PROPOSED ADDITIONAL WORKS TO IMMEDIATE REPAIR EMBANKMENT SLOPE FAILURE AT KM 107+100 (B)

ALONG CIKOPO - PALIMANAN HIGHWAY (CIPALI) REV 01

ID Task Name Duration Start Finish % Complete % Schedule August 2017 September 2017
20170821 20170821 26 31 5 10 15 20 25 30 4 9 14 19
1 PROPOSED ADDITIONAL WORKS TO IMMEDIATE 41 days Mon 7/8/17 Sat 16/9/17 12% 31%
REPAIR EMBANKMENT SLOPE FAILURE AT KM
107+100 (B) ALONG CIKOPO - PALIMANAN
HIGHWAY (CIPALI)
2 Documentation 7 days Mon 7/8/17 Sun 13/8/17 70% 100%
3 Preparation work programmed, Org Chart. Method 7 days Mon 7/8/17 Sun 13/8/17 70% 100%
Statement. Work Permit. Inventory List. Precom
Meeting
4 Mobilisation 33 days Mon 14/8/17 Fri 15/9/17 0% 29%
5 Machineries& Team 2 days Mon 14/8/17 Tue 15/8/17 0% 100%
6 Setting Out, TMP, Documentation (Daily Report) 33 days Mon 14/8/17 Fri 15/9/17 0% 24%
7 Earthwork 8 days Mon 14/8/17 Mon 21/8/17 56% 100%
8 Site Clearing 3 days Mon 14/8/17 Wed 16/8/17 50% 100%
9 Excavation of Earth 1 day Thu 17/8/17 Thu 17/8/17 0% 100%
10 Transport and Disposal of excavated materials 1 day Fri 18/8/17 Fri 18/8/17 0% 100%
11 Borron material 3 days Sat 19/8/17 Mon 21/8/17 100% 100%
12 Pilling Work 14 days Tue 22/8/17 Mon 4/9/17 0% 0%
13 Supply and Install Concrete Mini Pile 25 cm x 25 9 days Tue 22/8/17 Wed 30/8/17 0% 0%
cm, Length : 6 m, 75 cm spacing
14 Capping beam mini pile include Reinforcing steel 5 days Thu 31/8/17 Mon 4/9/17 0% 0%
bars (350 mm W x 500 mm H)
15 Drainage 10 days Tue 5/9/17 Thu 14/9/17 0% 0%
16 Supply and apply Interceptor drain by using stone 3 days Tue 5/9/17 Thu 7/9/17 0% 0%
masonry and blinding stone include finishing
17 (CHUTE
Ditch DRAIN)
Plain concrete pipe 1/2 Ø400 include sand 3 days Fri 8/9/17 Sun 10/9/17 0% 0%
backfill and mortared ruber (DS14)
18 Ditch Plain concrete pipe 1/2 Ø200 include sand 3 days Fri 8/9/17 Sun 10/9/17 0% 0%
backfill and mortared ruber (ROAD SIDE DRAIN)
19 Eart Drain 2 days Mon 11/9/17 Tue 12/9/17 0% 0%
20 Box Control size 2.6 m x 1 m x 1.350 m with brick 2 days Wed 13/9/17 Thu 14/9/17 0% 0%
wall and sand backfill, include finishing
21 Pipe pvc 6"include fitting 1 day Thu 14/9/17 Thu 14/9/17 0% 0%
22 Structure Works 2 days Tue 12/9/17 Wed 13/9/17 0% 0%
23 Concrete surface with wiremesh M6 as per 2 days Tue 12/9/17 Wed 13/9/17 0% 0%
specifications (CONCRETE COVER)
24 Guardrail Works 33 days Mon 14/8/17 Fri 15/9/17 25% 50%
25 Remove, dismantle guardrail 1 day Mon 14/8/17 Mon 14/8/17 100% 100%
26 Remove and dispose off damage existing wire 1 day Sat 19/8/17 Sat 19/8/17 0% 100%
fance
27 Supply and install fence ROW Type B 1 day Fri 15/9/17 Fri 15/9/17 0% 0%
28 Reinstall of existing guardrail 1 day Mon 11/9/17 Mon 11/9/17 0% 0%
29 Solid Sodding 2 days Thu 14/9/17 Fri 15/9/17 0% 0%
30 Solid Sodding 2 days Thu 14/9/17 Fri 15/9/17 0% 0%
31 Demobilisation 1 day Sat 16/9/17 Sat 16/9/17 0% 0%
32 Machineries& Team 1 day Sat 16/9/17 Sat 16/9/17 0% 0%

PROPOSED ADDITIONAL WORKS TO IMMEDIATE REPAIR EMBA Task Summary Manual Task Manual Summary External Tasks
SLOPE FAILURE AT KM 107+100 (B) ALONG CIKOPO - PALIMAN
HIGHWAY (CIPALI)
Critical Task Inactive Milestone Duration-only Start-only External Milestone
Milestone Inactive Summary Manual Summary Rollup Finish-only Progress