Program for Mound walkway and Perimeter Path - Structural Steelworks

Zayed National Museum


ID Task Name Duration Start Finish Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12
1 Receipt of Drawing & design document 0 days Mon 6/13/22 Mon 6/13/22 6/13

2 Embeds 59.56 days Mon 6/13/22 Wed 8/24/22

3 Connection design & Shop drawings for embeds 21 days Mon 6/13/22 Thu 7/7/22

4 Approval of design & shop drawings for embeds 17 days Tue 6/21/22 Thu 7/14/22 ST-JV

5 MAR submittal for embeds 3 days Thu 7/14/22 Mon 7/18/22

6 MAR Approval for embeds 7 days Mon 7/18/22 Wed 7/27/22 ST-JV

7 Materials procurement for Embeds 7 days Wed 7/27/22 Thu 8/4/22

8 Fabrication of emebeds 10 days Thu 8/4/22 Wed 8/17/22

9 Galvanizing of embeds 4 days Wed 8/17/22 Mon 8/22/22

10 Delivery to Site 2 days Mon 8/22/22 Wed 8/24/22

11 Walkway- Primary structure 193.67 days Mon 6/13/22 Mon 2/6/23

12 Connection design 72 days Mon 6/13/22 Thu 9/8/22

13 Approval of design 68 days Fri 6/24/22 Mon 9/26/22 ST-JV

14 Moelling & GA Drawing 68 days Tue 6/28/22 Tue 9/20/22

15 Approval of GA drawing 68 days Tue 7/5/22 Wed 10/5/22 ST-JV

16 MAR submittal 14 days Fri 6/24/22 Tue 7/12/22

17 MAR Approval 7 days Tue 7/12/22 Thu 7/21/22 ST-JV

18 Materials procurement 18 days Thu 7/21/22 Fri 8/12/22

19 Fabrication 100 days Fri 8/12/22 Wed 12/14/22

20 Painting 110 days Thu 8/25/22 Sat 1/7/23

21 MIR at our workshop 110 days Fri 9/2/22 Mon 1/16/23

22 MIR approval 110 days Thu 9/8/22 Mon 2/6/23 ST-JV

23 Delivery to site 110 days Thu 9/15/22 Sat 1/28/23

24 Site activities & Installation 142 days Thu 9/15/22 Thu 3/9/23

25 Access for site installation 0 days Thu 9/15/22 Thu 9/15/22 9/15

26 Internal logistics at site 100 days Thu 9/15/22 Mon 1/16/23

27 Scaccolding / Acces for site intallation 120 days Fri 9/16/22 Tue 2/28/23 ST-JV

28 Installation 135 days Fri 9/23/22 Thu 3/9/23

Project: ZNM Walkway program R01 Task Progress Summary External Tasks Deadline
Date: Thu 6/16/22 Split Milestone Project Summary External Milestone