You are on page 1of 1

FRL Lagos State Multi-Agency Complex Building

Weekly Progress Report

FRL
Date: 13/08/2021 Job No:
Week 32 Report No: 2
WEEKLY PROGRESS REPORT Location: ALAUSA, IKEJA LAGOS STATE
Project Title: LAGOS STATE MULTI AGENCY OFFICE COMPLEX ALAUSA
Contractor: METROL FITTINGS & ACCESSORIES LTD
Sub-Contractor:
Project Duration: Commencement Date: Completion Date:
Overall Project Status to Date:
Work Weeks Completed to Date: Work Weeks Left to completion:
On Track Off Track Delayed
LEGEND:

DISTRIBUTION LIST
Contacts Name Phone No Email
The Special Adviser
Perm. Secretary
Dir. Architectural Services
Dir. Mechanical Services
Dir. Electrical Services
MD Metrol Fittings & Acc.
MD MC&T
MD Palmyra

SUMMARY OF WEEKLY WORK PROGRESS WEEK __32


Items Project Activities Average Total % Progress
1 Mobilization 90% 90%
100%
2 Demolition & Alteration 75% 75%
80%
3 MEP Works 0% 60%

4 Wet Works 15% 40%


15%
5 Dry Works 0% 20%
0% 0% 0% 0%
0%
6 External Works 0%
Mobilization Demolition & Alteration
MEP Works Wet Works
7 Commissioning & Handover 0% Dry Works External Works

Issues/Delays/Disruptions

Status Tallies Priority Tallies


0%
17%
1 nos
Not Started High 1 nos17%

1 nos16%
In Progress Medium
4 nos
67%

5 nos
83%
Closed Low

Items Description Status Priority Assignee Comments


1 Resolution of HVAC system In Progress High Ministry
2 Approval of Architectural Drawings In Progress High Metrol/Ministry
Submission of construction methodology, HSE management
3 In Progress High Metrol/Mct
plan and Quality management plan
4 Resolution of plumbing system In Progress High Metrol/Ministry
5 Resolution of Fire Fighting System In Progress Medium Metrol/Ministry
6 Sewage Treatment - (Bio-digester option) Not Started Low

You might also like