ID Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
0 EMBROIDED FUTURE AVENUE 180 days Wed Tue 21/05/24
(PTY) LTD, P. O. BOX 29, 13/09/23
MMATHETHE
1 THE WORKS CONTRACT FOR 180 days Wed 13/09/23 Tue 21/05/24
CONSTRUCTION OF
CLASSROOM BLOCK AT
MOLETE PRIMARY SCHOOL IN
THE GOODHOPE DISTRICT FOR
BOTSWANA
COMMUNICATIONS
REGULATORY AUTHORITY,
TENDER NO:
BOCRA/ST/001/2023.2024
2 Substructure 54 days Wed 13/09/23 Mon 27/11/23
3 Mobilisation 10 days Wed 13/09/23 Tue 26/09/23 Site foreman,Van,Managing Director
4 Site Clearance 5 days Wed 27/09/23 Tue 03/10/23 Labourers,Truck,Van,Site foreman,Bricklayer,TLB
5 Setting Out 1 day Wed 04/10/23 Wed 04/10/23 Bricklayer,Labourers,Site foreman
6 Trench Excavations 9 days Thu 05/10/23 Tue 17/10/23 Bricklayer,Labourers,Trench Compactor,TLB

7 Compaction Trenches 3 days Wed 18/10/23 Fri 20/10/23


8 Reinforcement & Concrete 5 days Mon 23/10/23 Fri 27/10/23 Bricklayer,Labourers,Plate Compactor
Footing
9 Brickwork Substructure 11 days Mon 30/10/23 Mon 13/11/23 Bricklayer,Labourers,Site foreman

10 Backfill and Compaction 5 days Tue 14/11/23 Mon 20/11/23 Bricklayer,Labourers,Plate Compactor

11 Casting of Floor Slab 5 days Tue 21/11/23 Mon 27/11/23 Bricklayer,Labourers


12 Superstructure 118 days Tue 28/11/23 Thu 09/05/24
13 Superstructure Brickwork 34 days Tue 28/11/23 Fri 12/01/24 Bricklayer,Labourers,Scaffolding
and Frames
14 Ring Beam, Shuttering and 4 days Mon 01/01/24 Thu 04/01/24 Bricklayer,Labourers
Casting
15 Roof Structure and 15 days Mon 15/01/24 Fri 02/02/24 Carpenter,Labourers,Scaffolding
Covering
16 Electrical works 8 days Mon 05/02/24 Wed 14/02/24 Electrician,Labourers,Scaffolding
17 Plastering 17 days Thu 15/02/24 Fri 08/03/24 Bricklayer,Labourers,Scaffolding
18 Ceilings 15 days Mon 11/03/24 Fri 29/03/24 Carpenter,Labourers
19 Carpentry and Joinery 8 days Mon 11/03/24 Wed 20/03/24 Carpenter,Labourers
20 Floor covering 15 days Mon 01/04/24 Fri 19/04/24 Tiller,Labourers
21 Painting works 14 days Mon 22/04/24 Thu 09/05/24 Carpenter,Labourers
22 Glazing 6 days Mon 22/04/24 Mon 29/04/24 Bricklayer,Labourers
23 External Works 16 days Tue 30/04/24 Tue 21/05/24
24 External Works 6 days Tue 30/04/24 Tue 07/05/24 Bricklayer,Labourers,Plumber
25 Site Clearance 7 days Fri 10/05/24 Mon 20/05/24 Carpenter,Labourers,Plumber,Van
26 Handing Over 1 day Tue 21/05/24 Tue 21/05/24 Site foreman,Managing Director

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: EMBROIDED FUTURE A
Milestone Inactive Summary Start-only Critical
Date: Wed 27/09/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress