Time aschedule Nginden

ID Task Task Name Duration Start Finish


Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
1 I PEKERJAAN PERSIAPAN 2 wks Wed 7/5/17 Tue 7/18/17 0%

2 Uitzet/Pasang 1 wk Wed 7/5/17 Tue 7/11/17 0%


bouwplank.
3 Direksikeet/Gudang & 1 wk Wed 7/5/17 Tue 7/11/17 0%
Barak Pekerja.
4 Pager Proyek 1 wk Wed 7/5/17 Tue 7/11/17 0%

5 Air Kerja 1 wk Tue 7/11/17 Tue 7/18/17 0%

6 Listrik kerja 1 wk Tue 7/11/17 Tue 7/18/17 0%

7 Pembersihan Akhir 1 wk Wed 7/5/17 Tue 7/11/17 0%

8 II. PEKERJAAN PONDASI 25 wks Tue 7/11/17 Sat 12/30/17


DAN DINDING TRASRAM

9 a. Pekerjaan Tanah. 6 wks Tue 7/11/17 Mon 0%


8/21/17
10 Galian tanah 1 wk Tue 7/11/17 Tue 7/18/17 0%
pondasi bangunan.

11 Urugan tanah 1 wk Mon 8/14/17 Mon 8/21/17 0%


kembali.
12 Urugan Pasir 1 wk Tue 7/18/17 Tue 7/25/17 0%
dibawah Pondasi

13 Urugan Sirtu 1 wk Tue 7/18/17 Tue 7/25/17 0%

14 Buangan Tanah 1 wk Mon 7/31/17 Mon 8/7/17 0%

15 Perataan tanah 1 wk Mon 8/14/17 Mon 8/21/17 0%

16 Pemadatan tanah 1 wk Mon 8/14/17 Mon 8/21/17 0%

17 b. Pekerjaan 24 wks Tue 7/18/17 Sat 12/30/17


Pondasi.
18 Lantai kerja 1 wk Mon 7/31/17 Mon 8/7/17 0%

19 Tiang Pancang + 2 wks Tue 7/18/17 Mon 7/31/17 0%


Boor strous
20 Mob Demob 2 wks Tue 7/18/17 Mon 7/31/17 0%

21 Kepras Tiang 1 wk Mon 7/31/17 Mon 8/7/17 0%


Pancang
22 Pile Cap 1 wk Mon 8/7/17 Mon 8/14/17 0%

23 P2 1 wk Mon 8/7/17 Mon 8/14/17 0%

24 P2A 1 wk Mon 8/7/17 Mon 8/14/17 0%

25 P3 1 wk Mon 8/7/17 Mon 8/14/17 0%

26 P4 1 wk Mon 8/7/17 Mon 8/14/17 0%

27 Sloof 2 wks Mon 8/14/17 Mon 8/28/17 0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 1
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
28 S1 2 wks Mon 8/14/17 Mon 8/28/17 0%

