ID Task Task Name Duration Start Finish Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Ha
Mode O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
1 NaCN FACILITY - CORNERSTONE ENERGY PARK - 770.88 days Thu 11/4/21 Thu 10/17/24
LOUISIANA/USA
2 MILESTONES 770.88 days Thu 11/4/21 Thu 10/17/24
3 KICK-OFF MEETING (CONCEPTUAL DESIGN) - N&A x UNIGEL
0.88 days Thu 11/4/21 Thu 11/4/21
4 APPROVAL OF CONCEPTUAL DESIGN 0.88 days Mon 1/31/22 Mon 1/31/22
5 AWARD BASIC DESIGN + FEED 0.88 days Mon 5/23/22 Mon 5/23/22
6 KICK-OFF MEETING (BASIC DESIGN + FEED) - N&A x 0.88 days Thu 6/2/22 Thu 6/2/22
UNIGEL/CORNERSTONE
7 NECESSARY INFORMATION TO START ENGINEERING 33 days Tue 7/5/22 Fri 8/19/22
15 CRITICAL MILESTONES 589 days Fri 7/15/22 Thu 10/17/24
16 PROCUREMENT PLAN (PACKAGES DEFINITION) 0 days Fri 7/15/22 Fri 7/15/22 7/15
17 BASIC (RFQ) COMPLETED 0 days Mon 9/12/22 Mon 9/12/22 9/12
18 RECEIPT VENDORS PROPOSAL 0 days Mon 10/10/22 Mon 10/10/22 10/10
19 START PROCUREMENT (Long Lead Items) 0 days Mon 9/12/22 Mon 9/12/22 9/12
20 FEED COMPLETION 0 days Thu 1/5/23 Thu 1/5/23 1/5
21 AWARD FID (FINAL INVESTMENT DECISION) 0 days Thu 1/5/23 Thu 1/5/23 1/5
22 DETAILED ENGINEERING COMPLETED 0 days Thu 8/17/23 Thu 8/17/23 8/17
23 CONSTRUCTION PERMITING 0 days Thu 8/24/23 Thu 8/24/23 8/24
24 CONSTRUCTION START 0 days Thu 8/24/23 Thu 8/24/23 8/24
25 MECHANICAL COMPLETION 0 days Tue 9/17/24 Tue 9/17/24 9/17
26 COMMISSIONING 0 days Thu 10/17/24 Thu 10/17/24 10/17
27 START UP 0 days Thu 10/17/24 Thu 10/17/24 10/17
28 ENGINEERING AND MANAGEMENT 628 days Tue 5/24/22 Thu 10/17/24
29 PERMITTING 165 days Fri 1/6/23 Thu 8/24/23
30 LOCAL CONSTRUCTION AND PARISH PERMITS 35 days Fri 1/6/23 Thu 2/23/23
31 ENVIROMENTAL PERMIT 130 days Fri 2/24/23 Thu 8/24/23
32 FEED - ISBL & OSBL 163 days Tue 5/24/22 Thu 1/5/23
33 PROJECT MANAGEMENT / TECHNICAL COORDINATION
157.13 days Tue 5/24/22 Thu 12/29/22
35 BASIC DESIGN - 30% GATE REVIEW 39 days Tue 6/28/22 Mon 8/22/22
67 HAZOP 1 day Tue 9/27/22 Tue 9/27/22
69 FEED PROJECT - 60% GATE REVIEW 56 days Fri 8/19/22 Fri 11/4/22
108 FEED PROJECT - GATE IFA - ISSUED FOR APPROVAL 60 days Fri 10/7/22 Thu 12/29/22
147 FEED PROJECT - FINAL PURPOSE 5 days Fri 12/30/22 Thu 1/5/23
149 DETAILED ENGINEERING 160 days Fri 1/6/23 Thu 8/17/23
150 CONSTRUCTION MANAGEMENT/ OWNERS 200 days Fri 1/12/24 Thu 10/17/24
ENGINEERING TEAM
151 PROCUREMENT, FABRICATION & INSTALLATION 278 days Thu 8/24/23 Tue 9/17/24
152 ISBL 263 days Thu 9/14/23 Tue 9/17/24
153 CIVIL CONSTRUCTION 180 edays Thu 9/14/23 Tue 3/12/24
154 STEEL STRUCTURE 150 edays Sun 12/3/23 Wed 5/1/24
155 MECHANICAL EQUIPMENT 200 edays Fri 2/2/24 Tue 8/20/24
156 PIPING AND ACESSORIES 200 edays Fri 3/1/24 Tue 9/17/24
157 ELECTRICAL EQUIPMENT AND MATERIALS 120 edays Mon 5/20/24 Tue 9/17/24
158 INSTRUMENTATION & AUTOMATION EQUIPMENT 120 edays Mon 5/20/24 Tue 9/17/24
159 OSBL 236 days Thu 8/24/23 Fri 7/19/24
160 CIVIL CONSTRUCTION 180 edays Thu 8/24/23 Tue 2/20/24
161 STEEL STRUCTURE 150 edays Tue 10/3/23 Fri 3/1/24
162 MECHANICAL EQUIPMENT 200 edays Tue 12/5/23 Sat 6/22/24
163 PIPING AND ACESSORIES 200 edays Mon 1/1/24 Fri 7/19/24
164 ELECTRICAL EQUIPMENT AND MATERIALS 120 edays Thu 3/21/24 Fri 7/19/24
165 INSTRUMENTATION & AUTOMATION EQUIPMENT 120 edays Thu 3/21/24 Fri 7/19/24
166 COMISSIONING 64 days Fri 7/19/24 Thu 10/17/24
167 ISBL 22 days Tue 9/17/24 Thu 10/17/24
169 OSBL 20 days Fri 7/19/24 Sun 8/18/24