Professional Documents
Culture Documents
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 1
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
28 S1 2 wks Mon 8/14/17 Mon 8/28/17 0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 2
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
67 Balok latai 1 wk Sat 11/11/17 Sat 11/18/17
68 Balok Canopy 1 wk Sat 11/18/17 Fri 11/24/17
69 Plat Canopy 1 wk Sat 11/18/17 Fri 11/24/17
70 ●Area Lantai atap. 4 wks Sat 11/18/17 Fri 12/15/17
71 Balok Struktur 1 wk Sat 11/18/17 Fri 11/24/17
72 Plat Atap 1 wk Sat 11/18/17 Fri 11/24/17
73 Kolom struktur 1 wk Sat 11/25/17 Fri 12/1/17
74 Kolom Praktis dan 1 wk Sat 11/25/17 Fri 12/1/17
Kolom Gewel
75 Ring Balok 1 wk Fri 12/1/17 Fri 12/8/17
76 Balok Struktur Gewel 1 wk Fri 12/1/17 Fri 12/8/17
77 Ring Balok Gewel 1 wk Fri 12/1/17 Fri 12/8/17
78 Balok Depan Atap 1 wk Fri 12/1/17 Fri 12/8/17
(Tampak Depan)
79 Dak Atap Area 1 wk Fri 12/8/17 Fri 12/15/17
Tangga Putar
80 a. Kolom 1 wk Fri 12/8/17 Fri 12/15/17
81 b. Balok 1 wk Fri 12/8/17 Fri 12/15/17
82 c. Plat 1 wk Fri 12/8/17 Fri 12/15/17
83 IV. PEKERJAAN 32.65 wks Mon Sat 4/28/18
PASANGANAN BATU 9/18/17
BATA DAN PELESTERAN
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 3
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
100 a. Tampak 1 wk Mon 1/15/18 Sat 1/20/18
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 4
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
129 Ekspos Balok 1 wk Fri 2/16/18 Fri 2/23/18
Tampak depan
130 Ekspos Plat + Balok 1 wk Fri 2/16/18 Fri 2/23/18
Atap Tangga Putar
131 Benangan Atap 1 wk Fri 2/16/18 Fri 2/23/18
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 5
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
156 Perkuatan Plafond 1 wk Fri 2/23/18 Thu 3/1/18
Di Lt. 4 ex. CNP
157 b. Pekerjaan 1 wk Wed 7/5/17 Tue 7/11/17 0%
Finishing Lantai dan
Dinding.
158 • Denah Lantai 1 1 wk Wed 7/5/17 Tue 7/11/17 0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 6
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
180 Meja Dapur 1 wk Wed 7/5/17 Tue 7/11/17 0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 7
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
205 b. Relling Besi 1 wk Wed 7/5/17 Tue 7/11/17 0%
ex. Hollow 2x4
dan 4x4
206 Tangga Putar 1 wk Wed 7/5/17 Tue 7/11/17 0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 8
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
306 Instalasi stop 1 wk Fri 12/15/17 Thu
kontak Pompa 12/21/17
307 Instalasi Exshous 2 wks Fri 12/15/17 Sat 12/30/17
fan
308 Asesoris Fiting biasa 2 wks Wed 7/5/17 Tue 7/18/17 0%
+ Dop 5 watt
309 Asesoris Outbow 2 wks Wed 7/5/17 Tue 7/18/17 0%
Tabung
310 Asesoris Taman 2 wks Fri 12/15/17 Sat 12/30/17
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 9
Time aschedule Nginden
ID Task Task Name Duration Start Finish
Mode
July August September October November
6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29
332 Kabel Grounding 2 wks Fri 12/15/17 Sat 12/30/17
/arcade
333 Pembagian Beban 2 wks Fri 12/15/17 Sat 12/30/17
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 10
Time aschedule Nginden
0%
0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 11
Time aschedule Nginden
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 12
Time aschedule Nginden
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 13
Time aschedule Nginden
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 14
Time aschedule Nginden
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 15
Time aschedule Nginden
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 16
Time aschedule Nginden
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 17
Time aschedule Nginden
0%
0%
0%
0%
0%
0%
0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 18
Time aschedule Nginden
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 19
Time aschedule Nginden
0%
Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline
Page 20