29 S1A 2 wks Mon 8/14/17 Mon 8/28/17 0%

30 S2 2 wks Mon 8/14/17 Mon 8/28/17 0%

31 S3 2 wks Mon 8/14/17 Mon 8/28/17 0%

32 SK 01 2 wks Mon 8/14/17 Mon 8/28/17 0%

33 S4 2 wks Mon 8/14/17 Mon 8/28/17 0%

34 SK05 2 wks Mon 8/14/17 Mon 8/28/17 0%

35 Pasangan Transram 2 wks Tue 9/5/17 Mon 9/18/17 0%

36 Plester + Acian 1 wk Thu Sat 12/30/17


12/21/17
37 III. PEKERJAAN 17 wks Tue 8/22/17 Fri 12/15/17
STRUKTUR
38 • Denah Lantai 1 9 wks Tue 8/22/17 Mon 10/23/17 0%
39 Plat lantai dasar / 1 wk Tue 8/22/17 Mon 8/28/17 0%
Slab on ground ex.
Weremesh M5 tbl 8
cm
40 Kolom Struktur 1 wk Mon 8/28/17 Tue 9/5/17 0%
41 Kolom Praktis 1 wk Mon 8/28/17 Tue 9/5/17 0%
42 Balok latai 2 wks Tue 9/26/17 Mon 10/9/17 0%
43 Balok praktis 2 wks Tue 9/26/17 Mon 10/9/17 0%
(Belakang)
44 Tangga Lt. 1 ke Lt. 2 2 wks Tue 10/10/17 Mon 10/23/17 0%
45 a. Kolom Bordes 2 wks Tue 10/10/17 Mon 10/23/17 0%
46 b. Balok Bordes 2 wks Tue 10/10/17 Mon 10/23/17 0%
47 c. Tangga beton 2 wks Tue 10/10/17 Mon 10/23/17 0%
48 Balok Canopy 2 wks Tue 9/26/17 Mon 10/9/17 0%
49 Plat Canopy 2 wks Tue 9/26/17 Mon 10/9/17 0%
50 • Denah Lantai 2 9 wks Tue 9/26/17 Fri 11/24/17
51 Balok Struktur 2 wks Tue 9/26/17 Mon 10/9/17 0%
52 Plat lantai 1 2 wks Tue 9/26/17 Mon 10/9/17 0%
53 Kolom Struktur 1 wk Mon 10/23/17 Mon 10/30/17 0%
54 Kolom Praktis 1 wk Mon 10/23/17 Mon 10/30/17 0%
55 Balok latai 1 wk Mon 10/30/17 Sat 11/4/17 0%
56 Tangga Lt. 2 ke Lt. 3 2 wks Sat 11/11/17 Fri 11/24/17
57 a. Kolom Bordes 2 wks Sat 11/11/17 Fri 11/24/17
58 b. Balok Bordes 2 wks Sat 11/11/17 Fri 11/24/17
59 c. Tangga beton 2 wks Sat 11/11/17 Fri 11/24/17
60 Balok Canopy 2 wks Mon 10/30/17 Sat 11/11/17
61 Plat Canopy 2 wks Mon 10/30/17 Sat 11/11/17
62 • Denah Lantai 3 4 wks Mon 10/30/17Fri 11/24/17
63 Balok Struktur 1 wk Mon 10/30/17 Sat 11/4/17 0%
64 Plat lantai 1 wk Mon 10/30/17 Sat 11/4/17 0%
65 Kolom Struktur 1 wk Sat 11/11/17 Sat 11/18/17
66 Kolom Praktis 1 wk Sat 11/11/17 Sat 11/18/17

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 2
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
67 Balok latai 1 wk Sat 11/11/17 Sat 11/18/17
68 Balok Canopy 1 wk Sat 11/18/17 Fri 11/24/17
69 Plat Canopy 1 wk Sat 11/18/17 Fri 11/24/17
70 ●Area Lantai atap. 4 wks Sat 11/18/17 Fri 12/15/17
71 Balok Struktur 1 wk Sat 11/18/17 Fri 11/24/17
72 Plat Atap 1 wk Sat 11/18/17 Fri 11/24/17
73 Kolom struktur 1 wk Sat 11/25/17 Fri 12/1/17
74 Kolom Praktis dan 1 wk Sat 11/25/17 Fri 12/1/17
Kolom Gewel
75 Ring Balok 1 wk Fri 12/1/17 Fri 12/8/17
76 Balok Struktur Gewel 1 wk Fri 12/1/17 Fri 12/8/17
77 Ring Balok Gewel 1 wk Fri 12/1/17 Fri 12/8/17
78 Balok Depan Atap 1 wk Fri 12/1/17 Fri 12/8/17
(Tampak Depan)
79 Dak Atap Area 1 wk Fri 12/8/17 Fri 12/15/17
Tangga Putar
80 a. Kolom 1 wk Fri 12/8/17 Fri 12/15/17
81 b. Balok 1 wk Fri 12/8/17 Fri 12/15/17
82 c. Plat 1 wk Fri 12/8/17 Fri 12/15/17
83 IV. PEKERJAAN 32.65 wks Mon Sat 4/28/18
PASANGANAN BATU 9/18/17
BATA DAN PELESTERAN

