ID % Task Name Baseline Start Baseline Finish Start Finish Actual Start Actual Finish Predecessors

Complete Qtr 2, 2021 Qtr 3, 2021


Apr May Jun Jul Aug Se
1 21% Programa de Construcción Mon 31/05/21 Thu 29/07/21 Mon 31/05/21 Thu 29/07/21 Mon 31/05/21 NA
2 30% REF Mon 31/05/21 Fri 23/07/21 Mon 31/05/21 Fri 23/07/21 Mon 31/05/21 NA
3 8% Sistema DAA/DAC/DPC (Priority 1 Cimesa) Mon 07/06/21 Sat 10/07/21 Mon 07/06/21 Sat 10/07/21 Mon 07/06/21 NA
4 15% Prefrabricated Mon 07/06/21 Sat 10/07/21 Mon 07/06/21 Sat 10/07/21 Mon 07/06/21 NA 15%
5 0% Mounting Mon 07/06/21 Sat 10/07/21 Mon 07/06/21 Sat 10/07/21 NA NA 4SS 0%
6 8% Sistema DP/DPC (Priority 1 Santandreu) Thu 10/06/21 Sat 10/07/21 Thu 10/06/21 Sat 10/07/21 Thu 10/06/21 NA 8%
7 15% Prefrabricated Thu 10/06/21 Sat 10/07/21 Thu 10/06/21 Sat 10/07/21 Thu 10/06/21 NA 5SS+3 days 15%
8 0% Mounting Thu 10/06/21 Sat 10/07/21 Thu 10/06/21 Sat 10/07/21 NA NA 7SS 0%
9 3% Sistema DPC (Priority 2 Cimesa) Mon 21/06/21 Thu 22/07/21 Mon 21/06/21 Thu 22/07/21 Fri 18/06/21 NA
10 5% Prefrabricated Mon 21/06/21 Wed 21/07/21 Fri 18/06/21 Tue 20/07/21 Fri 18/06/21 NA 5%
11 0% Mounting Mon 21/06/21 Wed 21/07/21 Mon 21/06/21 Wed 21/07/21 NA NA 10SS 0%
12 75% Sistema ACI Mon 31/05/21 Wed 21/07/21 Mon 31/05/21 Wed 21/07/21 Mon 31/05/21 NA 75%
13 94% Prefrabricated Mon 31/05/21 Wed 21/07/21 Mon 31/05/21 Wed 21/07/21 Mon 31/05/21 NA 94%
14 56% Mounting Mon 31/05/21 Wed 21/07/21 Mon 31/05/21 Wed 21/07/21 Mon 31/05/21 NA 13SS 56%
15 5% 1.- Painting work Mon 14/06/21 Tue 27/07/21 Mon 14/06/21 Tue 27/07/21 Mon 14/06/21 NA 5%
16 13% REF Mon 14/06/21 Wed 14/07/21 Mon 14/06/21 Sat 10/07/21 Mon 14/06/21 NA 13%
17 70% Supplu of materials and equipment Mon 14/06/21 Sat 19/06/21 Mon 14/06/21 Sat 19/06/21 Mon 14/06/21 NA 70%
18 10... Fabrication of stand Mon 21/06/21 Thu 24/06/21 Mon 14/06/21 Tue 22/06/21 Mon 14/06/21 Tue 22/06/21 17FS+1 day 100%
19 0% Sand Blast Cleaning Fri 25/06/21 Fri 09/07/21 Wed 23/06/21 Tue 06/07/21 NA NA 18FS+1 day 0%
20 0% Primary Sat 26/06/21 Sat 10/07/21 Wed 23/06/21 Wed 07/07/21 NA NA 19SS+0.5 days 0%
21 0% Bond Tue 29/06/21 Mon 12/07/21 Fri 25/06/21 Thu 08/07/21 NA NA 20SS+2 days 0%
22 0% Termination of painting Wed 30/06/21 Wed 14/07/21 Mon 28/06/21 Sat 10/07/21 NA NA 21SS+1 day 0%
23 0% FCC Mon 28/06/21 Tue 27/07/21 Mon 28/06/21 Tue 27/07/21 NA NA 0%
24 0% Hauling of the unit to the workshop Mon 28/06/21 Tue 06/07/21 Mon 28/06/21 Tue 06/07/21 NA NA 0%
25 0% Unloading in painting shop Tue 29/06/21 Wed 07/07/21 Tue 29/06/21 Wed 07/07/21 NA NA 24SS+1 day 0%
26 0% Sand Blast Cleaning Fri 02/07/21 Wed 21/07/21 Fri 02/07/21 Wed 21/07/21 NA NA 25SS+3 days 0%
27 0% Primary Fri 02/07/21 Fri 23/07/21 Fri 02/07/21 Fri 23/07/21 NA NA 26SS 0%
28 0% Bond Tue 06/07/21 Mon 26/07/21 Tue 06/07/21 Mon 26/07/21 NA NA 27SS+3 days 0%
29 0% Termination of painting Wed 07/07/21 Mon 26/07/21 Wed 07/07/21 Mon 26/07/21 NA NA 28SS+1 day 0%
30 0% Hauling of the shop to the site Mon 12/07/21 Tue 27/07/21 Mon 12/07/21 Tue 27/07/21 NA NA 29SS+4 days 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

P62 DBNR Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Date: 20210618 Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline