JAN 06 JAN 13 JAN 20 JAN 27 FEB 03 FEB 10 FEB 17 FEB 24 MAR 03 MAR 10 MAR 17 MAR 24 MAR 31 APR 07 APR

24 MAR 03 MAR 10 MAR 17 MAR 24 MAR 31 APR 07 APR 14 APR 21 APR 28


ID Task Name Duration Start Finish
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

1 Warehouse 73 days Mon 19/01/14 Wed 19/04/24

2 Site establishment 3 days Mon 19/01/14 Wed 19/01/16

3 Site clearance 3 days Thu 19/01/17 Mon 19/01/21

4 Set out building 2 days Tue 19/01/22 Wed 19/01/23

5 Foundations 20 days Thu 19/01/24 Wed 19/02/20

6 Foundation Brickwork 3 days Thu 19/02/21 Mon 19/02/25

7 Backfill floor area and compact 5 days Tue 19/02/26 Mon 19/03/04

8 Erect structural steel 15 days Tue 19/03/05 Mon 19/03/25

9 Roof sheeting 8 days Tue 19/03/26 Thu 19/04/04

10 Superstructure brickwork 10 days Tue 19/03/26 Mon 19/04/08

11 Fit aluminium windows and louvres 3 days Mon 19/04/08 Wed 19/04/10

12 Plumbing First Fix 1 day Fri 19/04/05 Fri 19/04/05

13 Prep and cast s/bed to warehouse 2 days Fri 19/04/05 Mon 19/04/08

14 Plaster and tiling to splashback wall of toilet area 3 days Tue 19/04/09 Thu 19/04/11

15 Plumbing final 4 days Wed 19/04/10 Mon 19/04/15

16 Painting internally 4 days Tue 19/04/09 Fri 19/04/12

17 Plaster external 8 days Tue 19/04/09 Thu 19/04/18

18 Paint externally 8 days Mon 19/04/15 Wed 19/04/24

19 Civil works 17 days Tue 19/04/02 Wed 19/04/24

20

21 Refuse room 20 days Thu 19/02/21 Wed 19/03/20

22 Set out room 1 day Thu 19/02/21 Thu 19/02/21

23 Excavate footings 2 days Fri 19/02/22 Mon 19/02/25

24 Cast footings 1 day Tue 19/02/26 Tue 19/02/26

25 Foundation brickwork 1 day Wed 19/02/27 Wed 19/02/27

26 Cavity fill 1 day Thu 19/02/28 Thu 19/02/28

27 Backfill floor area and compact 1 day Fri 19/03/01 Fri 19/03/01

28 Fit floor drain 1 day Mon 19/03/04 Mon 19/03/04

29 Cast floor 1 day Tue 19/03/05 Tue 19/03/05

30 Super structure brickwork 3 days Wed 19/03/06 Fri 19/03/08

31 Roof sheeting 2 days Mon 19/03/11 Tue 19/03/12

32 Plaster internal and externally 4 days Wed 19/03/13 Mon 19/03/18

33 Fit gate 1 day Tue 19/03/19 Tue 19/03/19

34 Paint internally and externally 1 day Wed 19/03/20 Wed 19/03/20