84 • Denah Lantai 1 32.65 wks Mon Sat 4/28/18


9/18/17
85 Pasangan Bata 1 wk Mon 9/18/17 Tue 9/26/17 0%

86 Plesteran + Acian 3 wks Thu Sat 1/13/18


dinding 12/21/17
87 a. Tampak 1 wk Thu Sat 12/30/17
12/21/17
88 b. Dinidng Pager 1 wk Thu Sat 12/30/17
Belakang 12/21/17
89 c. Dinding Dalam 2 wks Sat 12/30/17 Sat 1/13/18

90 Ekpos Kolom 2 wks Sat 12/30/17 Sat 1/13/18

91 Ekpos Balok Tepi 2 wks Sat 12/30/17 Sat 1/13/18

92 Ekspos Balok 3.05 wks Sat 12/30/17 Sat 4/28/18


Lisplank
93 Plat Ekspos + Tali 2 wks Sat 12/30/17 Sat 1/13/18
Air
94 Benangan 2 wks Sat 12/30/17 Sat 1/13/18

95 Openingan Pintu 2 wks Sat 12/30/17 Sat 1/13/18


dan Jendela
96 Tali air kavling 2 wks Sat 12/30/17 Sat 1/13/18

97 • Denah Lantai 2 16 wks Mon Fri 2/9/18


10/23/17
98 Pasangan Bata 1 wk Mon Mon 0%
Ringan 10/23/17 10/30/17
99 Plesteran + Acian 3 wks Mon Sat 2/3/18
Dinding 1/15/18

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 3
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
100 a. Tampak 1 wk Mon 1/15/18 Sat 1/20/18

101 b. Dalam 2 wks Sat 1/20/18 Sat 2/3/18

102 Kolom Ekspos 1 wk Sat 1/27/18 Sat 2/3/18

103 Balok Ekspos 1 wk Sat 1/27/18 Sat 2/3/18

104 Plat Ekspos + Tali 1 wk Sat 1/27/18 Sat 2/3/18


Air
105 Balok Jangutan 1 wk Sat 2/3/18 Fri 2/9/18

106 1. Balok 1 wk Sat 2/3/18 Fri 2/9/18


jangutan
107 2. Finihing 1 wk Sat 2/3/18 Fri 2/9/18
balok
108 Benangan 1 wk Sat 2/3/18 Fri 2/9/18

109 Openingan pintu 1 wk Sat 2/3/18 Fri 2/9/18


dan jendela
110 Tali Air Kavling 1 wk Sat 2/3/18 Fri 2/9/18

111 • Denah Lantai 3 14 wks Sat 11/11/17 Fri 2/16/18

112 Pasangan Bata 2 wks Sat 11/11/17 Fri 11/24/17


Ringan
113 Plesteran + Acian 2 wks Sat 2/3/18 Fri 2/16/18
Dinding
114 b. Tampak 1 wk Sat 2/3/18 Fri 2/9/18

115 c. Dalam 2 wks Sat 2/3/18 Fri 2/16/18

116 Kolom Ekspos 1 wk Fri 2/9/18 Fri 2/16/18

117 Balok Ekspos 1 wk Fri 2/9/18 Fri 2/16/18

118 Plat Ekspos + Tali 1 wk Fri 2/9/18 Fri 2/16/18


Air
119 Balok Jangutan 1 wk Fri 2/9/18 Fri 2/16/18

120 1. Balok 1 wk Fri 2/9/18 Fri 2/16/18


jangutan
121 2. Finihing 1 wk Fri 2/9/18 Fri 2/16/18
balok
122 Benangan 1 wk Fri 2/9/18 Fri 2/16/18

