TWO WEEK A HEAD

WEEKLY 19
ID Task Task Name Duration Start Finish Jul '18 Aug '18 Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19
Mode 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05
4 Site management, Site Office, dll (sesuai BQ) 286 days Sun 15/07/18 Tue 30/04/19
7 Pekerjaan Tanah dan Pondasi 56 days Mon 10/09/18 Sun 04/11/18
8 Indikator Pile 14 days Sun 15/07/18 Sat 28/07/18
9 Test Pile/Loading test 16 days Sun 29/07/18 Mon 13/08/18
10 Pondasi Pancang (diesel + drop hammer) 61 days Tue 14/08/18 Sun 14/10/18
11 Pekerjaan Pondasi Pile Cap 56 days Mon 17/09/18 Sun 11/11/18
12 Pekerjaan Retaining Wall (dpt) 63 days Mon 17/09/18 Sun 18/11/18
13 Pekerjaan Tie Beam 59 days Fri 21/09/18 Sun 18/11/18
16 Pekerjaan Kolom 63 days Mon 17/09/18 Sun 18/11/18
19 Pekerjaan kolom mezzanine 48 days Sun 04/11/18 Fri 21/12/18
20 Pekerjaan balok mezzanine 50 days Sun 02/12/18 Wed 23/01/19
21 Pekerjaan slab mezzanine 50 days Sun 02/12/18 Wed 23/01/19
24 Pekerjaan kolom mezzanine 48 days Sun 11/11/18 Sun 30/12/18
29 Pekerjaan kolom mezzanine 48 days Sun 04/11/18 Fri 21/12/18
30 Pekerjaan balok mezzanine 50 days Sun 02/12/18 Wed 23/01/19
31 Pekerjaan slab mezzanine 50 days Sun 02/12/18 Wed 23/01/19
43 Steel Structure Works+Canopy 94 days Sun 25/11/18 Fri 01/03/19
55 Mushola & Ruang Tunggu Sopir 148 days Thu 01/11/18 Sun 31/03/19
56 Ruang Panel Travo 148 days Thu 01/11/18 Sun 31/03/19
57 Ruang Genset 148 days Thu 01/11/18 Sun 31/03/19
58 Ruang Pompa & Ground Water Tank 148 days Thu 01/11/18 Sun 31/03/19
59 PLN 148 days Thu 01/11/18 Sun 31/03/19
60 Pos Jaga 148 days Thu 01/11/18 Sun 31/03/19
62 Pekerjaan Pagar BRC 120 days Mon 12/11/18 Thu 14/03/19
63 Pekerjaan Pagar Panel 120 days Mon 19/11/18 Thu 21/03/19
65 Saluran U-ditch tertutup 600/600 (As 1 & 17 / A - 100 days Mon 19/11/18 Fri 01/03/19
J)

66 Saluran U-dith tertutup 1000/1200 (depan) 100 days Mon 19/11/18 Fri 01/03/19
67 Saluran Buis Beton Ø ID 800 mm 100 days Mon 19/11/18 Fri 01/03/19
69 Lapis Perkerasan (Loading Dock) 150 days Mon 12/11/18 Sat 13/04/19
84 PEKERJAAN REMEASURED RETAINING WALL 90 days Mon 12/11/18 Tue 12/02/19
96 Pekerjaan Tanah dan Pondasi 56 days Mon 05/11/18 Wed 02/01/19
97 Indikator Pile 14 days Sat 15/09/18 Fri 28/09/18
98 Test Pile/Loading test 16 days Sat 29/09/18 Sun 14/10/18
99 Pondasi Pancang (diesel + drop hammer) 75 days Mon 15/10/18 Sun 30/12/18
100 Pekerjaan Pondasi Pile Cap 68 days Mon 12/11/18 Mon 21/01/19
101 Pekerjaan Retaining Wall (dpt) 80 days Mon 12/11/18 Sat 02/02/19
102 Pekerjaan Tie Beam 70 days Sun 18/11/18 Tue 29/01/19
105 Pekerjaan Kolom 70 days Sun 18/11/18 Tue 29/01/19

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
PROJECT WH 14
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
DELTA SILICONE 3- CIKARANG
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress