 31 0% 26/10 20/12

49 Glass/Steel works 8 wks Tue 26 Oct '21 Mon 20 Dec '21 48SS 0% 26/10 20/12

50 Install Doors 8 wks Tue 02 Nov '21 Fri 07 Jan '22 34SS+6 wks 0% 02/11 07/01

51 1st coats internal painting 8 wks Tue 02 Nov '21 Fri 07 Jan '22 50SS 0% 02/11 07/01

52 MEP fittings and accessories/AC units 12 wks Tue 02 Nov '21 Fri 04 Feb '22 51SS 0% 02/11 04/02

53 Suspended Modular ceiling tiles 10 wks Tue 16 Nov '21 Fri 04 Feb '22 52SS+2 wks 0%
54 Panel glass partitioning 10 wks Tue 30 Nov '21 Fri 18 Feb '22 53SS+2 wks 0%

55 Final coats internal painting 10 wks Tue 30 Nov '21 Fri 18 Feb '22 53SS+2 wks 0%
56 Signages 6 wks Mon 17 Jan '22 Fri 25 Feb '22 50FS+1 wk 0% 17/01 25/02

57 Furnitures 6 wks Mon 17 Jan '22 Fri 25 Feb '22 56SS 0% 17/01 25/02

58 Lift Installation 8 wks Tue 30 Nov '21 Fri 04 Feb '22 52SS+4 wks 0% 30/11 04/02

59 EXTERNAL WORKS 40 days Tue 30 Nov '21 Fri 04 Feb '22 0% 30/11 04/02

60 External painting works 8 wks Tue 30 Nov '21 Fri 04 Feb '22 35 0%
61 Testing/Commissioning/Cleaning/Handover 8 wks Mon 07 Feb '22 Fri 01 Apr '22 52,58 0% 07/02 01/04

62 Emergency Staircase 62 days? Tue 24 Aug '21 Wed 17 Nov '21 0% 24/08 17/11

71 POST CONSTRUCTION ACTIVITIES 0 days Fri 01 Apr '22 Fri 01 Apr '22 61 0% 01/04

Task External Tasks Duration-only External Tasks Deadline


Split External Milestone Manual Summary Rollup External Milestone
Project: COMPLETION PROGRAMME
Date: Wed 11 Aug '21 Milestone Inactive Milestone Manual Summary Critical
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Progress