123 Openingan pintu 1 wk Fri 2/9/18 Fri 2/16/18


dan jendela
124 Tali Air Kavling 1 wk Fri 2/9/18 Fri 2/16/18

125 • Denah Lantai Atap 13 wks Sat 11/25/17 Fri 2/23/18

126 Rabatan Lantai Atap 1 wk Fri 2/9/18 Fri 2/16/18

127 Pas. Bata Ringan 1 wk Sat 11/25/17 Fri 12/1/17

128 Plesteran + Acian 2 wks Fri 2/9/18 Fri 2/23/18

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 4
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
129 Ekspos Balok 1 wk Fri 2/16/18 Fri 2/23/18
Tampak depan
130 Ekspos Plat + Balok 1 wk Fri 2/16/18 Fri 2/23/18
Atap Tangga Putar
131 Benangan Atap 1 wk Fri 2/16/18 Fri 2/23/18

132 Tali Air Kavling 1 wk Fri 2/16/18 Fri 2/23/18

133 V. PEKERJAAN ATAP 14 wks Sat 11/25/17 Thu 3/1/18

134 Rangka Atap ex. 2 wks Sat 11/25/17 Fri 12/8/17


Galvalum
135 Penutup Atap 2 wks Sat 11/25/17 Fri 12/8/17
Genteng ex.
Zingkalum tbl 0,4 mm

136 Wuwung 2 wks Sat 11/25/17 Fri 12/8/17

137 Zeltech ex. ZT BB 01 2 wks Sat 11/25/17 Fri 12/8/17

138 Flesing dinding 2 wks Sat 11/25/17 Fri 12/8/17

139 Lisplank ex. Galvalum 1 wk Fri 2/23/18 Thu 3/1/18

140 VI. PEKERJAAN 1 wk Wed 7/5/17 Tue 7/11/17 0%


INSTALASI AIR KOTOR
141 Instalasi Pipa PVC Air 1 wk Wed 7/5/17 Tue 7/11/17 0%
hujan
142 Instalasi Pipa PVC Air 1 wk Wed 7/5/17 Tue 7/11/17 0%
Kotor
143 Instalasi Pipa Air 1 wk Wed 7/5/17 Tue 7/11/17 0%
Kotoran
144 Jebakan Hawa 1 wk Wed 7/5/17 Tue 7/11/17 0%

145 Tandon 2 m3 1 wk Wed 7/5/17 Tue 7/11/17 0%

146 Sapitank ex. Beton 2 1 wk Wed 7/5/17 Tue 7/11/17 0%


m3 + Resapan
147 Bak Kontrol air hujan 1 wk Wed 7/5/17 Tue 7/11/17 0%
30 x 30 Cm.
148 Roof Drain 1 wk Wed 7/5/17 Tue 7/11/17 0%

149 III. PEKERJAAN 35 wks Wed 7/5/17 Thu 3/1/18


FINISHING.
150 a. Pekerjaan 12 wks Fri 12/8/17 Thu 3/1/18
Plafond.
151 Pasang Rangka + 1 wk Fri 12/8/17 Fri 12/15/17
Gypsum Board 9
mmex. Hollow,
152 Showdow Line 1 wk Fri 2/23/18 Thu 3/1/18

153 Menhol 1 wk Fri 2/23/18 Thu 3/1/18

154 Pasang Rangka + 1 wk Fri 2/23/18 Thu 3/1/18


Kalsi Board 9
mmex. Hollow,
155 Plafond GRC 1 wk Fri 2/23/18 Thu 3/1/18

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 5
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
156 Perkuatan Plafond 1 wk Fri 2/23/18 Thu 3/1/18
Di Lt. 4 ex. CNP
157 b. Pekerjaan 1 wk Wed 7/5/17 Tue 7/11/17 0%
Finishing Lantai dan
Dinding.
158 • Denah Lantai 1 1 wk Wed 7/5/17 Tue 7/11/17 0%

159 Teras depan ex. 1 wk Wed 7/5/17 Tue 7/11/17 0%


Platinum Stone
Black 40x40
160 Ruko ex. granit 1 wk Wed 7/5/17 Tue 7/11/17 0%
tile uk. 60x60
161 Gudang ex. granit 1 wk Wed 7/5/17 Tue 7/11/17 0%
tile uk. 60x60
162 Taman Belakang 1 wk Wed 7/5/17 Tue 7/11/17 0%
ex. Platinum
Black Stone
163 Tangga Lt. 1 - lt. 2 1 wk Wed 7/5/17 Tue 7/11/17 0%
ex. granit tile uk.
60x60
164 Plint Lantai ex. 1 wk Wed 7/5/17 Tue 7/11/17 0%
Granit Tile 60x
7,5 cm +
165 KM 1 wk Wed 7/5/17 Tue 7/11/17 0%

166 1. Rabatan 1 wk Wed 7/5/17 Tue 7/11/17 0%


Lantai
167 2. Lantai ex. 1 wk Wed 7/5/17 Tue 7/11/17 0%
40x40
168 3. Dinding 1 wk Wed 7/5/17 Tue 7/11/17 0%
ex. 20x40
169 a. 1 wk Wed 7/5/17 Tue 7/11/17 0%
Plesteran
170 b. 1 wk Wed 7/5/17 Tue 7/11/17 0%
Keramik
171 Relling Tangga 1 wk Wed 7/5/17 Tue 7/11/17 0%
Lt. 1-2
172 a. Tanggulan 1 wk Wed 7/5/17 Tue 7/11/17 0%
Relling
173 b. Relling Besi 1 wk Wed 7/5/17 Tue 7/11/17 0%
ex. Hollow 2x4
dan 4x4
174 Pasang Granit 1 wk Wed 7/5/17 Tue 7/11/17 0%
Tile Area Kolom
Tampak Depan
175 a. Penebalan 1 wk Wed 7/5/17 Tue 7/11/17 0%
Kolom Tampak
176 b. Granit tile 1 wk Wed 7/5/17 Tue 7/11/17 0%
kolom tampak
depan
177 • Denah Lantai 2 1 wk Wed 7/5/17 Tue 7/11/17 0%

178 Ruko ex. granit 1 wk Wed 7/5/17 Tue 7/11/17 0%


tile uk. 60x60
179 Tangga Lt. 2 - lt. 3 1 wk Wed 7/5/17 Tue 7/11/17 0%
ex. granit tile uk.
60x60

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 6
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
180 Meja Dapur 1 wk Wed 7/5/17 Tue 7/11/17 0%

181 1. Meja 1 wk Wed 7/5/17 Tue 7/11/17 0%


Beton
182 2. Finishing 1 wk Wed 7/5/17 Tue 7/11/17 0%
Meja dapur
183 1. 1 wk Wed 7/5/17 Tue 7/11/17 0%
Meja ex.
Platinum
184 2. 1 wk Wed 7/5/17 Tue 7/11/17 0%
Dinding
Meja ex.
Platinum
185 Plint Lantai ex. 1 wk Wed 7/5/17 Tue 7/11/17 0%
Granit Tile 60x
7,5 cm +
186 Relling Tangga 1 wk Wed 7/5/17 Tue 7/11/17 0%
Lt. 2-3
187 a. Tanggulan 1 wk Wed 7/5/17 Tue 7/11/17 0%
Relling
188 b. Relling Besi 1 wk Wed 7/5/17 Tue 7/11/17 0%
ex. Hollow 2x4
dan 4x4
189 Waterprofing 1 wk Wed 7/5/17 Tue 7/11/17 0%

190 a. Canopy 1 wk Wed 7/5/17 Tue 7/11/17 0%


Belakang
191 Pasang Granit 1 wk Wed 7/5/17 Tue 7/11/17 0%
Tile Area Kolom
Tampak Depan
192 a. Penebalan 1 wk Wed 7/5/17 Tue 7/11/17 0%
Kolom Tampak
193 b. Granit tile 1 wk Wed 7/5/17 Tue 7/11/17 0%
kolom tampak
depan
194 • Denah Lantai 3 1 wk Wed 7/5/17 Tue 7/11/17 0%

195 Ruko ex. granit 1 wk Wed 7/5/17 Tue 7/11/17 0%


tile uk. 60x60
196 Plint Lantai ex. 1 wk Wed 7/5/17 Tue 7/11/17 0%
Granit Tile 60x
7,5 cm +
197 KM 1 wk Wed 7/5/17 Tue 7/11/17 0%

