ID Task Name Duration Start May Finish June July August September October Novembe

21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5
W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W
1 Design & Build s Shed for Agriclture 112 days Mon 5/29/23 Tue 10/31/23
training and wortk at the Hydroponic
Garden @ IMH
2 Preliminaries 100 days Mon 6/5/23 Fri 10/20/23
3 Letter of Award 0 days Mon 6/5/23 Mon 6/5/23 6/5
4 Bonds & Insurances 14 days Tue 6/6/23 Fri 6/23/23
5 Permits to Work 21 days Mon 7/24/23 Mon 8/21/23
6 Design, Authority submission, shop 60 days Tue 6/6/23 Mon 8/28/23
drawing and material submission
7 Awarding PE, Consultant, contractors 21 days Wed 6/7/23 Fri 7/14/23 Awarding
8 Design drawing and submission 60 days Wed 6/14/23 Tue 9/5/23 Design by appointed PE
9 Pre-con survey 7 days Mon 6/19/23 Tue 6/27/23
10 Underground services detector 2 days Wed 6/21/23 Thu 6/22/23 SIte Undergroung services detection
11 Instructmentation 2 days Fri 6/23/23 Mon 6/26/23 BMC marker
12 Land survey making 2 days Fri 6/23/23 Mon 6/26/23 BMC marker
13 Level survey & Site Boundry 2 days Tue 6/27/23 Wed 6/28/23
14 Hoarding of site boundary 5 days Thu 6/29/23 Wed 7/5/23
15 Signboard & site office 3 days Thu 7/6/23 Mon 7/10/23
16 Builder's Work 80 days Tue 7/11/23 Mon 10/30/23 Waiting
17 Design submitted & approved by Authories1 day Wed 8/16/23 Wed 8/16/23 Authories Approved
18 Steel column prepareation
19 Purchasing approved material 3 days Wed 8/16/23 Fri 8/18/23 Off site Welding work
20 Cutting & Welding refer to approved 10 days Mon 8/21/23 Fri 9/1/23 Welding work
drawing
21 Delivery to site 0 days Mon 9/4/23 Mon 9/4/23 9/4
22 Site Work
23 Installation of Steel Column 7 days Tue 9/5/23 Wed 9/13/23 Welding work
24 Grubbibing & soil disposal 3 days Thu 8/17/23 Mon 8/21/23
25 Laying hardcore & compaction 4 days Tue 8/22/23 Fri 8/25/23 10 Tons roller
26 Laying of BRC & Inspection by RTO 7 days Mon 8/28/23 Tue 9/5/23
27 Surveyor marking Column position 0 days Mon 8/28/23 Mon 8/28/23 8/28
28 Installation of J-Bolt for steel column 5 days Tue 8/29/23 Mon 9/4/23 Welding work
29 Surveyor column position confirmation0 days Tue 8/29/23 Tue 8/29/23 8/29
30 Installation of Steel Column 7 days Tue 9/5/23 Wed 9/13/23 Welding work
31 Column position by Inspection by RTO 2 days Thu 9/14/23 Fri 9/15/23 RTO Inspection
32 Concreting 0 days Mon 9/18/23 Mon 9/18/23 9/18
33 Hardening on concrete surface 0 days Tue 9/19/23 Tue 9/19/23 9/19
34 Roof Installation 14 days Wed 9/20/23 Mon 10/9/23
35 M&E Work 31 days Mon 8/28/23 Mon 10/9/23
36 Laying pumbing pipe line (1st fix) 4 days Mon 8/28/23 Thu 8/31/23
37 Laying Electrical pipe line (1st fix) 4 days Fri 9/1/23 Wed 9/6/23
38 1st Fix T&C 0 days Mon 9/25/23 Mon 9/25/23 9/25
39 M&E 2nd fix 3 days Tue 9/26/23 Thu 9/28/23
40 M&E 2nd fix T&C 0 days Fri 9/29/23 Fri 9/29/23 9/29
41 Completion of work 14 days Tue 10/10/23 Fri 10/27/23

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Design & Build a shud for Split External Tasks Inactive Summary Manual Summary Progress
Date: 24/05/2023 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Name Duration Start May Finish June July August September October Novembe
21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5
W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W
42 House keeping 4 days Wed 10/11/23Mon 10/16/23
43 RI Inspection 0 days Tue 10/17/23 Tue 10/17/23 10/17
44 TOP 0 days Tue 10/24/23 Tue 10/24/23 10/24
45 Handover 0 days Tue 10/31/23 Tue 10/31/23 10/31

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Design & Build a shud for Split External Tasks Inactive Summary Manual Summary Progress
Date: 24/05/2023 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2