SCHEDULE & CONSTRUCTION METHOD

PROJECT PT. SENOPATI SCHEDULE


CONSTRUCTION WORK

NEW WH (SENOPATI)
1. Dismantling Existing Buildings
2. Civil Work
3. Steel Structure Work
1170

4. Architectural & Utility


EXISTING WH NEW WH 5. Infrastructure
6. Mechanical, Electrical, & Plumbing
(MEP)
PROJECT PT. SENOPATI SCHEDULE
TIMELINE SCHEDULE

CONSTRUCTION WORK 8 MONTH


Month 0 – Month 1,5 Month 1,5 – Month 6 Month 6 – Month 8 Month 5 – Month 8

PREPARATION & DISMANTLING STRUCTURE WORK ARCHITECTURAL WORK MEP, & INFRASTRUCTURE
EXISTING BUILDING

• Submit Propose Design & • Piling Work & Fill For to MEP
• Internal Wall (Brickwall & • Install Hydrant
Tender Process Slab Finishes)
• Permit IMB, Environmental • Foundation Work • Install Grounding & Lighting
• Expose Concrete Protector
Coordination • Column Pedestal • Floor Finish (Liquid Harderner)
• Approval Master Schedule & • Concrete Slab 1st Floor • Install Electrical
• External & Internal Door Infrastructure
Construction Method • Staircase • Painting Wall
• Kick off Meeting • Steel Structure • Drainage
• Stair & Railing • Decker + Caseiron
• Preparation Work • Roofing Works • Bollard & Dockleveler
• Dismantling Existing • Fascia & Metal Cladding • Wheelstoper
• UTILITY (GWT & PUMP ROOM) • Repair Paving Existing
Buildings • Canopy

M0
M1 M1 M2
M1 M3 M4 M5 M6 M7 M8

PROPOSE DESIGN

DISMANTLING EXISTING BUILDINGS STRUCTURE WORK ARCHITECTURE WORK


M E P & INFRASTRUCTURE WORKS
PROJECT PT. SENOPATI
SQUENCE OF WORKS

2 4

3
6
1

SQUENCE OF WORKS STRUCTURE

Preparation Work & Dismantling Existing Buildings = 0 Month - 1,5st Month

1. Foundation Work (Pilling, Pile Cap, Tie Beam,


& Retaining Wall) = 1,5st Month - 4th Month
2. Structure Mezzanine Floor = 3,5th Month - 4,5th Month
3. Column Pedestal = 3,5th Month - 4,5th Month
4. Steel Structure = 4th Month - 5th Month
5. Roofing Works = 4,5th Month - 5,5th Month
6. Slab Structure 1st Floor = 5th Month - 6th Month