198 1. Rabatan 1 wk Wed 7/5/17 Tue 7/11/17 0%


Lantai
199 2. Lantai ex. 1 wk Wed 7/5/17 Tue 7/11/17 0%
40x40
200 3. Dinding 1 wk Wed 7/5/17 Tue 7/11/17 0%
ex. 20x40
201 a. 1 wk Wed 7/5/17 Tue 7/11/17 0%
Plesteran
202 b. 1 wk Wed 7/5/17 Tue 7/11/17 0%
Keramik
203 Relling Tangga 1 wk Wed 7/5/17 Tue 7/11/17 0%
Lt. 3-4
204 a. Tanggulan 1 wk Wed 7/5/17 Tue 7/11/17 0%
Relling

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 7
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
205 b. Relling Besi 1 wk Wed 7/5/17 Tue 7/11/17 0%
ex. Hollow 2x4
dan 4x4
206 Tangga Putar 1 wk Wed 7/5/17 Tue 7/11/17 0%

207 Waterprofing 1 wk Wed 7/5/17 Tue 7/11/17 0%

208 a. Canopy 1 wk Wed 7/5/17 Tue 7/11/17 0%


Belakang
209 b. KM 1 wk Wed 7/5/17 Tue 7/11/17 0%

210 • Denah Lantai 1 wk Wed 7/5/17 Tue 7/11/17 0%


Atap
211 WaterProfing 1 wk Wed 7/5/17 Tue 7/11/17 0%
Dak Atap
212 a. Dak Atap 1 wk Wed 7/5/17 Tue 7/11/17 0%
Belakang +
213 b. Dak Atap 1 wk Wed 7/5/17 Tue 7/11/17 0%
Depan 15,3
214 c. Dak Atap 1 wk Wed 7/5/17 Tue 7/11/17 0%
Belakang +
215 D. Flasing 1 wk Wed 7/5/17 Tue 7/11/17 0%
gewel
216 Pasang 1 wk Wed 7/5/17 Tue 7/11/17 0%
Keramik
217 Tali Air 1 wk Wed 7/5/17 Tue 7/11/17 0%
Tampak Depan
218 c. Pekerjaan Pintu dan 1 wk Wed 7/5/17 Tue 7/11/17 0%
Jendela
268 d. Pekerjaan 1 wk Wed 7/5/17 Tue 7/11/17 0%
Pengecetan
275 e. Pekerjaan Saniter 1 wk Wed 7/5/17 Tue 7/11/17 0%

276 KM/ WC Lt. 1 1 wk Wed 7/5/17 Tue 7/11/17 0%

283 Dapur Lt. 2 1 wk Wed 7/5/17 Tue 7/11/17 0%

286 KM/ WC Lt. 3 1 wk Wed 7/5/17 Tue 7/11/17 0%

297 f. Pekerjaan Instalasi 1 wk Wed 7/5/17 Tue 7/11/17 0%


Air Bersih
298 Header 1 wk Wed 7/5/17 Tue 7/11/17 0%

299 g. Pekerjaan Instalasi 26 wks? Wed 7/5/17 Sat 12/30/17


Listrik, Data dan Telp
300 Instlasi Listrik 26 wks Wed 7/5/17 Sat 12/30/17

301 Instalasi titik lampu 2 wks Fri 12/15/17 Sat 12/30/17


Fiting Biasa
302 Instalasi titik lampu 2 wks Fri 12/15/17 Sat 12/30/17
Outbow
303 Instalasi titik Taman 2 wks Fri 12/15/17 Sat 12/30/17

304 Instalasi stop 2 wks Fri 12/15/17 Sat 12/30/17


kontak
305 Instalasi stop 2 wks Fri 12/15/17 Sat 12/30/17
kontak AC

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 8
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
306 Instalasi stop 1 wk Fri 12/15/17 Thu
kontak Pompa 12/21/17
307 Instalasi Exshous 2 wks Fri 12/15/17 Sat 12/30/17
fan
308 Asesoris Fiting biasa 2 wks Wed 7/5/17 Tue 7/18/17 0%
+ Dop 5 watt
309 Asesoris Outbow 2 wks Wed 7/5/17 Tue 7/18/17 0%
Tabung
310 Asesoris Taman 2 wks Fri 12/15/17 Sat 12/30/17

311 Asesoris Stop 2 wks Wed 7/5/17 Tue 7/18/17 0%


Kontak
312 Asesoris Stop 2 wks Wed 7/5/17 Tue 7/18/17 0%
Kontak AC
313 Asesoris Stop 2 wks Wed 7/5/17 Tue 7/18/17 0%
Kontak pompa
314 Asesoris Exshous 2 wks Wed 7/5/17 Tue 7/18/17 0%
fan
315 Asesoris Saklar 2 wks Wed 7/5/17 Tue 7/18/17 0%
tunggal ex.
Panasonic
316 Asesoris Saklar 2 2 wks Wed 7/5/17 Tue 7/18/17 0%
titik ex. Panasonic
317 Asesoris Saklar 3 2 wks Fri 12/15/17 Sat 12/30/17
titik ex. Panasonic
318 Box Sekring 12 2 wks Fri 12/15/17 Sat 12/30/17
Group
319 Box Sekring 12 2 wks Fri 12/15/17 Sat 12/30/17
Group
320 MCB 10 A (3 Phase) 2 wks Fri 12/15/17 Sat 12/30/17

321 MCB 10 A (1 Phase) 2 wks Fri 12/15/17 Sat 12/30/17

322 Box MCB 2 wks Fri 12/15/17 Sat 12/30/17

323 Box Meter / KWH 2 wks Fri 12/15/17 Sat 12/30/17

324 Sisir MCB 3 Phase 2 wks Fri 12/15/17 Sat 12/30/17

325 Conex MCB 3 Phase 2 wks Fri 12/15/17 Sat 12/30/17

326 Sisir MCB 1 Phase 2 wks Fri 12/15/17 Sat 12/30/17

327 Conex MCB 1 Phase 2 wks Fri 12/15/17 Sat 12/30/17

328 Kabel NYY 4x10 2 wks Fri 12/15/17 Sat 12/30/17


untuk persediaan
KWH meter.
329 Kabel NYY 4x6 2 wks Fri 12/15/17 Sat 12/30/17
untuk Overspaning
Lt. 1 ke :t. 2
330 Kabel NYY 4x6 2 wks Fri 12/15/17 Sat 12/30/17
untuk Overspaning
Lt. 2 ke :t. 3
331 Kabel NYY 4x6 2 wks Fri 12/15/17 Sat 12/30/17
untuk Overspaning
Lt. 3 ke :t. 4

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 9
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
332 Kabel Grounding 2 wks Fri 12/15/17 Sat 12/30/17
/arcade
333 Pembagian Beban 2 wks Fri 12/15/17 Sat 12/30/17

334 Instalasi Kabel Data, 1 wk Wed 7/5/17 Tue 7/11/17 0%


TV dan Telp
335 Instalasi Kabel TV , 1 wk Wed 7/5/17 Tue 7/11/17 0%
Data dan Telp
336 Box Panel 1 wk Wed 7/5/17 Tue 7/11/17 0%

337 i. Pekerjaan 1 wk? Wed 7/5/17 Tue 7/11/17 0%


Lain-Lain.
338 Pompa ex. Ecofil 1 wk Wed 7/5/17 Tue 7/11/17 0%

339 Tandon air stenlis 1 1 wk Wed 7/5/17 Tue 7/11/17 0%


m3
340 0.2 wks? Wed 7/5/17 Thu 7/6/17 0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 10
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6

0%

0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 11
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6

0%

0%

0%

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 12
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6
0%
0%
0%
0%
0%
0%
0%
0%

0%
0%
0%
0%

0%

0%
0%
0%
0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 13
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6
0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 14
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6
0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 15
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6
0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 16
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 17
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6

0%

0%

0%

0%

0%

0%

0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 18
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6
0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 19
Time aschedule Nginden

November December January February March April May


11/5 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18 2/25 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6
0%

0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone

Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary

Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline